Cash flow year 0=-2000000
Cash flow Year 1=600000
Cash Flow Year 2=850000
Cash Flow Year 3=900000
Cash Flow Year 4 =700000
Pay Back Period Years before recovery + Cost not covered in that
year/ Cash flow for that year =3 +
(600000+850000+900000-2000000)/900000 =3.39 years
IRR using financial calculator
CF0=-2000000,CF1=600000;CF2 =850000;CF3=900000;CF4=700000 CPT IRR
=7.97%
NPV =PV of Cash Flows-Investment
=600000/1.10+850000/1.1^2+900000/1.1^3+700000/1.1^4-2000000
=402226.62
PI =1+NPV/Investment =1+402226.62/2000000=1.20
Calculate the Payback Period, IRR, NPV, and PI if cash flows are as follows: -$2M; $600K;...
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85.000 and expected free cash flows of $20,000 at the end of each year for 7 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
(Payback period, NPV, PI, and IRR calculations )You are considering a project with an initial cash outlay of 90,000 and expected free cash flows of 30,000 at the end of each year for 6 years. The required rate of return for this project is 8 percent. a. What is the project's payback period? b. What is the project's NPV ? c. What is the project's PI ? d. What is the project's IRR ?
(Payback period, NPV, PI, and IRR calculations) You are considering a project with an initial cash outlay of $85 comma 000 and expected free cash flows of $30 comma 000 at the end of each year for 6 years. The required rate of return for this project is 6 percent. a. What is the project's payback period? b. What is the project's NPV? c. What is the project's PI? d. What is the project's IRR?
You must know all the cash flows of an investment project to compute its NPV, IRR, PI and payback period OA NPV, PI, IRR ОВ. Ос. OD IRR, PI payback period and discount payback period NPV, IRR, PI payback period, and discount payback period IRR, PI and payback period NPV, IRR, PI and discount payback period OE. OF.
This assignment supports the following objectives: Calculate IRR, NPV and Payback Period Analyze the cash flows generated by mutually exclusive projects Formulate a recommendation using IRR, NPV and Payback Period as the criteria Background Suppose that your firm is considering the following two mutually exclusive projects. Both projects have the same initial cost of $312,500 and the resulting annual cash flows for the first five years are as shown in the table below: Year Alpha Beta 0 $ (312,500) $...
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 -$350,000 1 $100,000 2 $100,000 3 $100,000 5 $50,000 $50,000 NPV= IRRE Payback period= b) Should you accept or reject the project according to NPV and IRR?
Please show your steps! Question 1 a) What is the NPV, IRR, and payback period of a project with the following cash flows if WACC is 20%? Time: 0 -$350,000 1 $100,000 2 $100,000 3 $100,000 $100,000 A $50,000 $50,000 NPV= IRR= Payback period b) Should you accept or reject the project according to NPV and IRR?!
1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year Cash Flow Net Profit Depreciation 0 -$125,000 1 $22,000 $15,000 $10,000 2 $58,000 $43,000 $25,000 3 -$30,000 $24,000 $21,000 4 $35,000 $28,000 $18,000 5 $28,000 $20,000 $15,000 6 $60,000 ...
Calculate the payback period, ARR, IRR and NPV (at 12%) for two proposed four-year projects, B1 and B2, the cash flows (EBDIT) for which are as follows: Year 0 1 2 3 4 B1 -60,000 9,000 10,000 25,000 30,000 B2 -60,000 30,000 25,000 10,000 9,000 (Assume that straight-line depreciation is applicable and that there is no income tax.) Why are the NPV and IRR of project B2 superior to B1?