COST ACCOUNTING
(JOB ORDER COSTING & PROCESS COSTING)
Question 01: Blake Cement (Pvt.) Ltd is engaged in the manufacturing of different kinds of cement. The production facility is located near Houston. It received an order from Triton Industries for 2,000Kg of white cement on October 01, 2016. This order is assigned Job number 313. The following information is available for the month of November 2016:
Material purchased during the month amounted to $50,000.
50% of this material was assigned to Job# 313. Each bag uses $1,250 of material.
Labor hours available in the month were 292. Each hour is paid @ $12 per hour. 200 hours were allocated to Job 313. Every 10Kg of cement requires 1 hour.
FOH is applied @ $20 per machine hour. A total of 200 machine hours were available in October.
Job # 313 utilized 145 machine hours. Every 20Kg bag of cement requires 1.45 hours on the machine.
Actual FOH amounted to $1,500.
Each cement bag weighs 20Kg and is sold for $1,800.
REQUIRED: You are required to:
Prepare a Job Order Cost Sheet (Job# 313) for the month of October 2016.
Pass necessary journal entries in the books of Triton Industries, assuming that the order was ready on October 25, but was shipped to customer on October 27, that was the required date provided by the customer for the order.
Answer
Note : the material required for 100 bags is more than the material assigned. It is assumed that additional material was made available to complete the order.

COST ACCOUNTING (JOB ORDER COSTING & PROCESS COSTING) Question 01: Blake Cement (Pvt.) Ltd is engaged...
Question 01: Blake Cement (Pvt.) Ltd is engaged in the manufacturing of different kinds of cement. The production facility is located near Houston. It received an order from Triton Industries for 2,000Kg of white cement on October 01, 2016. This order is assigned Job number 313. The following information is available for the month of November 2016: Material purchased during the month amounted to $50,000. 50% of this material was assigned to Job# 313. Each bag uses $1,250 of material....
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Prull Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Job 86 Job 87 Job 88 Balance, July 1 $21,320 $6,300 $0 Direct materials $10,490 $12,280 $16,210 Direct labor $16,000 $12,150 $23,990 Machine hours 480 290 1,020 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 86 and 88 were completed. Jobs 82 and 86...
Job Order Costing To keep records of the actual cost of a special order job, a Job Order Cost System has been developed. Overhead is applied at the rate of 50% of the direct labor cost. Job Order Costing Section On January 1, 20x2, Division S began Job 2407 for the Client, THE BIG CHILDREN STORE. The job called for 4,000 customized lamps. The following set of transactions occurred from January 5 until the job was completed: 5-Jan Purchased 4,200...
Exercise 2-9 (Algo) Job-Order Costing and Decision Making (LO2-1, LO2-2, LO2-3] Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 260,000 $ 5,720,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2....
Exercise 2-9 (Algo) Job-Order Costing and Decision Making [LO2-1, LO2-2, LO2-3] Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 250,000 Fixed manufacturing overhead cost $ 6,000,000 Variable manufacturing overhead cost per machine-hour $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2....
QUESTION 2 Citysites Sdn. Bhd. uses a job-order costing system. On Sept 1, Materials and Supplies Control account had a balance of $28.000, whilst the Finished Goods (Job X10) balance on the same date was $15,000. Work in process as at Sept 1 consists of 2 jobs. Details as follows: Job Materials ($) Labour (S) Overhead (S) XII 5.200 2,300 3,300 X12 8,700 3,200 5,775 Direct labour cost (S) incurred and machine hours for the month of Sept: Job Direct...
Practice Quiz Job Order Costing The information below is for ABC Co.'s first month of operations. The following jobs were begun during the month: Number of Direct Job # Products Materials Labor Labor Hours 100 $ 1,200 $ 1.100 $ 1,500 $ 1,500 $ 1,100 $ 900 103 $ 800 $ 1,000 Indirect $ 500 $ 700 Additional Information: 1. Jobs #100, W101 and 102 were completed during the month; Job 103 remained unfinished at the EOM 2. Other factory...
Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Balance, July 1 Direct materials Direct labor Machine hours Job 106 $21,310 $10,450 $16,000 500 Job 107 $6,250 $12,300 $12,200 300 Job 108 $0 $16,150 $24,000 1,000 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 106 and 108 were completed. Jobs 102 and 106...
Question 27: Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company following estimates 100,000 Machine-hours required to support estimated production Fixed manufacturing overhead cost ble mamahcturtgne-hour S3.00 per machine-hourS650,000 Required: 1. Compute the predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: S450 Direct materials requisitioned Direct labor cost S210 Machine-hours used...
PART 5 Job Order Costing To keep records of the actual cost of a special order icb, a Job Order Cost System has been developed Overhead is applied at the rate of 50% of the direct labor cost. Job Order Costing Section On January 1, 20x2. Division S began Job 2407 for the client. THE BIG CHILDREN STORE. The job called for 4,000 customized lamps. The following set of transactions occurred from January 5 until the job was completed: 5-Jan...