| Land | Building | |
| Land | 560000 | |
| Razing Costs | 58800 | |
| Less: Salvage | (8820) | |
| Legal Fees | 2590 | |
| Survey | 3080 | |
| Plans | 95200 | |
| Title Insurance | 2100 | |
| Liability Insurance | 1260 | |
| Construction | 3836000 | |
| Interest | 238000 | |
| Total | $614,670 | $4,173,540 |
Question 7 View Policies Current Attempt in Progress Nash Co. purchased land as a factory site...
Bonita Co. purchased land as a factory site for $512,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $53,760 to raze the old buildings and sold salvaged lumber and brick for $8,064. Legal fees of $2,368 were paid for title Investigation and drawing the purchase contract. Bonita paid $2,816 to an engineering form for a land survey, and $87,040 for drawing the factory plans. The land survey...
Question 3 Concord Co. purchased land as a factory site for $440,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $46,200 to raze the old buildings and sold salvaged lumber and brick for $6,930. Legal fees of $2,035 were paid for title investigation and drawing the purchase contract. Concord paid $2,420 to an engineering firm for a land survey, and $74,800 for drawing the factory plans. The...
Cheyenne Co. purchased land as a factory site for $456,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $47,880 to raze the old buildings and sold salvaged lumber and brick for $7,182. Legal fees of $2,109 were paid for title investigation and drawing the purchase contract. Cheyenne paid $2,508 to an engineering firm for a land survey, and $77,520 for drawing the factory plans. The land survey...
Sarasota Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract.Sarasota paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey had...
Sweet Co. purchased land as a factory site for $600,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $63,000 to raze the old buildings and sold salvaged lumber and brick for $9,450. Legal fees of $2,775 were paid for title investigation and drawing the purchase contract. Sweet paid $3,300 to an engineering firm for a land survey, and $102,000 for drawing the factory plans. The land survey...
Coronado Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Coronado paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...
Shamrock Co. purchased land as a factory site for $432,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $45,360 to raze the old buildings and sold salvaged lumber and brick for $6,804. Legal fees of $1.998 were paid for title investigation and drawing the purchase contract. Shamrock paid $2,376 to an engineering firm for a land survey, and $73.440 for drawing the factory plans. The land survey...
Flounder Co. purchased land as a factory site for $488,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $51,240 to raze the old buildings and sold salvaged lumber and brick for $7,686. Legal fees of $2,257 were paid for title investigation and drawing the purchase contract. Flounder paid $2,684 to an engineering firm for a land survey, and $82,960 for drawing the factory plans. The land survey...
Exercise 10-02 Sheridan Co. purchased land as a factory site for $576,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $60,480 to raze the old buildings and sold salvaged lumber and brick for $9,072. Legal fees of $2,664 were paid for title investigation and drawing the purchase contract. Sheridan paid $3,168 to an engineering firm for a land survey, and $97,920 for drawing the factory plans. The...
Exercise 10-02 Sheridan Co. purchased land as a factory site for $576,000. The process of tearing down two old buildings on the site and constructing the factory required 6 months. The company paid $60,480 to raze the old buildings and sold salvaged lumber and brick for $9,072. Legal fees of $2,664 were paid for title investigation and drawing the purchase contract. Sheridan paid $3,168 to an engineering firm for a land survey, and $97,920 for drawing the factory plans. The...