Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania's plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year:
|
Department A |
Department B |
|
|
Overhead costs (expected) |
$750,000 |
$330,000 |
|
Normal activity (machine hours) |
6,000 |
10,000 |
Required:
|
Job 73 Plantwide |
Job 73 Departmental |
|
Job 74 Plantwide |
Job 74 Departmental |
$$_________________________ over-applied/under-applied (circle one)
$$_________________________ Cost of Goods Sold increased/decreased (circle one)
| 1) predetermined overhead rate for the plant as a whole based on machine hours. | |||||||
| = Total Overheads/ Total Machine Hours | |||||||
| =($750000+330000)/(6000+10000) | |||||||
| =$67.50 per machine hour | |||||||
| 2) predetermined overhead rates for each department using machine hours | |||||||
| Department A= $750000/6000 =$125 per hour | |||||||
| Department B = $330000/10000 =$33 per hour | |||||||
| 3) | a)overhead cost assigned to each job using the plantwide rate computed in Requirement 1. | ||||||
| Job 73 | Job 74 | ||||||
| Machine hours | |||||||
| Department A | 25 | 40 | |||||
| Department B | 50 | 15 | |||||
| A) | Total | 75 | 55 | ||||
| B) | Overhead Rate Per hour | $ 67.50 | $ 67.50 | ||||
| Overhead Assigned (A*B) | $ 5,062.50 | $ 3,712.50 | |||||
| b)computation using the departmental rates found in Requirement 2 | |||||||
| Job 73 | Job 74 | ||||||
| Machine hours | |||||||
| 1 | Department A | 25 | 40 | ||||
| 2 | Department B | 50 | 15 | ||||
| Overhead Rates Per Hour | |||||||
| 3 | Department A | $ 125 | $ 125 | ||||
| 4 | Department B | $ 33 | $ 33 | ||||
| Overhead Assigned | |||||||
| 5 | Department A (1*3) | $ 3,125 | $ 5,000 | ||||
| 6 | Department B (2*4) | $ 1,650 | $ 495 | ||||
| 7 | Total | $ 4,775 | $ 5,495 | ||||
| 3) | Absorbed overhead = 17000 hours *$67.50 =$1147500 | ||||||
| Actual Overhead =$1100000 | |||||||
| Overapplied =$47500 | |||||||
| $47500 Cost of goods sold decreased. | |||||||
Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine...
Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania's plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $750,000 $330,000 Normal activity (machine hours) 6,000 10,000 Required: Compute a predetermined overhead rate for the plant as a whole...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $100,000 $61,000 Normal activity (machine hours) 18,000 14,800 Required: 1. Compute a predetermined...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania’s plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) $95,000 $48,000 Normal activity (machine hours) 12,000 3,800 Required: 1. Compute a predetermined...
Overhead Applied to Jobs, Departmental Overhead Rates Xania Inc, uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Xania's plant manager has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Xania has the following data for its two departments for the coming year: Department A Department B Overhead costs (expected) Normal activity (machine hours) $75,000 14,500 $81,000 11,800 Required: 1. Compute a predetermined...
8
Overhead Applied to Jobs, Departmental Overhead Rates Watson Products Inc. uses a normal job-order costing system. Currently, a plantwide overhead rate based on machine hours is used. Marlon Burke, the plant manager, has heard that departmental overhead rates can offer significantly better cost assignments than a plantwide rate can offer. Watson has the following data for its two departments for the coming year: Department B Department A $2,660,000 140,000 Overhead costs (estimated) Normal activity (machine hours) $924,000 84,000 Required:...
Mariposa, Inc., produces machine tools and currently uses a plantwide overhead rate, based on machine hours. Harry Whipple, the plant manager, has heard that departmental overhead rates can offer significantly better cost assignments than can a plantwide rate. Mariposa has the following data for its two departments for the coming year: Compute a predetermined overhead rate for the plant as a whole based on machine hours. Compute predetermined overhead rates for each department using machine hours. Suppose that a machine...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine- hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $656,000 Variable manufacturing overhead cost per $ 4.30 machine-hour Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $300...
White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Department Cutting Finishing Direct labor-hours 64,000 Machine-hours 65,000 1,300 Total fixed manufacturing overhead cost $360,000 $488,600 Variable manufacturing overhead per machine-hour 4.00 Variable manufacturing overhead per...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine- hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 157,000 $ 651,000 $ 4.20 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials...