| Cost of Good sold | $ 13,010 | ||
| Workings: | |||
| Morrow Corporation | |||
| Cost of goods manufactured | |||
| Beginning Inventory | $ 7,500 | ||
| Direct Materials | $ 11,700 | ||
| Add: | Direct Labor | $ 3,900 | |
| Add: | Manufacturing overheads applied | $ 5,900 | |
| (i) | Cost of goods manufactured | $ 29,000 | |
| (ii) | Completed units | 290 | |
| (i) / (ii) | Unit cost | $ 100 | |
| Total cost of Ending Finished goods Inventory: | = | (Units completed - Units sold) X Unit cost | |
| = | (290 - 135) X $100 | ||
| = | $ 15,500 | ||
| Schedule of Cost of Goods Sold | |||
| Finished Goods Inventory Beginning | $ - | ||
| Cost of goods manufactured | $ 29,000 | ||
| Cost of goods available for sale | $ 29,000 | ||
| Deduct: | Finished Goods Inventory Ending | $ -15,500 | |
| Unadjusted cost of goods sold | $ 13,500 | ||
| Less: | Overapplied Overheads | $ -490 | |
| Adjusted cost of goods sold | $ 13,010 | ||
Morrow Corporation had only one job in process during May—Job X322—and had no finished goods inventory...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X32Z Beginning balance $ 7,500 Charged to the job during May Direct materials $ 11,700 Direct labor $ 3,900 Manufacturing overhead applied $ 5,900 Units completed 290 Units in process at the end of May 0 Units sold during May 135 In May, overhead...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: $ 7,400 Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May $ $ $ 13,000 5,100 6,700 280 0 130 In May, overhead was overapplied...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X322 5,300 A A A Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May 5,600 2,300 4,300 125 A 55 In May, overhead was...
Morrow Corporation had only one job in process during May-Job X322-and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below. Job X322 $ 5,300 Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May $ $ $ 5,600 2,300 4,300 125 @ 55 In May, overhead...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job x32Z 5,100 $ $ Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May eu 8,200 2,100 4,100 100 0 45 In May, overhead was...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X32Z 6.000 $ $ Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May 9.000 3.000 5.000 200 80 In May, overhead was overapplied by...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X32Z 5,400 Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May ਬੀਬੀ ਬੀ ਸੀ 7,600 2,400 4,400 110 In May, overhead was overapplied by...
Morrow Corporation had only one job in process during May-Job X322—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X32Z S 5,700 $ Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May 9,000 2.700 4,700 170 0 75 In May, overhead was overapplied...
Morrow Corporation had only one job in process during May-Job X322-and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below: Job X322 $ 5,700 Beginning balance Charged to the job during May Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of May Units sold during May $ $ $ 9,000 2,700 4,700 170 0 75 In May, overhead...
Morrow Corporation had only one job in process during May—Job
X32Z—and had no finished goods inventory on May 1. Job X32Z was
started in April and finished during May. Data concerning that job
appear below