Question

Exercise 9-37 (Static) Activity-Based Costing (LO 9-4, 5) After reviewing the new activity-based costing system that...

Exercise 9-37 (Static) Activity-Based Costing (LO 9-4, 5)

After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 100,000 units of the Sport model and 40,000 units of the Pro model in the first quarter. He believes that with his more efficient setup routine, he can reduce the number of setup hours for both the Sport and the Pro products by 25 percent.

Cost Drivers and Cost Driver Volumes—CenterPoint Manufacturing Facility

Cost Driver Volume
Activity Cost Driver Sport Pro Total
Assembly building
Assembling Machine-hours 6,000 30,000 36,000
Setting up machines Setup hours 40 400 440
Handling material Production runs 8 40 48
Packaging building
Inspecting and packing Direct labor-hours 60,000 22,800 82,800
Shipping Number of shipments 100 200 300

Third Quarter Unit Cost Report, Activity-Based Costing—CenterPoint Manufacturing Facility

Sport Pro
Direct material $ 1,500,000 $ 2,400,000
Direct labor
Assembly $ 750,000 $ 600,000
Packaging 990,000 360,000
Total direct labor $ 1,740,000 $ 960,000
Direct costs $ 3,240,000 $ 3,360,000
Overhead
Assembly building
Assembling (@ $30 per MH) $ 180,000 $ 900,000
Setting up machine (@ $900 per setup hour) 36,000 360,000
Handling material (@ $3,000 per run) 24,000 120,000
Packaging building
Inspecting and packing (@ $5 per direct labor-hour) 300,000 114,000
Shipping (@ $1,320 per shipment) 132,000 264,000
Total ABC overhead $ 672,000 $ 1,758,000
Total ABC cost $ 3,912,000 $ 5,118,000
Number of units 100,000 40,000
Unit cost $ 39.12 $ 127.95

Required:

a. Compute the amount of overhead allocated to the Sport and the Pro drones for the first quarter using activity-based costing. Assume that all events are the same in the first quarter as in the third quarter except for the number of setup hours. Assume the cost of a setup hour remains at $900.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Setup hours for Sport 30 40*75%
Setup hours for Pro 300 400*75%
Sport Pro
Direct material $1,500,000 $2,400,000
Direct labor
Assembly $750,000 $600,000
Packaging $990,000 $360,000
Total direct labor $1,740,000 $960,000
Direct costs $3,240,000 $3,360,000
Overhead
Assembly building
Assembling (@ $30 per MH) $180,000 $900,000
Setting up machine (@ $900 per setup hour) $27,000 $270,000 (30*900; 300*900)
Handling material (@ $3,000 per run) $24,000 $120,000
Packaging building
Inspecting and packing (@ $5 per direct labor-hour) $300,000 $114,000
Shipping (@ $1,320 per shipment) $132,000 $264,000
Total ABC overhead $663,000 $1,668,000
Total ABC cost $3,903,000 $5,028,000
Number of units $100,000 $40,000
Unit cost $39.03 $125.70
Overhead costs allocated to Sports is $663,000
Overhead costs allocated to Pro is $1,668,000
Add a comment
Answer #2

100-25%= 75%

Add a comment
Know the answer?
Add Answer to:
Exercise 9-37 (Static) Activity-Based Costing (LO 9-4, 5) After reviewing the new activity-based costing system that...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 100,000 units of the Sport model and 40,000 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 109,000 units of the Sport model and 44,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 119,000 units of the Sport model and 49,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 112,000 units of the Sport model and 46,000 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 103,000 units of the Sport model and 41,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 113,000 units of the Sport model and 46,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has Implemented at IVC's CenterPoint manufacturin...

    After reviewing the new activity-based costing system that Nancy Chen has Implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 115,000 units of the Sport model and 47,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing...

    After reviewing the new activity-based costing system that Nancy Chen has implemented at IVC's CenterPoint manufacturing facility, Tom Spencer, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability. He plans to produce 115,000 units of the Sport model and 47,500 units of the Pro model in the first...

  • After reviewing the new activity-based costing system that Janis McGee has implemented at Joplin Industries's Port...

    After reviewing the new activity-based costing system that Janis McGee has implemented at Joplin Industries's Port Arthur manufacturing facility, Kris Kristoff, the production supervisor, believes that he can reduce production costs by reducing the time spent on machine setups. He has spent the last month working with employees in the plant to change over the machines more quickly with the same reliability, He plans to produce 106.000 units of J25P and 43.000 units of J40X in the first quarter. He...

  • After reading an article about activity-based costing in a trade journal for the furniture industry, Santana...

    After reading an article about activity-based costing in a trade journal for the furniture industry, Santana Rey wondered if it was time to critically analyze overhead costs at Business Solutions. In a recent month, Santana found that setup costs, inspection costs, and utility costs made up most of its overhead. Additional information about overhead follows. Activity Setting up machines Inspecting components Providing utilities Cost $21,750 $5,300 $10,600 Driver 25 batches 5,300 parts 5,300 machine hours Overhead has been applied to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT