For the year 2021:
As per percentage of completion method,
Percentage completed = Cost incurred till this year end/Total estimated cost of project
Percentage completed= $36/($36+$84)=36/120= 30%
Hence, 30% of the project is completed.
Revenue
Revenue for the year= Percentage completed*Total Project Revenue
Revenue for 2021= 30% * $150 million= $45 million
Gross Profit
Gross profit for the year= Revenue for 2021 - Costs incurred in 2021
Gross profit for 2021= $45 million - $36 million = $9 million
For the year 2022:
As per percentage of completion method,
Percentage completed = Cost incurred till this year end/Total estimated cost of project
Percentage completed= ($36+$58.5)/($36+$58.5+$40.5) = 94.5/135 = 70%
Hence, 70% of the project is completed.
Revenue
Revenue for the year= (Percentage completed*Total Project Revenue) - Revenue of the previous year(s)
Revenue for 2022= (70% * $150 million) - $45 million = $105 million - $45 million= $60 million
Gross Profit
Gross profit for the year= Revenue for 2022 - Costs incurred in 2022
Gross profit for 2021= $60 million - $58.5 million = $1.5 million
1) Indiana Co. began a construction project in 2021 with a contract price of $150 million...
On June 15, 2021, Sanderson Construction entered into a
long-term construction contract to build a baseball stadium in
Washington, D.C., for $370 million. The expected completion date is
April 1, 2023, just in time for the 2023 baseball season. Costs
incurred and estimated costs to complete at year-end for the life
of the contract are as follows ($ in millions):
2021
2022
2023
Costs incurred during the year
$
70
$
110
$
80
Estimated costs
to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
On June 15, 2021. Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.C. for $350 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows (5 in millions): 2021 $ 3e 170 Costs incurred during the year Estimated costs to complete as of December 31 2022 $142 0...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 2022 2023 Costs incurred during the year $ 80 $ 40 $ 90 Estimated costs to complete as of...
2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...
On February 1, 2021. Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2.475,000 cash was collected. The project was completed in 2023 after additional costs of...