Question

In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

I NEED HELP RESOLVING THE EMPTY 8 BOXES BELOW (4&5).

4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers

  • Requirement 4

2016

2017

2018

Revenue

$                2,900,000.00

$               3,822,164

$                    3,277,836

Gross Profit (Loss)

$                   290,000.00

$                   100,000.00

$                     (100,000.00)

--Working

Working

2016

2017

2018

A

Contract Price

$             10,000,000.00

$             10,000,000.00

$                  10,000,000.00

B

Cost Incurred to Date

$                2,610,000.00

$               6,460,000.00

$                    9,710,000.00

C

Estimated cost yet to be incurred to complete the contract

$                6,390,000.00

$               3,150,000.00

$                                         -  

D = B+C

Total Cost

$                9,000,000.00

$               9,610,000.00

$                    9,710,000.00

E = (B/D) x 100

% of Completion

29.00%

67.22%

100.00%

F = A x E

Revenue to date

$                2,900,000.00

$               6,722,164.41

$                  10,000,000.00

G

Revenue of Previous year

$                                     -  

$               2,900,000.00

$                    6,722,164.41

H = F - G

Net Revenue this year

$                2,900,000.00

$               3,822,164.41

$                    3,277,835.59

I (=B)

Cost to date

$                2,610,000.00

$               6,460,000.00

$                   9,710,000.00

J

Cost to date of previous year

$                                     -  

$               2,610,000.00

$                    6,460,000.00

K = I - J

Net Cost for the year

$                2,610,000.00

$               3,850,000.00

$                    3,250,000.00

L = A - D

Estimated Gross Profit (Loss)

$                1,000,000.00

$                   390,000.00

$                        290,000.00

M

Gross Profit (Loss) to be recognised

$                   290,000.00

$                   100,000.00

$                     (100,000.00)

  • Requirement 5

2016

2017

2018

Revenue

$                2,900,000.00

$               3,160,038

$                    3,939,962

Gross Profit (Loss)

$                   290,000.00

$                 (950,000.00)

$                        150,000.00

--Working

Working

2016

2017

2018

A

Contract Price

$             10,000,000.00

$             10,000,000.00

$                  10,000,000.00

B

Cost Incurred to Date

$                2,610,000.00

$               6,460,000.00

$                  10,510,000.00

C

Estimated cost yet to be incurred to complete the contract

$                6,390,000.00

$               4,200,000.00

$                                         -  

D = B+C

Total Cost

$                9,000,000.00

$             10,660,000.00

$                  10,510,000.00

E = (B/D) x 100

% of Completion

29.00%

60.60%

100.00%

F = A x E

Revenue to date

$                2,900,000.00

$               6,060,037.52

$                  10,000,000.00

G

Revenue of Previous year

$                                     -  

$               2,900,000.00

$                    6,060,037.52

H = F - G

Net Revenue this year

$                2,900,000.00

$               3,160,037.52

$                    3,939,962.48

I (=B)

Cost to date

$                2,610,000.00

$               6,460,000.00

$                  10,510,000.00

J

Cost to date of previous year

$                                     -  

$               2,610,000.00

$                    6,460,000.00

K = I - J

Net Cost for the year

$                2,610,000.00

$               3,850,000.00

$                    4,050,000.00

L = A - D

Estimated Gross Profit (Loss)

$                1,000,000.00

$                 (660,000.00)

$                     (510,000.00)

M

Gross Profit (Loss) to be recognised

$                   290,000.00

$                 (950,000.00)

$                        150,000.00

Add a comment
Know the answer?
Add Answer to:
In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County...

    In 2016, Pioneer Construction Company entered into a contract to construct a road for Denton County for S10,000,000. The road was completed in 2018. Information related to the contract is as follows: 2017 $2,610,000 S3,162,000 $2,230,800 2,028,000 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2016 2018 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year 6,390,000 0 Cash collections during the year Pioneer recognizes revenue over time according to percentage of completion. Calculate the...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,044,000 5, 256,000 2,170,000 1,885,000 2022 2023 $2,628,000 $2,890, 800 2,628,000 2,502,0005, 328,000 2,600,0005,515,000 Westgate recognizes revenue over time according to percentage of completion....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: Westgate recognizes revenue over time according to percentage of completion. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,230, 800 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,610,000 6,390,000 2,100,000 1,850,000 2022 $3,162,000 2,028,000 3,672,000 3,000,000 4,228,000...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during the year 1,870,000 3,200,000 4,930,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT