Question

4. Project 1 costs A initially, costs B every year, generates C benefits every year and D disbenefits every year with a life

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We will first create a table of all the costs and benefits. next, we will calculate the present worth of all the cash flows by the discount factor of 12%.
However, projects have unequal lives so we will have to calculate the equivalent annual value by using the PV annuity factor for respective project life.
The benefit to cost ratio should be more than 1 to be accepted.
However, all three projects have a BC ratio of less than 1 so actually all should be rejected.
If that is not possible then the project with the highest BC ratio should be selected.
Project 3 should be selected in this case.

Project 1
PV of annual cost
=PV(12%,5,-60)
=216.29

BC Ratio = Total Benefits / Total Costs

Option 1 PW @ 12% Option 2 PW @ 12% Option 3 PW @ 12%
Initial Cost 128 128 160 160 340 340
Annual Cost 60 216.29 62.00 254.91 50 282.51
Disbenefits 10 36.05 15.00 61.67 20 113.00
Benefits 60 216.29 69.00 283.69 83 468.97
Life 5 6 10
Interest Rate 0.12 0.12 0.12
Total Benefits 216.29 283.69 468.97
Total Cost 380.3343 476.5784 735.5156
PV Annuity Factor 3.6048 4.1114 5.6502
Equivalent Annual Benefits 60 69 83
Equivalent Annual Costs 105.5084 115.9161 130.1746
Benefits to Cost Ratio 0.5687 0.5953 0.6376
Add a comment
Know the answer?
Add Answer to:
4. Project 1 costs A initially, costs B every year, generates C benefits every year and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 4. Project 1 costs A initially, costs B every year, generates C benefits every year and...

    4. Project 1 costs A initially, costs B every year, generates C benefits every year and D disbenefits every year with a life of 5 years. Project 2 costs e initially, cost F every year, generates G benefits every year and H disbenefits every year with a life of 6 years. Project 3 costs I initially, costs J every year, generates K benefits every year and L disbenefits every year with a life of 10 years. Use an annual rate...

  • Final Selection 4. Project 1 costs A initially, costs B every year, generates C benefits every year and D disbene...

    Final Selection 4. Project 1 costs A initially, costs B every year, generates C benefits every year and D disbenefits every year with a life of 5 years. Project 2 costs E initially, cost Fevery year, generates G benefits every year and H disbenefits every year with a life of 6 years. Project 3 costs: initially, costs I every year, generates K benefits every year and L disbenefits every year with a life of 10 years. Use an annual rate...

  • disbenefits every year with a life of 5 years. Project 2 costs E initially, cost Fevery...

    disbenefits every year with a life of 5 years. Project 2 costs E initially, cost Fevery year, generates G benefits every year and H disbenefits every year with a life of 6 years. Project 3 costs I initially, costs J every year, generates K benefits every year and L disbenefits every year with a life of 10 years. Use an annual rate of R to conduct Incremental B/C ratio analyses to select one of the alternatives. "Do Nothing" is not...

  • The estimated annual cash flows for a proposed municipal government project are costs of $830,000 per year, benefits of...

    The estimated annual cash flows for a proposed municipal government project are costs of $830,000 per year, benefits of $910,000 per year, and disbenefits of $280,000 per year. Calculate the conventional B/C ratio at an interest rate of 9% per year, and determine if it is economically justified. The B/C ratio is . The project is economically is justified or nonjustified

  • Q1 ) The Ministry of public health considering a project  a the following cash flows: benefits of...

    Q1 ) The Ministry of public health considering a project  a the following cash flows: benefits of $214,726 in the first years and increase by 3,993 for through year 20,  disbenefits  of $49,852 in the first year and decreases by $1,148 through year 20, The project first cost $687,400 and M&O costs of $25,000 per year. If the discount rate is 10% and study period is 20 years the modified B/C ratio of the project  is closest to Q2) A local government considering two...

  • Consider the following two projects Project 1: High rise residential building project Project 2: Low rize...

    Consider the following two projects Project 1: High rise residential building project Project 2: Low rize building First Cost, $ 320,000 540,000 M&O Cost, $/year 45,000 35,000 Benefits, $/year 110,000 150,000 Disbenefits, $/year 20,000 45,000 Life, years 10 20       -       A.       B.       C.       D.       E.       F.       G.       H.    For project 1, the Benefits/Cost ratio is nearest to       -   ...

  • The estimated annual cash flows for a proposed municipal government project are costs of $730,000 per...

    The estimated annual cash flows for a proposed municipal government project are costs of $730,000 per year, benefits of $890,000 per year, and disbenefits of $160,000 per year. Calculate the conventional B/C ratio at an interest rate of 8% per year, and determine if it is economically justified. The B/C ratio is . The project is economically (Click to select)justifiednot justified .

  • 15 (15 points The City of Coral Gables is going to undertake a beautification project the...

    15 (15 points The City of Coral Gables is going to undertake a beautification project the UM campus at a cost of $100,000. They expect to realize benefits of 10 000 in vear 0 and $30,000 in year 3. The Disbenefits of the project will occur er $7,000. The City of Coral Gables will save $25.000 in vears 1-4 The project life is 5 years and the MARR is 6%. What is the 0%. What is the conventional B/C ratio?

  • Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed...

    Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed municipal government project are costs of $710,000 per year, benefits of $910,000 per year, and disbenefits of $160,000 per year. Calculate the conventional B/C ratio at an interest rate of 12% per year, and determine if it is economically justified. The B/C ratio is The project is economically (Click to select) A

  • Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed...

    Problem 09.010 Benefit/Cost Analysis of a Single Project The estimated annual cash flows for a proposed municipal government project are costs of $800,000 per year, benefits of $910,000 per year, and disbenefits of $230,000 per year. Calculate the conventional B/C ratio at an interest rate of 9% per year, and determine if It is economically justified. The B/C ratio is The project is economically not justified

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT