Activity Rate = Overheads/Total Activity
Cost Pool Estimated Overhead Total Activity Rate
Machine Setup                          17,500                   35                   500 per setup
Machining                        120,750              4,830                     25 per machine hour
Packing                          28,670                 470                     61 per order
Total                        166,920
Overhead assigned = Activity rate*Activity consumed
BC113 AD908
Cost Pool Estimated Use Rate Cost Assigned Estimated Use Rate Cost Assigned
Machine Setup                                 20                 500             10,000                             15        500                7,500
Machining                            1,140                   25             28,500                       3,690           25             92,250
Packing                               120                   61                7,320                          350           61             21,350
Total             45,820           121,100
Number of units                2,000                1,000
Overheads per unit 22.91 121.1
Add a comment
Know the answer?
Add Answer to:
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Activity Cost Pools Machine setup Machining Packing Cost Drivers Setups Machine hours Orders Estimated Overhead $14,800 78,560 27,030 Estimated Use of Cost Drivers per Product Estimated Use...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $22,000 97,200 30,080 Cost Drivers Setups Machine hours Orders 21 Estimated Use of Cost Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...

  •    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units...

       Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $18,500 106,920 35,640 Cost Drivers Setups Machine hours...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers BC113 AD908 per Activity Estimated Overhead Activity Cost Pools Cost Drivers Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Prod...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Activity Cost Pools Cost Drivers Estimated Overhead Estimated Use of Cost Drivers per Activity Product BC113 Product AD908 Machine setup...

  • Question 1 Swifty Industries has three activity cost pools and two products. It estimates production 2,000...

    Question 1 Swifty Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Swifty accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Cost Drivers Estimated Use of Cost Product Drivers per Activity BC113 Product AD908 Activity Cost Pools Machine setup...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Please solve the questions in the boxes, much appreciated! thank you so much!! Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each . pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Product AD908 Annual Overhead Data Estimated Activity Cost Pools Cost Drivers Overhead Machine setup Setups $22,000 Machining Machine hours 97,200 Packing Orders 30,080 Estimated Use of Cost Drivers per...

  • Flynn Industries has three activity cost pools and two products. It estimates production 2,000 un...

    Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Annual Overhead Data Estimated Overhead $18,500 106,920 35,640 Drivers per Activity Activity Cost Pools Machine setup Machining...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT