Heritage Gardens provides complete garden design and landscaping
services. The company uses a job-order costing system to track the
costs of its landscaping projects. The table below provides data
concerning the three landscaping projects that were in progress
during May. There was no work in process at the beginning of
May.
| Project | ||||||||||
| Williams | Chandler | Nguyen | ||||||||
| Designer-hours | 300 | 180 | 220 | |||||||
| Direct materials | $ | 5,800 | $ | 2,800 | $ | 4,600 | ||||
| Direct labor | $ | 3,400 | $ | 2,000 | $ | 2,500 | ||||
Actual overhead costs were $33,000 for May. Overhead costs are
applied to projects on the basis of designer-hours because most of
the overhead is related to the costs of the garden design studio.
The predetermined overhead rate is $55 per designer-hour. The
Williams and Chandler projects were completed in May; the Nguyen
project was not completed by the end of the month. No other jobs
were in process during May.
Required:
1. Compute the amount of overhead cost that would have been applied to each project during May.
2. Determine the cost of goods manufactured for May.
1) Overhead applied
| Williams | Chandler | Nguyen | Total | |
| Total overhead applied | 300*55 = 16500 | 180*55 = 9900 | 220*55 = 12100 | 38500 |
2) Cost of goods manufactured
| Williams | Chandler | |
| Direct material | 5800 | 2800 |
| Direct labor | 3400 | 2000 |
| Overhead | 16500 | 9900 |
| Total | 25700 | 14700 |
Cost of goods manufactured = 25700+14700 = 40400
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system...
Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 330 210 250 $6,100 $3,100 $4,900 $3,700 $2,300 $2,800 Actual overhead costs were $36,000 for May. Overhead costs are applied...
Che Heritage Gardens provides complete garden design and landscaping services. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials Direct labor Project Williams Chandler Nguyen 320 200 240 $6,000 $ 3,000 $ 4,800 $ 3,600 $2,200 $ 2,700 Actual overhead costs were $35,000 for...
Management Accounting
I'd be grateful if someone could show how to approach this
management accounting problem. Thanks in advance.
Local Landscaping uses a job-order costing system to track the costs of its landscaping projects. The company provides complete garden design and landscaping services. The following table provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May. Designer-hours Direct materials cost Direct labour cost. Williams 200 $4,800...
Applying Overhead in a Service Company: Journal Entries (L04, LOS, LOB] Vista Landscaping uses a job-order costing system to track the costs of its landscaping projects The company provides garden design and installation services for its clients. The table below provides data concerning the three landscaping projects that were in progress during April. There was no work in process at the beginning of April Project Harris Chan James Designer- hours 120 100 90 Actual overhead costs were $30,000 for April....
Creative Web Design uses a job-order costing system to track the costs of its web design projects. The company provides complete website design and hosting services. The following table provides data concerning the three design projects that were in process during May. There was no work in process at the beginning of May Project Happy Daycare Designer hours. Direct labour cost Car city 90 2 ,430 Jan's flowers 60 5 1,200 5 $1,320 Actual overhead costs were $3.250 for May....
Larry’s Lawn Services provides custom landscaping for homes and businesses and uses job order costing to capture the cost of its landscaping jobs. There are no jobs in process at the beginning of May. Listed below are data concerning the three landscaping jobs conducted during May. Southside Oceanview Rocky Heights Direct materials $5,730 $7,910 $6,490 Landscaper labor costs $4,662 $5,544 $5,355 Landscaper hours 74 88 85 Overhead costs are applied to jobs on the basis of landscaper hours, and the...
Number 2 Larry's Lawn Services provides custom landscaping for homes and businesses and uses job order costing to capture the cost of its landscaping jobs. There are no jobs in process at the beginning of May. Listed below are data concerning the three landscaping jobs conducted during May Rocky Heights $6,480 $5,525 85 Oceanview $7,635 $5,980 92 Southside $5,450 $4,810 Direct materials Landscaper labor costs Landscaper hours 74 Overhead costs are applied to jobs on the basis of landscaper hours,...
Greener Garden USA provides lawn care and landscaping services to commercial clients. Greener Garden USA uses activity-based costing to bid on jobs and to evaluate their profitability. Greener Garden USA reports the following budgeted annual costs: (Click the icon to view budgeted annual costs.) (Click the icon to view additional information.) Read the requirements. Requirement 1. Allocate Greener Garden USA's costs to the activity-cost pools and determine the activity rate for each pool. Start by allocating Greener Garden USA's costs...
Job-Order Costing U-Design-It Furniture Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $144,000 for the year and the estimated direct labor hours were 18,000 hours. In March, Job #175 was completed. Direct materials totaled $7,000. Total labor costs were $6,000 at $20 per hour. At the end of the year, it was determined that the company worked 17,000 direct labor hours...
Week 5 Job Costing The Fine Manufacturing Company uses job order costing system. The company uses machine hours to apply overhead cost to jobs. At the beginning of 2019, the company estimated that 150,000 machine hours would be worked and $900,000 overhead cost would be incurred during 2012. The balances of raw materials, work in process (WIP), and finished goods at the beginning of 2012 were as follows: Raw materials: $40,000 Work in process: $30,000 Finished goods: $60,000 The Fine...