Month Machine Hours Electricity Costs
January 2,900 $ 18,600
February 3,300 $ 21,400
March 2,300 $ 13,700
April 3,500 $ 23,400
May 4,200 $ 28,450
June 3,700 $ 22,400
July 4,500 $ 24,950
August 3,900 $ 22,950
September 2,400 $ 15,900
October 4,100 $ 26,400
November 5,300 $ 31,400
December 4,900 $ 27,950

  

Summary Output
Regression Statistics
Multiple R .959
R Square .920
Adjusted R2 .912
Standard Error 1,550.32
Observations 12.00

  

Coefficients Standard Error t Stat P-value Lower 95% Upper 95%
Intercept 2,992.80 1,933.78 1.55 0.15 (1,315.92) 7,301.52
Machine Hours 5.37 0.50 10.70 0.00 4.25 6.49

  
Based on the results of the high-low analysis, the estimate of electricity costs in a month with 2,600 machine hours would be: (Round "Per unit" answer to 2 decimal places and all dollar amount to nearest whole dollar.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • First, using High Low method, we should find out:
    Variable cost per machine hour, and
    Fixed cost per month.
  • High Low working

Months

Units

Cost

High Level

Nov

                            5,300

$                   31,400.00

Low Level

Mar

                            2,300

$                   13,700.00

Difference

                            3,000

$                   17,700.00

A

Difference in Cost

$                   17,700.00

B

Difference in units

                              3,000

C = A/B

Variable cost per unit

$                           5.900

Working

High Level

Low Level

A

Total Cost

$                 31,400.00

$                   13,700.00

B

Total Units

5300

2300

C

Variable cost per unit

$                           5.90

$                             5.90

D = B x C

Total Variable cost

$                 31,270.00

$                   13,570.00

E = A - D

Total Fixed Cost

$                       130.00

$                         130.00

  • Variable cost = $ 5.90 per machine hour
    Fixed Cost = $ 130 per month.
  • Requirement:
    Electricity cost for 2600 machine hours = $ 130 fixed cost + ($5.90 x 2600 MHs)
    = 130 + 15340
    = $ 15,470 Answer
Add a comment
Know the answer?
Add Answer to:
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,300 2,700 1,700 2,900 3,600 3,100 3,900 3,300 1,800 3,500 4,500 4,000 Electricity Costs $19, 100 $22,400 $14,200 $24,400 $28,950 $23,400 $25,450 $23,450 $ 16,900 $27,400 $32,400 $28,450 Summary Output Regression Statistics...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,300 2,700 1,700 2,900 3,600 3, 100 3,900 3,300 1,800 3,500 4,500 4,000 Electricity Costs $19, 100 $22,400 $14,200 $24,400 $28,950 $23,400 $25,450 $23,450 $ 16,900 $27,400 $32,400 $28,450 Summary Output Regression...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,000 $ 18,650 February 3,400 $ 21,500 March 2,400 $ 13,750 April 3,600 $ 23,500 May 4,300 $ 28,500 June 3,800 $ 22,500 July 4,600 $ 25,000 August 4,000 $ 23,000 September 2,500 $ 16,000 October 4,200 $ 26,500 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2.500 $ 18.400 February 2,900 21,000 March 1.900 13,500 April 3,100 23,000 May 3.800 28,250 3,300 22,000 4,500 24,750 August 3.500 22,750 September 2,000 15,500 October 3,700 26,000 November 4,700 31.000 December 4.200 27,750 Summary Output Regression Stonistics Multiple 0.965 0.932...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,200 2,600 1,600 2,800 3,500 3,000 3,800 3,200 1,700 3,400 4,400 3,900 Electricity Costs $ 19,050 $22,300 $14,150 $24,300 $28,900 $23,300 $25,400 $23,400 $ 16,800 $27,300 $32,300 $28,400 Summary Output Regression Statistics...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,100 $ 18,700 February 3,500 $ 21,600 March 2,500 $ 13,800 April 3,700 $ 23,600 May 4,400 $ 28,550 June 3,900 $ 22,600 July 4,700 $ 25,050 August 4,100 $ 23,050 September 2,600 $ 16,100 October 4,300 $ 26,600 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow:    Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,600 3,000 2,000 3,200 3,900 3,400 4,200 3,600 2,100 3,800 4,800 4,300 Electricity Costs $19, 250 $22,700 $14,350 $24,700 $29,100 $23,700 $25,600 $23,600 $17,200 $27,700 $32,700 $28,600 Summary Output Regression Statistics Multiple...

  • Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...

    Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17, 100 $27,600 $32,600 $28,550 Summary Output Regression Statistics...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT