Answer
| december 31 2020 | december 31 2021 | |||
| (a) | balance in land account | 152640 | 152640 | |
| (b) | balance in building account | 44160 | 706560 | |
| (c) | balance in interest expense | 4527 | 58851 | |
note* i have assumed simple interest on loan
WORKING NOTES
land account 31 december 2020
| date | particular | amount | date | particular | amount |
| dec1 2020 | to cash | 142800 | 1 dec 2020 | by cash | 720 |
| dec1 2020 | to survey cost | 2880 | 31 dec 2020 | by balance carried down | 152640 |
| dec 1 2020 | to insurance policy |
4320 |
|||
| dec 1 2020 | to demolition expense | 3360 | |||
| 153360 | 153360 |
land account 31 december 2021
| date | particular | amount | date | particular | amount |
| 1 jan 2021 | to balance brought down | 152640 | 31 dec | by balance carried down | 152640 |
| 152640 | 152640 | ||||
| 1 jan 2022 | to balance brought down | 152640 | |||
building account as on 31 december 2020
| date | particular | amount | date | particular | amount |
| dec 1 2020 | To architecture cost | 40800 | 31 dec 2020 | by balance carried down | 44160 |
| dec 1 2020 | To building permit expense | 3360 | |||
| 44160 | 44160 |
building account as on 31 december 2021
| date | particular | amount | date | particular | amount |
| 1 jan 2021 | to balance brought down | 44160 | 31 december 2021 | by balance carried down | 706560 |
| 1 march 2021 | to bank | 264000 | |||
| 1 May 2021 | to bank | 334800 | |||
| 1 may 2021 | to bank | 63600 | |||
| 706560 | 706560 |
interest expense account as on 31 december 2020
| date | particular | amount | date | particular | amount |
| 31 dec 2020 | to balance carried down | 4527 | 31 dec 2020 | interest payable account (603600 *9% /12) | 4527 |
| 4527 | 4527 |
interest expense accounts on december 2021
| date | particular | amount | date | particular | amount |
| 31 dec 2021 | to balance carried down | 58851 | 1 jan 2021 | by balance brought down | 4527 |
| 1 dec 2021 | by interest payable account | 49797 | |||
| 31 dec 2021 | by interest payable account | 4527 | |||
| 58851 | 58851 | ||||
i request you to give me a thumbs up if you are satisfied with my answers.
x Your answer is incorrect. Oriole Landscaping began construction of a new plant on December 1,...
Oriole Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $142,800 in cash. In addition, it paid $2,880 in surveying costs and $4,320 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $40,800. The necessary...
Sheridan Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary...
Problem 10-6 Larkspur Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $140,400 in cash. In addition, it paid $2,640 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $1,200 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $34,800....
I
just can’t figure out why I am getting the 2018 building and
interest wrong and everything else right
ment CALCULATOR FULL SCREEN PRINTER VERSION BACK NEXT Grouper Landscaping began construction of a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $139,200 in cash. In addition, it paid $1,920 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 74 October 1, 2020 42 February 1, 2021 50 April 1, 2021 31 September 1, 2021 30 October 1, 2021 16 On July 1, 2020, Crocus obtained a $90 million construction loan with a 6% interest rate. The loan was outstanding through the end of...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021 Expenditures on the project were as follows is in millions) July 1, 2020 October 1, 2020 February 1.2021 April 1. 2021 September 1, 2021 October 1.2021 On July 1, 2020. Crocus obtained a $106 million construction loan with a 10% interest rate The loan was outstanding through the end of October, 2021 The company's only other interest-bearing debt...
Oriole Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $1,884,000 on March 1, $1,284,000 on June 1, and $3,049,820 on December 31. Oriole Company borrowed $1,038,290 on March 1 on a 5-year, 13% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 5-year, $2,241,900 note payable and an 11%, 4-year, $3,500,300 note payable. Compute the weighted-average interest rate used for interest...
Oriole Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $3,060,000 on March 1, $2,040,000 on June 1, and $5,100,000 on December 31. Oriole Company borrowed $1,700,000 on March 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 12%, 5-year, $3,400,000 note payable and an 11%, 4-year, $5,950,000 note payable. Compute avoidable interest for Oriole Company. Use the...
On January 2, 2020, Vaughn Manufacturing began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 599000 September 1, 2020 1801200 December 31, 2020 1801200 March 31, 2021 1801200 September 30, 2021 1220000 Vaughn Manufacturing borrowed $3230000 on a construction loan at 10% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
On January 2, 2020, Bonita Industries began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 September 1, 2020 December 31, 2020 March 31, 2021 September 30, 2021 $ 609000 1812000 1812000 812000 198000 1 1 Bonita Industries borrowed $3290000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period....