Question

P 8-30 (similar to) Question Help You are considering the following two projects and can take only one. Your cost of capital
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part-a:

Project-A:

At IRR,

Present Value of Cash Outflows = Present value of Cash Inflows

Let IRR of Project –A be “x%”

At IRR,

99 = 22/(1+x)^1 + 30/(1+x)^2 + 41/(1+x)^3 + 52/(1+x)^4

Computing for x , we get x = 14.785%

Therefore, IRR of Project A is 14.79%

.

Project-B:

At IRR,

Present Value of Cash Outflows = Present value of Cash Inflows

Let IRR of Project –B be “y%”

At IRR,

99 = 52/(1+y)^1 + 41/(1+y)^2 + 30/(1+y)^3 + 21/(1+y)^4

Computing for y , we get y = 20.183%

Therefore, IRR of Project B is 20.18%

.

.

.

Part-b:

NPV of Project-A:

Year CashFlows DF Working Discounting Factor @ 11.3% Present Value
0 -99 1 1                    (99.00)
1 22 1/1.113^1 0.898472597                      19.77
2 30 1/1.113^2 0.807253007                      24.22
3 41 1/1.113^3 0.725294705                      29.74
4 52 1/1.113^4 0.651657417                      33.89
NPV of Project-A:                         8.61

.

NPV of Project-B:

Year CashFlows DF Working Discounting Factor @ 11.3% Present Value
0 -99 1 1                    (99.00)
1 52 1/1.113^1 0.898472597                      46.72
2 41 1/1.113^2 0.807253007                      33.10
3 30 1/1.113^3 0.725294705                      21.76
4 21 1/1.113^4 0.651657417                      13.68
NPV of Project-B:                      16.26

.

.

.
Part-C:

Let the cost of capital at which both the two projects are indifferent be "z%

NPV of Project – A = NPB of Project – B

22/(1+z)^1 + 30/(1+z)^2 + 41/(1+z)^3 + 52/(1+z)^4 - 99 = 52/(1+z)^1 + 41/(1+z)^2 + 30/(1+z)^3 + 21/(1+z)^4 - 99

30/(1+z)^1 + 11(1+z)^2 -11/(1+z)^3 – 31/(1+z)^4 = 0

Computing for z , we get z = 0.98%

.

Therefore , at cost of capital = 0.98% , we will be indifferent between the two projects.

.

.

Part-D:

We should invest in Project-B , since it has higher NPV and higher IRR as compared to that of Project-B.

Add a comment
Know the answer?
Add Answer to:
P 8-30 (similar to) Question Help You are considering the following two projects and can take...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You are considering the following two projects and can take only one. Your cost of capital...

    You are considering the following two projects and can take only one. Your cost of capital is 11.2%. The cash flows for the two projects are as follows ($ million): Project Year 0 - $101 - $101 Year 1 $22 $52 Year 2 $29 $40 Year 3 $40 $29 Year 4 $52 $18 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...

  • Problem 8-27 (bookmatch) Question Help O You are considering the following two projects and can take...

    Problem 8-27 (bookmatch) Question Help O You are considering the following two projects and can take only one. Your cost of capital is 11.0%. The cash flows for the two projects are as follows ($ million): Project Year 1 Year 0 - $100 - $100 $25 $50 Year 2 $30 $40 $30 Year 3 $40 $30 Year 4 $50 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of...

  • You are considering the following two projects and can take only one. Your cost of capital...

    You are considering the following two projects and can take only one. Your cost of capital is 11.0%. The cash flows for the two projects are as follows ($ million): Project Year 4 Year 0 - $100 - $100 Year 1 $25 $50 Year 2 $30 $40 Year 3 $40 $30 $50 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of capital...

  • You are considering the following two projects and can take only one. Your cost of capital...

    You are considering the following two projects and can take only one. Your cost of capital is 11.0 %. The cash flows for the two projects are as follows (S million): Year 3 $40 $30 Year 0 -$100 -$100 Project Year 2 Year 4 Year 1 $50 $25 $50 $30 $40 $20 1,42 B a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...

  • You are considering the following two projects and can take only one. Your cost of capital is 11....

    You are considering the following two projects and can take only one. Your cost of capital is 11.4%. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$98 $27 $29 $38 $51 B −$98 $51 $38 $29 $18 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At what cost of capital...

  • You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Y...

    You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each​ project? b. What is the NPV of each project at your cost of​ capital? c. At what cost of...

  • You are considering the projects below and can take only one. Your cost of capital is...

    You are considering the projects below and can take only one. Your cost of capital is 11%. Complete the steps below using cell references to given data or previous calculations. In some cases, a simple cell reference is all you need. To copy/paste a formula across a row or down a column, an absolute cell reference or a mixed cell reference may be preferred. If a specific Excel function is to be used, the directions will specify the use of...

  • P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for...

    P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $51 - $102 Year 1 $23 $20 Year 2 $22 $42 Year 3 $22 $48 Year 4 $16 $61 a. What are the IRRs of the two projects? b. If your discount rate is 4.8%, what are the NPVs of the two projects? c. Why do IRR and NPV rank...

  • P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for...

    P 8-28 (similar to) Question Help You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project A B Year 0 - $48 - $101 Year 1 $25 $21 Year 2 $20 $41 Year 3 $19 $50 Year 4 $14 $59 a. What are the IRRs of the two projects? b. If your discount rate is 5.1%, what are the NPVs of the two projects? c. Why do IRR and...

  • You are choosing between two projects. The cash flows for the projects are given in the...

    You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): a. What are the IRRs of the two​ projects? The IRR for project A is ______​%. ​(Round to one decimal​ place.) The IRR for project B is ______​%. ​(Round to one decimal​ place.) b. If your discount rate is 4.8 %​, what are the NPVs of the two​ projects? If your discount rate is 4.8%​, the NPV for project A...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT