Question

16. Jane is a project manager for a company that produces two special widgets each year for suppliers around the world. Jane
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Let us first understand the basic terms used in the calculations:

PV-Planned Value:- It is cost of the work that is planned to be expensed as per budget.

EV-Earned Value:- It is cost of the work that is performed as per budget.

AC-Actual Cost:- It is cost of the budget that is completed till the time.

SV-Schedule Variance:- EV – PV

CV-Cost Variance:- EV – AC

SPI(scheduled performance index) = EV / PV

CPI (cost performance index) = EV /AC

Now we calculates the initial basic terms PV,EV and AC for Widget A and B:

Widget A

PV = Per Widget $50 spent x 200 Widget per month x 6 months = $60,000

EV = Per Widget $50 spent x 800 Widget Produced = $40,000

AC = $45,000

Widget B

PV = Per Widget $100 spent x 100 Widget per month x 4 months = $40,000

EV = Per Widget $100 spent x 400 Widget Produced = $40,000

AC = $35,000

Widget A

Widget B

SV = EV-PV

$40,000-$60,000

SV = EV-PV

$40,000-$40,000

-$20,000

$0

CV = EV - AC

$40,000-$45,000

CV = EV - AC

$40,000-$35,000

-$5,000

$5,000

SPI = EV/PV

$40,000/$60,000

SPI = EV/PV

$40,000/$40,000

0.67

1

CPI = EV/AC

$40,000/$45,000

CPI = EV/AC

$40,000/$35,000

0.89

1.14

Interpretation:

SPI = 1, All work has been completed as scheduled

SPI <1, Work has not been completed as scheduled

SPI >1, Work is completed fast as scheduled before time.

CPI = 1, Team is spending as originally planned

CPI < 1, Project is over Budget

CPI > 1, Project is under Budget

Here Widget A SPI is just 0.67, i.e. it is behind schedule and CPI is 0.89, I.e. Project is over budget by $5,000 ($40,000-$45,000)

Widget B SPI is 1, i.e. its is on schedule and CPI is 1.14, i.e. Project is under budget by $5,000 ($40,000-$35,000)

Add a comment
Know the answer?
Add Answer to:
16. Jane is a project manager for a company that produces two special widgets each year...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q4 Maria is a project manager for a company that produces two types of appliances each...

    Q4 Maria is a project manager for a company that produces two types of appliances each year for local suppliers. The project requires 200 appliances to be produced per month for Appliance A with a cost of RM 50 each, and 100 appliances to be produced per month for Appliance B with a cost of RM 100 each. Maria receives a project budget of RM 200,000 for 10 months to produce both appliances. After Maria's project team into six months...

  • Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit...

    Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below: 120 total units were planned to be produced 130 units have actually been produced The financial manager reported that the business had actually spent $13,000 on the project by the end of week three. Answer the following questions; show...

  • Sweet Ayla Company currently has the capacity to manufacture 150,000 widgets a year. The widgets normally...

    Sweet Ayla Company currently has the capacity to manufacture 150,000 widgets a year. The widgets normally sell for $23.00 each. Sweet Ayla Company has the following costs related to manufacturing and selling 120,000 widgets: Direct materials $300,000 Direct labor $540,000 Variable manufacturing overhead $180,000 Depreciation on equipment only used for the widgets $40,000 Depreciation on factory $100,000 Salary of widget production manager $70,000 Variable selling costs (commissions) $60,000 Fixed selling costs $80,000 Total $1,370,000 Now assume that at the end...

  • Monrose Park had the following transactions during the month of November 2018. Nov 2                        Purchased 1,000 widgets...

    Monrose Park had the following transactions during the month of November 2018. Nov 2                        Purchased 1,000 widgets for $20 per unit on credit Nov 5                        Sold 900 widgets for $55 each for cash Nov 10                     Purchased 500 widgets for $25 per unit on credit Nov 18                     Sold 100 widgets for $60 each on credit Nov 29                     Sold 300 widgets for $50 each for cash Monrose Park uses a perpetual inventory system and the FIFO inventory valuation method. There were no widgets in the company’s opening...

  • Calculate the fully loaded cost of labor for your project team members. (20 points) Write only th...

    Calculate the fully loaded cost of labor for your project team members. (20 points) Write only the total fully loaded labor cost for each member. Don't wTite the cost for each activity in the table below Project Team Hours Needed forOverhead NameEach ActvityCharge RateHourly RateLabor Cest Total) C-10 E-10 Tommy 1.70 $20 Kellie 1.35 $15 B-10 Drew D-10 F-20 1.70 $15 Blake E-10 1.50 $25 esse 1.70 $25 Schedule for each task is as follows: Calculate the cost for each...

  • Software Installation: You are the project manager of the software installation project (see figure & table)...

    Software Installation: You are the project manager of the software installation project (see figure & table) below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25. In addition, your project team determined that indirect project costs are $2,500 per week. Oo un D FINISH START START I Normal Normal Crash Crash Max reduction $ per Week Activity Time Cost Time Cost AI 5...

  • please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next si...

    please showing working.. formulas 10. A company produces sofas. The manager wants to prepare a 0. am for the next six months using the following information: plan Month 2 3 456 160 150 160 180 170 140 recast demand For Cost Per Unit Regular time $100 Overtime $150 Part-time $120 Inventory, per month $10 Back order, per month $50 There are five workers, each making 30 sofas a month. The maximum number of sofas produced during overtime is 30 per...

  • You are the manager of a project to improve a billing process at your firm. The...

    You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project Indirect costs are $1,600 per week, and penalty costs are $600 per week after week 12 Immediate Normal Cost Crash Cost Predecessor(s) Normal Time (weeks) Crash Time (weeks) ($) ($) Activity A 4 5,500 7,500 В 5 3 8,000 9,500 A 1 1 3,500 3,500 В 6 3...

  • 20. Chapman Company manufactures widgets Embrse Compare with a proposal to sell the company widgets et a price $179 Cha...

    20. Chapman Company manufactures widgets Embrse Compare with a proposal to sell the company widgets et a price $179 Chapman is currently making the one in G are associated with this part of the process when 100.000 Direct materials Direct labor Manufacturing overhead r 100 e company has approach Vents in its own factory. The following 100.000 units are product $ 46,500 43,500 60.000 us Total no longer produced by Chaprnan. From Chapman's point o 24,000 of costs that will...

  • Jane Smith, age 40, is single and has no dependents. She is employed as a legal secretary by Lega...

    Jane Smith, age 40, is single and has no dependents. She is employed as a legal secretary by Legal Services, Inc. She owns and operates Typing Services located near the campus of Florida Atlantic University at 1986 Campus Drive. Jane is a material participant in the business. She is a cash basis taxpayer. Jane lives at 2020 Oakcrest Road, Boca Raton, FL 33431. Jane's Social Security number is 123-45-6789. Jane indicates that she wants to designate $3 to the Presidential...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT