Question

Problem 2 East Coast Colorworks produces modular office space units. The company uses a job order costing system to accumulate product costs. Because much of the production process is automated, East Coast has selected machine hours as its overhead application rate In October, East Coast worked on four jobs. Job 105 and Job 106 were started in September and completed and delivered to customers in October. Job 107 and Job 108 were started in October and Job 107 was finished but has yet to be sold. The relevant data for September and October are ob 105 Job 106 Job 107 Job 108 Costs added September Direct materials Direct labor Mfg. Overhead Machine Hours $25,000 36,000 $40,000 1,600 MH $ 10,000 $4,000 $ 500 20 MH Costs added in October Direct materials Direct labor Machine Hours 0 $ 8,000 120 MH $ 9,000 $28,000 500 MH $ 8,000 $12,000 325 MH $ 4,000 500 45 MH Required: a) Calculate the predetermined overhead rate used by East Coast. b) Calculate the total manufacturing cost for October c) Calculate the total cost for each of the five jobs as of October 31. d) Calculate the cost of goods manufactured for October e) Calculate the balance in the Work in Progress Inventory account as of October 31. f) Calculate the Cost of Goods Sold for October. e) Calculate the balance in the finished goods Inventory account as of October 31.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.
a. Predetermined overhead rate used:
Job 105 Job 106
Manufacturing Overheads A $ 40,000 $        500
Machine Hours B         1,600              20
Predetermined Overhead Rate A/B $      25.0 $      25.0
b. Manufacturing Cost for October:
Job 105 Job 106 Job 107 Job 108 Total
Direct Material $           -   $    9,000 $              8,000 $    4,000 $ 21,000
Direct Labor $    8,000 $ 28,000 $            12,000 $       500 $ 48,500
Manufacturing Overheads $    3,000 $ 12,500 $              8,125 $    1,125 $ 24,750
(Machine Hours*$25 Rate in a)
Manufacturing Cost for October $ 11,000 $ 49,500 $            28,125 $    5,625 $ 94,250
c. Total Cost
Job 105 Job 106 Job 107 Job 108 Total
Beginning WIP:
25000+36000+40000 $101,000 $101,000
10000+4000+500 $ 14,500 $ 14,500
Direct Material $           -   $    9,000 $              8,000 $    4,000 $ 21,000
Direct Labor $    8,000 $ 28,000 $            12,000 $       500 $ 48,500
Manufacturing Overheads $    3,000 $ 12,500 $              8,125 $    1,125 $ 24,750
(Machine Hours*$25 Rate in a)
Manufacturing Cost for October $112,000 $ 64,000 $            28,125 $    5,625 $209,750
d. Cost of Goods Manufactured
Direct Material Used From part b $ 21,000
add:Direct manufacturing labor costs From part b $ 48,500
add:Manufacturing Overheads From part b $ 24,750
Manufacturing costs incurred $ 94,250
Add beginning work-in-process inventory 101000+14500 $115,500
Total manufacturing costs to account for $209,750
Less Ending WIP-Job 108 From part c/e $   -5,625
Cost of Goods Manufactured $204,125
e. Work in process as on October 31
Job 105 Job 106 Job 107 Job 108 Total
Beginning WIP:
25000+36000+40000 $101,000 $101,000
10000+4000+500 $ 14,500 $ 14,500
Direct Material $           -   $    9,000 $              8,000 $    4,000 $ 21,000
Direct Labor $    8,000 $ 28,000 $            12,000 $       500 $ 48,500
Manufacturing Overheads $    3,000 $ 12,500 $              8,125 $    1,125 $ 24,750
(Machine Hours*$25 Rate in a)
Manufacturing Cost for October $112,000 $ 64,000 $            28,125 $    5,625 $209,750
Work in process No, Sold No, Sold No, Completed Yes
Work in Process as on October 31 Job 108 $    5,625
f. Cost of Goods Sold
Beginning Finished Goods Inventory $           -  
Add: Cost of Goods Manufactured $204,125
Cost of Goods available for sale $204,125
Less: Ending finished goods inventory Job 107 $ -28,125
Cost of Goods Sold Job 105 and 106 $176,000
g. Finished goods inventory on October 31
Finished Goods Inventory Job 107 $ 28,125
Direct Material $                 8,000
Direct Labor $               12,000
Manufacturing Overheads $                 8,125
(Machine Hours*$25 Rate in a)
$               28,125
Add a comment
Know the answer?
Add Answer to:
Problem 2 East Coast Colorworks produces modular office space units. The company uses a job order...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • XLS 4-27 Job order costing (LO 5) E. Cain, Ltd. produces decorative lamps in sev styles...

