Question

1) Indiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is
1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

For the year 2021:

As per percentage of completion method,

Percentage completed = Cost incurred till this year end/Total estimated cost of project

Percentage completed= $36/($36+$84)=36/120= 30%

Hence, 30% of the project is completed.

Revenue

Revenue for the year= Percentage completed*Total Project Revenue

Revenue for 2021= 30% * $150 million= $45 million

Gross Profit

Gross profit for the year= Revenue for 2021 - Costs incurred in 2021

Gross profit for 2021= $45 million - $36 million = $9 million

For the year 2022:

As per percentage of completion method,

Percentage completed = Cost incurred till this year end/Total estimated cost of project

Percentage completed= ($36+$58.5)/($36+$58.5+$40.5) = 94.5/135 = 70%

Hence, 70% of the project is completed.

Revenue

Revenue for the year= (Percentage completed*Total Project Revenue) - Revenue of the previous year(s)

Revenue for 2022= (70% * $150 million) - $45 million = $105 million - $45 million= $60 million

Gross Profit

Gross profit for the year= Revenue for 2022 - Costs incurred in 2022

Gross profit for 2021= $60 million - $58.5 million = $1.5 million

Add a comment
Know the answer?
Add Answer to:
1) Indiana Co. began a construction project in 2021 with a contract price of $150 million...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $370 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 70 $ 110 $ 80 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

  • On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...

  • 2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction...

    2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...

  • On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT