In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: |
I NEED HELP RESOLVING THE EMPTY 8 BOXES BELOW (4&5).

Answers
|
2016 |
2017 |
2018 |
|
|
Revenue |
$ 2,900,000.00 |
$ 3,822,164 |
$ 3,277,836 |
|
Gross Profit (Loss) |
$ 290,000.00 |
$ 100,000.00 |
$ (100,000.00) |
--Working
|
Working |
2016 |
2017 |
2018 |
|
|
A |
Contract Price |
$ 10,000,000.00 |
$ 10,000,000.00 |
$ 10,000,000.00 |
|
B |
Cost Incurred to Date |
$ 2,610,000.00 |
$ 6,460,000.00 |
$ 9,710,000.00 |
|
C |
Estimated cost yet to be incurred to complete the contract |
$ 6,390,000.00 |
$ 3,150,000.00 |
$ - |
|
D = B+C |
Total Cost |
$ 9,000,000.00 |
$ 9,610,000.00 |
$ 9,710,000.00 |
|
E = (B/D) x 100 |
% of Completion |
29.00% |
67.22% |
100.00% |
|
F = A x E |
Revenue to date |
$ 2,900,000.00 |
$ 6,722,164.41 |
$ 10,000,000.00 |
|
G |
Revenue of Previous year |
$ - |
$ 2,900,000.00 |
$ 6,722,164.41 |
|
H = F - G |
Net Revenue this year |
$ 2,900,000.00 |
$ 3,822,164.41 |
$ 3,277,835.59 |
|
I (=B) |
Cost to date |
$ 2,610,000.00 |
$ 6,460,000.00 |
$ 9,710,000.00 |
|
J |
Cost to date of previous year |
$ - |
$ 2,610,000.00 |
$ 6,460,000.00 |
|
K = I - J |
Net Cost for the year |
$ 2,610,000.00 |
$ 3,850,000.00 |
$ 3,250,000.00 |
|
L = A - D |
Estimated Gross Profit (Loss) |
$ 1,000,000.00 |
$ 390,000.00 |
$ 290,000.00 |
|
M |
Gross Profit (Loss) to be recognised |
$ 290,000.00 |
$ 100,000.00 |
$ (100,000.00) |
|
2016 |
2017 |
2018 |
|
|
Revenue |
$ 2,900,000.00 |
$ 3,160,038 |
$ 3,939,962 |
|
Gross Profit (Loss) |
$ 290,000.00 |
$ (950,000.00) |
$ 150,000.00 |
--Working
|
Working |
2016 |
2017 |
2018 |
|
|
A |
Contract Price |
$ 10,000,000.00 |
$ 10,000,000.00 |
$ 10,000,000.00 |
|
B |
Cost Incurred to Date |
$ 2,610,000.00 |
$ 6,460,000.00 |
$ 10,510,000.00 |
|
C |
Estimated cost yet to be incurred to complete the contract |
$ 6,390,000.00 |
$ 4,200,000.00 |
$ - |
|
D = B+C |
Total Cost |
$ 9,000,000.00 |
$ 10,660,000.00 |
$ 10,510,000.00 |
|
E = (B/D) x 100 |
% of Completion |
29.00% |
60.60% |
100.00% |
|
F = A x E |
Revenue to date |
$ 2,900,000.00 |
$ 6,060,037.52 |
$ 10,000,000.00 |
|
G |
Revenue of Previous year |
$ - |
$ 2,900,000.00 |
$ 6,060,037.52 |
|
H = F - G |
Net Revenue this year |
$ 2,900,000.00 |
$ 3,160,037.52 |
$ 3,939,962.48 |
|
I (=B) |
Cost to date |
$ 2,610,000.00 |
$ 6,460,000.00 |
$ 10,510,000.00 |
|
J |
Cost to date of previous year |
$ - |
$ 2,610,000.00 |
$ 6,460,000.00 |
|
K = I - J |
Net Cost for the year |
$ 2,610,000.00 |
$ 3,850,000.00 |
$ 4,050,000.00 |
|
L = A - D |
Estimated Gross Profit (Loss) |
$ 1,000,000.00 |
$ (660,000.00) |
$ (510,000.00) |
|
M |
Gross Profit (Loss) to be recognised |
$ 290,000.00 |
$ (950,000.00) |
$ 150,000.00 |
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....
In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County for S10,000,000. The road was completed in 2018. Information related to the contract is as follows: 2017 $2,610,000 S3,162,000 $2,230,800 2,028,000 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2016 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 6,390,000 0 Cash collections during the year Pioneer recognizes revenue over time according to percentage of completion. Calculate the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,044,000 5, 256,000 2,170,000 1,885,000 2022 2023 $2,628,000 $2,890, 800 2,628,000 2,502,0005, 328,000 2,600,0005,515,000 Westgate recognizes revenue over time according to percentage of completion....
In 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
Westgate recognizes revenue over time according to percentage of
completion.
Calculate the amount of revenue and gross profit (loss) to be
recognized in each of the three years assuming the following costs
incurred and costs to complete information. (Do not round
intermediate calculations and round your...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...