With payback period decision model
CUT OFF IS 3 YEARS
FOR
b) Initial cash outflow = $25,000
Cash flow YEAR 1 = $2000
YEAR 2 = $ 8000
YEAR 3 = $ 14000
YEAR 4 = $ 20000
PAYBACK PERIOD = PYFR +BA/ CIYER
PYFR = NUMBER OF YEARS IMMEDIATELY PRECEDING THE YEAR OF FINAL RECOVERY
BA = BALANCE AMOUNT TO BE RECOVERED
CIYER = CASH INFLOW( YEAR OF FINAL RECOVERY)
THEREFORE, 3 + 1000/ 20000 = 3+.05 =3.05 YEARS IS THE PAYBACK PERIOD AND THIS REJECTED
c) Initial cash outflow = $ 45,000
cash flow YEAR 1= $$10,000
YEAR 2 = $15,000
YEAR 3 = $ 20,000
BY APPLYING FORMULA, WE GET 2 + 20000/ 20000 = 2+1 = 3 YEARS, THIS IS ACCEPTED
d) Initial cash flow =$ 1,00,000
YEAR 1= $ 40,000
YEAR 2 = $ 30,000
YEAR 3= $ 20,000
YEAR 4 = $ 10,000
BY APPLYING FORMULA, WE GET, 3+10,000/10,000 = 3+1= 4 YEARS, THIS IS ALSO REJECTED
what are the payback periods for b,c, and d? should they be accepted or rejected? %B9-1...
Payback period Given the cash Bow of two projects A and B and using the payback period decision model, which project(s) do you accept and which project(s) do you reject if you have a three-year cutoff period for recapturing the initial cash outflow? For payback period calculations, assume that the cash flow is equally distributed over the year Cash Flow Cost Cash low year 1 Cash flow year 2 Cash flow Cash flow year 4 Cash flow year 5 Cash...
Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000 and has a cutoff period of four years for these small-value projects. Two projects, R and S, in the following table, PE, are under consideration. Their anticipated cash flows are listed in the following table. If Becker uses a discount rate of 4% on these projects, are they accepted or rejected? If it uses a discount rate of 8%? A discount rate of 18%?...
Payback period. What are the payback periods of projects E and F in the following table:93: ? Assume all the cash flow is evenly spread throughout the year. If the cutoff period is 3 years, which project(s) do you accept? What is the payback period for project E? Data Table years (Round to one decimal place.) (Click on the following icon in order to copy its contents into a spreadsheet.) Cash Flow Cost Cash flow year 1 Cash flow year...
Given the following after-tax cash flow on a new toy for Tyler's Toys, find the project's payback period, NPV, and IRR. The appropriate discount rate for the project is 9%. If the cutoff period is 6 years for major projects, determine whether management will accept or reject the project under the three different decision models. Initial cash outflow: $12,800,000 Years one through four cash inflow: $3,200,000 each year Year five cash outflow: $1,280,000 Years six through eight cash inflow: $548,667...
Discounted payback period. Becker, Inc. uses the discounted payback period for projects costing less than $25,000 and has a cutoff period of four years for these small-value projects. Two projects, R and S, in the following table, B are under consideration. Their anticipated cash flows are listed in the following table. If Becker uses a discount rate of 6% on these projects, are they accepted or rejected? If it uses a discount rate of 12%? A discount rate of 18%?...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...
Problem 8-3 Calculating Payback [LO 1) Global Toys, Inc., imposes a payback cutoff of three years for its international investment projects. Assume the company has the following two projects available. Year Cash Flow A Cash Flow B 0 -$49,000 $ 94,000 1 19,000 21,000 2 25,400 26,000 21000 33,000 7,000 246,000 Requirement 1: What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Project A Project B Payback...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time Cash flow -$2,700 $1,160 $990 $1,030 $640 $440 0 2 4 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
Cas a llars) a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? e. If you use a cutoff period of 3 years, which projects will you accept? d-1. If the opportunity cost of capital is 10%, calculate the NPV for projects A. B. and C. (Negative amounts should be indicated by a minus sign. Do not round Intermediate calculations,...
Compute the discounted payback statistic for Project D if the appropriate cost of capital is 13 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: 2 4 Cash flow:-$11,500 $3,400 $4,280 $1,620 $0 $1,100 Discounted payback period years Should the project be accepted or rejected? O accepted O rejected