    XLS 4-27 Job order costing (LO 5) E. Cain, Ltd. produces decorative lamps in sev styles and finishes. The company uses a job order costing system to accumulate product costs. Because much of the production process is automated, E. Cain, Ltd. has selected machine hours as its overhead application base. In April, E. Cain, Ltd. worked on four jobs. Jobs 78 and 79 were started in March and completed and delivered to customers in April. Tob 80 was started and...

  • Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing...

    Job-Order Cost Sheets, Balance in Work in Process and Finished Goods Golding Company, a job-order costing firm, worked on three jobs in July. Data are as follows: Balance, July 1 Direct materials Direct labor Machine hours Job 106 $21,310 $10,450 $16,000 500 Job 107 $6,250 $12,300 $12,200 300 Job 108 $0 $16,150 $24,000 1,000 Overhead is applied to jobs at the rate of $16 per machine hour. By July 31, Jobs 106 and 108 were completed. Jobs 102 and 106...

  • Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...

    Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 20,500 $ 13,300 $ 0...

  • Overhead cost looks to be $25 per machine hour based on March's details XLS 4-27 Job...

    Overhead cost looks to be $25 per machine hour based on March's details XLS 4-27 Job order costing (LO 5) E. Cain, Ltd. produces decorative lamps in sev styles and finishes. The company uses a job order costing system to accumulate product costs. Because much of the production process is automated, E. Cain, Ltd. has selected machine hours as its overhead application base. In April, E. Cain, Ltd. worked on four jobs. Jobs 78 and 79 were started in March...

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,000. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $1,960 $1,780 102 2,390 2,400 103 1,590 1,170 104 5,370 4,410 105 3,410 3,360 106 2,490 2,140 For general factory use 670 2,630 Factory overhead costs incurred on account, $3,740....

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,320. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,300 $3,280 102 2,810 4,430 103 1,860 2,160 104 6,300 8,130 105 4,000 6,200 106 2,920 3,940 For general factory use 780 4,850 Factory overhead costs incurred on account, $4,390....

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: a. Materials purchased on account, $2,010. b. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,230 4,360 2,130 $2,920 3,560 2,370 8,000 5,080 3,710 990 8,010 6,100 105 106 3,880 For general factory use 4,780 c. Factory overhead costs incurred on account, $5,580....

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,110. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,440 $2,460 102 2,980 3,320 103 1,980 1,620 104 6,690 6,100 105 4,250 4,650 106 3,100 2,950 For general factory use 830 3,640 Factory overhead costs incurred on account, $4,660....

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,350. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $2,610 $2,330 102 3,180 3,150 103 2,110 1,540 104 7,150 5,780 105 4,540 4,400 106 3,310 2,800 For general factory use 890 3,450 Factory overhead costs incurred on account, $4,990....

  • Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost...

    Entries and Schedules for Unfinished Jobs and Completed Jobs Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: a. Materials purchased on account, $2,000. b. Materials requisitioned and factory labor used: Job No. Materials Factory Labor $1,960 $1,780 2.400 1,170 4,410 2,390 1,590 5,370 3,410 2,490 670 106 3,360 2.140 2,630 For general factory use c. Factory overhead costs incurred on account, $3,740. d. Depreciation...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT