a. filling partially filled out scenario inputs:
sales units best case: +10%*300 = 30, total sales units best case= 300+30 =330
Fixed cost best case: -10%*328000 = 32800, total fixed cost best case = 328000-32800 = 295200
cost/unit worst case: -10%*15700=1570, total cost/unit worst case = 15700+1570 = 17270
Note: cost gets added for worst case, and costs gets reduced for best case.
the scenario table would be as follows:
| scenario | units | price/unit | cost/unit | fixed cost |
| best(+10%) | 330 | 19200 | 14130 | 295200 |
| base | 300 | 19200 | 15700 | 328000 |
| worst(-10%) | 270 | 19200 | 17270 | 360800 |
operational cash flows formula= (sales -cost -depreciation)*(1-T) + Depreciation
here, depreciation = (982000-0)/4 = 245500 per yr
for best case: sales price = 330*19200 = 6336000
total cost = 330*14130 + 295200 = 4958100
A.OCF for best case = (6336000-4958100-245500)*(1-0.4) + 245500 = 924940
B.similarly for OCF for worst case = (5184000-5023700-245500)*(1-0.4) + 245500 = 194380
NPV = -intial investment + OCF/(1+r)^n , here n =4, r = 12%, initial investment = 982000, OCF is given above for each of the four yrs,
D.NPV for best case = -982000+ (924940/1.12^1) +(924940/1.12^2) +...….(924940/1.12^4) = -1827365.9
C.NPV for worst case = -928000+ (194380/1.12^1)………(194380/1.12^4) = -391600.03
need to see how you got to the answer 6) 25 Points You are considering a...
You are considering a new product launch. The project will cost $860,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 250 units per year; price per unit will be $16,500, variable cost per unit will be $11,500, and fixed costs will be $575,000 per year. The required return on the project is 12 percent, and the relevant tax rate is 23 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $920,000, have a 5-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 310 units per year; price per unit will be $15,915, variable cost per unit will be $11,800, and fixed costs will be $605,000 per year. The required return on the project is 10 percent and the relevant tax rate is 24 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $910,000, have a 5-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 300 units per year; price per unit will be $15,905, variable cost per unit will be $11,750, and fixed costs will be $600,000 per year. The required return on the project is 9 percent and the relevant tax rate is 23 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $857,000, have a four-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 180 units per year; price per unit will be $19,200, variable cost per unit will be $15,100, and fixed costs will be $345,000 per year. The required return on the project is 11 percent, and the relevant tax rate is 34 percent. Requirement 1: Based on your experience, you think...
You are considering a new product launch. The project will cost $800,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 190 units per year; price per unit will be $16,350, variable cost per unit will be $11,200, and fixed costs will be $545,000 per year. The required return on the project is 10 percent and the relevant tax rate is 22 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $800,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 190 units per year; price per unit will be $16,350, variable cost per unit will be $11,200, and fixed costs will be $545,000 per year. The required return on the project is 10 percent and the relevant tax rate is 22 percent. Based on your experience, you think the unit...
Can you answer/correct the variable cost portion for me
please?
You are considering a new product launch. The project will cost $2,350,000, have a four- year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 330 units per year; price per unit will be $19,600, variable cost per unit will be $14,000, and fixed costs will be $720,000 per year. The required return on the project is 10 percent, and the relevant tax rate...
You are considering a new product launch. The project will cost $830,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 220 units per year; price per unit will be $16,425, variable cost per unit will be $11,350, and fixed costs will be $560,000 per year. The required return on the project is 9 percent and the relevant tax rate is 25 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $860,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 250 units per year, price per unit will be $16,500, variable cost per unit will be $11,500, and fixed costs will be $575,000 per year. The required return on the project is 12 percent and the relevant tax rate is 23 percent. Based on your experience, you think the unit...
You are considering a new product launch. The project will cost $820,000, have a 4-year life, and have no salvage value; depreciation is straight-line to zero. Sales are projected at 210 units per year; price per unit will be $16,400, variable cost per unit will be $11,300, and fixed costs will be $555,000 per year. The required return on the project is 12 percent and the relevant tax rate is 24 percent. Based on your experience, you think the unit...