2. We find the IRR using goal seek function in excel
Lets Assume DF to be 20%, we find the NPV as below:
| Interest | 20.00% | ||
| Year | Amount | DF | PV |
| 0 | -5,00,000.00 | 1.00 | -5,00,000 |
| 1 | 1,50,000.00 | 0.83 | 1,25,000 |
| 2 | 2,50,000.00 | 0.69 | 1,73,611 |
| 3 | 3,10,000.00 | 0.58 | 1,79,398 |
| NPV | -21,991 |
Now we use goal seek function, such that NPV is Nil and with changing Interest Rate we get,
| Interest | 17.48% | ||
| Year | Amount | DF | PV |
| 0 | -5,00,000.00 | 1.00 | -5,00,000 |
| 1 | 1,50,000.00 | 0.85 | 1,27,680 |
| 2 | 2,50,000.00 | 0.72 | 1,81,135 |
| 3 | 3,10,000.00 | 0.62 | 1,91,185 |
| NPV | 0 |
At DF of 17.48%, NPV is Nil. Hence 17.48% is the IRR.
Since our cost of capital of 12% is below IRR 17.48%, project is acceptable.
3. Profitability Index
The Profitability Index (PI) measures the ratio between the present value of future cash flows and the initial investment.
If the PI is greater than 1, the project generates value and the company may want to proceed with the project.
We find the present value of cash inflow:
| Interest | 9.00% | ||
| Year | Amount | DF | PV |
| 1 | 70,000.00 | 0.92 | 64,220 |
| 2 | 2,30,000.00 | 0.84 | 1,93,586 |
| 3 | 3,35,000.00 | 0.77 | 2,58,681 |
| Total PV | 5,16,488 |
Profitability Index = PV of Cash Inflows / Initial Investment = 516,488 / 365000 = 1.42
As PI is above 1, project is acceptable.
2. Calculate the IRR for the following cash flows. Is the project acceptable if the firm's...
Given a project with the following cash flows and a cost of capital of 9%. Calculate the NPV, IRR, MIRR, and PI. For each of the four calculations, give a brief interpretation of what it measures and how it should be used to evaluate a project. Should the project be accepted? Why or why not? Time Period Cash Flow 0 -$200,000 1 $50,000 2 $70,000 3 -$80,000 4 $75,000 5 $100,000 6 $120,000...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes more reasonable assumption other than the project's IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $3,000,000. The project's expected cash flows are: Year Cash Flow...
1. Given the following set of cash flows for a project, calculate the NPV, PI, IRR, MIRR, Payback, Discounted Payback and Accounting Rate of Return. Assume a cost of capital of 10%. Assuming that this is an independent project, should the project be accepted? Why or why not? (20 pts.) Year Cash Flow Net Profit Depreciation 0 -$125,000 1 $22,000 $15,000 $10,000 2 $58,000 $43,000 $25,000 3 -$30,000 $24,000 $21,000 4 $35,000 $28,000 $18,000 5 $28,000 $20,000 $15,000 6 $60,000 ...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $500,000. The project's expected cash flows are: Year Year 1...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Grey Fox Aviation Company is analyzing a project that requires an initial investment of $550,000. The...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $500,000. The project's expected cash flows are: Year...
IRR: Mutually exclusive projects Bell Manufacturing is attempting to choose the better of two mutually exclusive projects for expanding the firm's warehouse capac ity. The relevant cash flows for the projects are shown in the following table. The firm's cost of capital is 15%. Initial investment (CF) Year (1) Project X Project Y $500,000 $325,000 Cash inflows (CF) $100,000 $140,000 120,000 120,000 150,000 95,000 190,000 70,000 250,000 50,000 a. Calculate the IRR to the nearest whole percent for each of...
Given the following cash flows for a capital project, calculate the Payback period, NPV, PI, IRR, and MIRR. The required rate of return is 8 percent. Year CF 0 $(50,000.00) 1 $15,000.00 2 $15,000.00 3 $15,000.00 4 $15,000.00 5 $5,000.00
Dropdown option: (accept, reject)
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation: Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000. The project's expected cash...