Total cost of completed Job= Direct materials+Direct labor+Manufacturing overhead applied

= $120000+180000+110000= $410000

Total cost of goods sold= (Total cost of completed Job/Number of units produced)*Number of units sold

= ($410000/8000)*6000= $307500

Cost of finished goods on hand= Total cost of completed Job-Total cost of goods sold

= $410000-307500

= $102500

So, the answer is option B) $102500

Add a comment
Know the answer?
Add Answer to:
0 m CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 76 The following information is available...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • BACK Multiple Choice Question 77 Sunland Company completed Job No. B14 during 2019. The job cost...

    BACK Multiple Choice Question 77 Sunland Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials $110000 Direct labor $100000 Manufacturing overhead applied $80000 Units produced 2000 units Units sold 1800 units How much is the cost of the finished goods on hand from this job? $332000 $ 29000 $290000 $261000

  • Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials....

    Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials. $20000; direct labor, $80000; manufacturing overhead applied $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $25000 O $110000 $27500. $82500 Save for Later Attempts: 0 of 1 used Submit Answer MacBook Air esc 2 3 % 5 &

  • the cost of the finished goods on hand from this job is? View Policies Current Attempt...

    the cost of the finished goods on hand from this job is? View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $20000; direct labor, $80000; manufacturing overhead applied, $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $82500. $25000 $110000. $27500 Save for Later

  • CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 102 Concord Corporation is preparing its direct labor...

    CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 102 Concord Corporation is preparing its direct labor budget for May. Projections for the month are that 600 units are to be produced and that direct bor time is three hours per unit. If the labor cost per hour is $10, what is the total budgeted direct labor cost for May 000000 1023000 1038000 1008000 Click if you would like to show Work for this questioni Don Shower

  • --/1 Question 32 View Policies Current Attempt in Progress The following information is available for completed...

    --/1 Question 32 View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $220000; direct labor, $280000; manufacturing overhead applied, $210000; units produced, 5000 units; units sold, 3000 units. The cost of the finished goods on hand from this job is $426000 $710000. $200000. $284000. Save for Later Attempts: 0 of 1 used 1 used Submit Answer Sulimit Answer Send to Gradebook

  • •The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000;...

    •The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000; manufacturing overhead applied, $60,000; units produced, 5,000 units; units sold, 4,000 units. The cost of the finished goods on hand from this job is

  • Multiple choice question CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 103 SheridanCompany is authorized to...

    Multiple choice question CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 103 SheridanCompany is authorized to issue 10000 shares of 1000096, $100 par value preferred stock and 458000 shares of no-par common stock with a stated value of $1 per share. If Sheridan issues 5000 shares of preferred stock for land with an asking price of $569000 and a market value of $542000, which of the following would be the journal entry for Sheridan to record? O Land O Land...

  • CALCULATOR FULL SCREEN PRINTER VERSION NEXT BACK Multiple Choice Question 130 Vaughn Manufacturing had checks outstanding...

    CALCULATOR FULL SCREEN PRINTER VERSION NEXT BACK Multiple Choice Question 130 Vaughn Manufacturing had checks outstanding totaling $33000 on its June bank reconciliation. In July, Vaughn Manufacturing issued checks totaling $238100. The July bank statement shows that $161000 in checks cleared the bank in July, A check from one of Vaughn Manufacturing's customers in the amount of $1800 was also returned marked "NSF" The amount of outstanding checks on Vaughrn Manufacturing's July bank reconciliation should be O$44100. $77100 O$110100 $108300...

  • Veyyalul Mallaydilal ACCOUNY, UE CALCULATOR MESSAGE MY INSTRUCTOR STANDARD VIEW PRINTER VERSION BACK Exercise 2-6 (Video)...

    Veyyalul Mallaydilal ACCOUNY, UE CALCULATOR MESSAGE MY INSTRUCTOR STANDARD VIEW PRINTER VERSION BACK Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given below. 469 2.500 JOB NO. ITEM FOR 7/2 Job Cost Sheet Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 800 900 7/31 Manufacturing Overhead Date 7/10 400 500 375 300 1,600 1,575 600 750 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost...

  • CALCULATOR FULL SCREEN PRINTER VERSION BACK NEXT Problem 15-01A Lott Company uses a job order cost...

    CALCULATOR FULL SCREEN PRINTER VERSION BACK NEXT Problem 15-01A Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $22.800, direct labor $13.680, and manufacturing overhead $18,240. As of January 1, Job 49 had been completed at a cost of $102,600 and was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT