Thane Company is interested in establishing the relationship
between electricity costs and machine hours. Data have been
collected and a regression analysis prepared using Excel. The
monthly data and the regression output follow:
| Month | Machine Hours | Electricity Costs | ||
| January | 2,900 | $ | 18,600 | |
| February | 3,300 | $ | 21,400 | |
| March | 2,300 | $ | 13,700 | |
| April | 3,500 | $ | 23,400 | |
| May | 4,200 | $ | 28,450 | |
| June | 3,700 | $ | 22,400 | |
| July | 4,500 | $ | 24,950 | |
| August | 3,900 | $ | 22,950 | |
| September | 2,400 | $ | 15,900 | |
| October | 4,100 | $ | 26,400 | |
| November | 5,300 | $ | 31,400 | |
| December | 4,900 | $ | 27,950 | |
| Summary Output | |
| Regression Statistics | |
| Multiple R | .959 |
| R Square | .920 |
| Adjusted R2 | .912 |
| Standard Error | 1,550.32 |
| Observations | 12.00 |
| Coefficients | Standard Error | t Stat | P-value | Lower 95% | Upper 95% | |
| Intercept | 2,992.80 | 1,933.78 | 1.55 | 0.15 | (1,315.92) | 7,301.52 |
| Machine Hours | 5.37 | 0.50 | 10.70 | 0.00 | 4.25 | 6.49 |
Based on the results of the high-low analysis, the estimate of
electricity costs in a month with 2,600 machine hours would be:
(Round "Per unit" answer to 2 decimal places and all dollar
amount to nearest whole dollar.)
Answer
|
Months |
Units |
Cost |
|
|
High Level |
Nov |
5,300 |
$ 31,400.00 |
|
Low Level |
Mar |
2,300 |
$ 13,700.00 |
|
Difference |
3,000 |
$ 17,700.00 |
|
|
A |
Difference in Cost |
$ 17,700.00 |
|
|
B |
Difference in units |
3,000 |
|
|
C = A/B |
Variable cost per unit |
$ 5.900 |
|
|
Working |
High Level |
Low Level |
|
|
A |
Total Cost |
$ 31,400.00 |
$ 13,700.00 |
|
B |
Total Units |
5300 |
2300 |
|
C |
Variable cost per unit |
$ 5.90 |
$ 5.90 |
|
D = B x C |
Total Variable cost |
$ 31,270.00 |
$ 13,570.00 |
|
E = A - D |
Total Fixed Cost |
$ 130.00 |
$ 130.00 |
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,300 2,700 1,700 2,900 3,600 3,100 3,900 3,300 1,800 3,500 4,500 4,000 Electricity Costs $19, 100 $22,400 $14,200 $24,400 $28,950 $23,400 $25,450 $23,450 $ 16,900 $27,400 $32,400 $28,450 Summary Output Regression Statistics...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,300 2,700 1,700 2,900 3,600 3, 100 3,900 3,300 1,800 3,500 4,500 4,000 Electricity Costs $19, 100 $22,400 $14,200 $24,400 $28,950 $23,400 $25,450 $23,450 $ 16,900 $27,400 $32,400 $28,450 Summary Output Regression...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2,600 $ 19,250 February 3,000 $ 22,700 March 2,000 $ 14,350 April 3,200 $ 24,700 May 3,900 $ 29,100 June 3,400 $ 23,700 July 4,200 $ 25,600 August 3,600 $ 23,600 September 2,100 $ 17,200 October 3,800 $ 27,700 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,000 $ 18,650 February 3,400 $ 21,500 March 2,400 $ 13,750 April 3,600 $ 23,500 May 4,300 $ 28,500 June 3,800 $ 22,500 July 4,600 $ 25,000 August 4,000 $ 23,000 September 2,500 $ 16,000 October 4,200 $ 26,500 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 2.500 $ 18.400 February 2,900 21,000 March 1.900 13,500 April 3,100 23,000 May 3.800 28,250 3,300 22,000 4,500 24,750 August 3.500 22,750 September 2,000 15,500 October 3,700 26,000 November 4,700 31.000 December 4.200 27,750 Summary Output Regression Stonistics Multiple 0.965 0.932...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,200 2,600 1,600 2,800 3,500 3,000 3,800 3,200 1,700 3,400 4,400 3,900 Electricity Costs $ 19,050 $22,300 $14,150 $24,300 $28,900 $23,300 $25,400 $23,400 $ 16,800 $27,300 $32,300 $28,400 Summary Output Regression Statistics...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,100 $ 18,700 February 3,500 $ 21,600 March 2,500 $ 13,800 April 3,700 $ 23,600 May 4,400 $ 28,550 June 3,900 $ 22,600 July 4,700 $ 25,050 August 4,100 $ 23,050 September 2,600 $ 16,100 October 4,300 $ 26,600 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month Machine Hours Electricity Costs January 3,500 $ 18,900 February 3,900 $ 22,000 March 2,900 $ 14,000 April 4,100 $ 24,000 May 4,800 $ 28,750 June 4,300 $ 23,000 July 5,500 $ 25,250 August 4,500 $ 23,250 September 3,000 $ 16,500 October 4,700 $ 27,000 November...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,600 3,000 2,000 3,200 3,900 3,400 4,200 3,600 2,100 3,800 4,800 4,300 Electricity Costs $19, 250 $22,700 $14,350 $24,700 $29,100 $23,700 $25,600 $23,600 $17,200 $27,700 $32,700 $28,600 Summary Output Regression Statistics Multiple...
Thane Company is interested in establishing the relationship between electricity costs and machine hours. Data have been collected and a regression analysis prepared using Excel. The monthly data and the regression output follow: Month January February March April May June July August September October November December Machine Hours 2,500 2,900 1,900 3,100 3,800 3,300 4,100 3,500 2,000 3,700 4,700 4,200 Electricity Costs $19, 200 $22,600 $14,300 $24,600 $29,050 $23,600 $25,550 $23,550 $17, 100 $27,600 $32,600 $28,550 Summary Output Regression Statistics...