Question

An example of a contingent product is: Select one: O A. choosing between one of two manufacturing sites. O B. building a new
Two projects have the same initial cost. Project A has estimated cash flows of $1,000, $2,000, $3,000, $4,000 at the end of y
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

a) A contingent good is are a type of future goods where the acquisition of the goods by the seller depends upon certain contingencies that may or may not happen.

Option1 : Choosing between two manufacturing sites .. there is no condition as such in choosing between the two sites , one may chose either of them but no condition is mentioned as such.

Option2: Building a new manufacturing plant with an optional waste recycling is the right answer as the waste cycling plant comes into picture only if there is a waste generation from the facility.

Option3 : Adding manufacturing capacity to a plant has no condition embedded ie. it is implied that for a plant manufacturing capacity will be added automatically.

Option 4: None of the above is automatically incorrect.

b) For projects with high amount of cash flows in the early years of existence presents better NPV as the time increases the discounting factor increases and hence the PV of the future cash flows.

Project B has higher cash flows of $4000, $3000, $2000, $1000, in the first and the second year and hence will have the higher NPV than the project A which have flows such as $1000, $2000, $3000, $4000 which have higher amounts later in the life of the project.

Option A: Both have same NPV , which is not correct as we just concluded B have a higher NPV.

Option B: Project B .. is the right answer

Option C: Project A … Is not as we just explained.

Option D: Cannot be determined … we can make out about the NPV by just looking at the amounts and the timings of the cash flows.

Add a comment
Know the answer?
Add Answer to:
An example of a contingent product is: Select one: O A. choosing between one of two...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project A has cash flows of $4,000, $3,000, $0, and $3,000 for Years 1 to 4,...

    Project A has cash flows of $4,000, $3,000, $0, and $3,000 for Years 1 to 4, respectively. Project B has cash flows of $2,000, $3,000, $2,000, and $3,000 for Years 1 to 4, respectively. Which one of the following statements is correct assuming the discount rate is positive? (No calculations needed) Multiple Choice The cash flows for Project B are an annuity, but those of Project A are not. Both sets of cash flows have equal present values as of...

  • Decision Rules. Suppose your firm is choosing between two new product lines. One project has an...

    Decision Rules. Suppose your firm is choosing between two new product lines. One project has an initial investment of $450 million and offers annual cashflows of $160 million for 5 years. The other has an initial investment of $1,560 million and offers annual cashflows of $475 million for 5 years. Using the payback period, which project would you suggest? (2 points) If your cost of capital is estimated to be 7%, which project offers the higher NPV? (4 points) What...

  • Which one of the following statements correctly defines a time value of money relationship? Multiple Choice...

    Which one of the following statements correctly defines a time value of money relationship? Multiple Choice 2.5 points eBook • Time and future values are inversely related, all else held constant. Print References O Interest rates and time are positively related, all else held constant. O An increase in a positive discount rate increases the present value. O An increase in time increases the future value given a zero rate of interest. O Time and present value are inversely related,...

  • Suppose your firm would like to earn 10% yearly return from the following two investment projects...

    Suppose your firm would like to earn 10% yearly return from the following two investment projects of equal risk. Year (t) Cash flows from Project A (Ct) Cash flows from Project B (Ct) year        cash flow from project a           project b 0                       –$8,000                                     –$8,000 1                         $2,000                                     $4,000 2                      $3,000                                      $2,000 3                      $5,000                                    $2,500 4                       $1,000                                         $2,000 (a) If only one project can be accepted, based on the NPV method which one...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): a. What are the IRRs of the two​ projects? The IRR for project A is ______​%. ​(Round to one decimal​ place.) The IRR for project B is ______​%. ​(Round to one decimal​ place.) b. If your discount rate is 4.8 %​, what are the NPVs of the two​ projects? If your discount rate is 4.8%​, the NPV for project A...

  • Jurong Inc. has $50 million long-term debt. The balance sheet also shows the company has 5...

    Jurong Inc. has $50 million long-term debt. The balance sheet also shows the company has 5 million shares of common stock. The current share price is $20 per share, shareholders' required return is 12%, cost of debt is 4.5%, and the company's tax rate is 30%. Jurong Inc. is considering two mutually exclusive projects. The two projects have similar risk and the project cash flows are shown below. If the investment decision is made by choosing the project with the...

  • Suppose your firm would like to earn 10% yearly return from the following two investment projects...

    Suppose your firm would like to earn 10% yearly return from the following two investment projects of equal risk.(the table is attatched in the form of image) (a)​If only one project can be accepted, based on the NPV method which one should it be? Support your answer with calculations. ​​​​​​(9 marks) (b)​Suppose there is another four-year project (Project C) and its cash flows are as follows: ​ C0 = –$8,000 ​C1 = $2,000 ​C2 = $2,500 ​C3 = $2,000 ​C4...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table ($ milion); Project Year Year 2 Year o -$48 - $101 Year 3 $21 $50 Year 4 $14 $27 $20 $40 $62 Tes a What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the...

  • PO-20 ar to) I Question Help You are choosing between two projects. The cash flows for...

    PO-20 ar to) I Question Help You are choosing between two projects. The cash flows for the projects we given in the following table Project Year a. What are the IRR of the two projects? b. If your discount 52%. what are the NPV of the two projects? G. Why do IRR and NPV rank the two projects differently a. What are the Rs of the two projects? The IRR for project As Round to one decimal place)

  • needs to be dont like this excel sheet example all values must be filled in and...

    needs to be dont like this excel sheet example all values must be filled in and in an excel sheet with formulas. using the data procided all parameters in the excel table shown have to be calculated that excel sheet image is just an example and have to come up with the sams dable with the data procided in the first table Perform a financial analysis for a project where the projected costs and benefits are spread over five years...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT