During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.
|
2020 |
2021 |
2022 |
||||
|---|---|---|---|---|---|---|
|
Costs incurred to date |
$380,000 | $847,770 | $1,069,000 | |||
|
Estimated costs to complete |
620,000 | 253,230 | –0– | |||
|
Billings to date |
302,000 | 896,000 | 1,610,000 | |||
|
Collections to date |
272,000 | 812,000 | 1,418,000 |
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
|
Gross profit recognized in 2020 |
$enter a dollar amount |
|
|---|---|---|
|
Gross profit recognized in 2021 |
$enter a dollar amount |
|
|
Gross profit recognized in 2022 |
$enter a dollar amount |
Answer
|
2020 |
2021 |
2022 |
|
|
Gross Profits (Loss) |
$231,800 |
$160,130 |
$149,070 |
|
Working |
2020 |
2021 |
2022 |
|
|
A |
Contract Price |
$1,610,000 |
$1,610,000 |
$1,610,000 |
|
B |
Cost Incurred to Date |
$380,000 |
$847,770 |
$1,069,000 |
|
C |
Estimated cost yet to be incurred to complete the contract |
$620,000 |
$253,230 |
$0 |
|
D = B+C |
Total Cost |
$1,000,000 |
$1,101,000 |
$1,069,000 |
|
E = (B/D) x 100 |
% of Completion |
38.00% |
77.00% |
100.00% |
|
F = A x E |
Revenue to date |
$611,800 |
$1,239,700 |
$1,610,000 |
|
G |
Revenue of Previous year |
$0 |
$611,800 |
$1,239,700 |
|
H = F - G |
Net Revenue this year |
$611,800 |
$627,900 |
$370,300 |
|
I (=B) |
Cost to date |
$380,000 |
$847,770 |
$1,069,000 |
|
J |
Cost to date of previous year |
$0 |
$380,000 |
$847,770 |
|
K = I - J |
Net Cost for the year |
$380,000 |
$467,770 |
$221,230 |
|
L = H - K |
Gross Profits |
$231,800 |
$160,130 |
$149,070 |
During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Sweet Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $380,000 $847,770 $1,069,000 Estimated costs to complete 620,000 253,230 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 272,000 812,000 1,418,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Bramble Company started a construction job with a
contract price of $1,610,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$434,300
$859,560
$1,073,000
Estimated costs to complete
575,700
242,440
–0–
Billings to date
301,000
897,000
1,610,000
Collections to date
271,000
817,000
1,428,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Pharoah Company started a construction job with a
contract price of $1,620,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$373,700
$902,000
$1,070,000
Estimated costs to complete
636,300
198,000
–0–
Billings to date
303,000
899,000
1,620,000
Collections to date
273,000
807,000
1,412,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amountenter...
During 2020, Stellar Company started a construction job with a
contract price of $1,620,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$373,700
$749,360
$1,070,000
Estimated costs to complete
636,300
352,640
–0–
Billings to date
302,000
907,000
1,620,000
Collections to date
268,000
815,000
1,425,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amount...
During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Ivanhoe Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $396,000 $806,600 $1,080,000 Estimated costs to complete 594,000 283,400 -0- Billings to date 301,000 268,000 892,000 816,000 1,590,000 1,427,000 Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Pearl Company started a construction job with a
contract price of $1,590,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$396,000
$806,600
$1,080,000
Estimated costs to complete
594,000
283,400
–0–
Billings to date
301,000
892,000
1,590,000
Collections to date
268,000
816,000
1,427,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amount...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...