Marcelino Co.'s March 31 inventory of raw materials is $84,000.
Raw materials purchases in April are $580,000, and factory payroll
cost in April is $379,000. Overhead costs incurred in April are:
indirect materials, $54,000; indirect labor, $25,000; factory rent,
$32,000; factory utilities, $21,000; and factory equipment
depreciation, $52,000. The predetermined overhead rate is 50% of
direct labor cost. Job 306 is sold for $675,000 cash in April.
Costs of the three jobs worked on in April follow.
| Job 306 | Job 307 | Job 308 | ||||||||||
| Balances on March 31 | ||||||||||||
| Direct materials | $ | 32,000 | $ | 37,000 | ||||||||
| Direct labor | 24,000 | 15,000 | ||||||||||
| Applied overhead | 12,000 | 7,500 | ||||||||||
| Costs during April | ||||||||||||
| Direct materials | 133,000 | 205,000 | $ | 110,000 | ||||||||
| Direct labor | 102,000 | 151,000 | 101,000 | |||||||||
| Applied overhead | ? | ? | ? | |||||||||
| Status on April 30 | Finished (sold) | Finished (unsold) | In process | |||||||||
| No | Transaction | General Journal | Debit | Credit |
|---|---|---|---|---|
| 1 | a. | Raw materials inventory | 580,000 | |
| Accounts payable | 580,000 | |||
| 2 | b. | Work in process inventory | 448,000 | |
| Raw materials inventory | 448,000 | |||
| 3 | c. | Factory overhead | 379,000 | |
| Cash | 379,000 | |||
| 4 | d. | Factory overhead | 25,000 | |
| Factory overhead | 25,000 | |||
| 5 | e. | Work in process inventory | 177,000 | |
| Factory overhead | 177,000 | |||
| 6 | f(1). | Factory overhead | 54,000 | |
| Raw materials inventory | 54,000 | |||
| 7 | f(2). | Factory overhead | 32,000 | |
| Cash | 32,000 | |||
| 8 | f(3). | Factory overhead | 21,000 | |
| Accumulated depreciation-factory equipment | 21,000 | |||
| 9 | f(4). | Factory overhead | 52,000 | |
| Accumulated depreciation-factory equipment | 52,000 | |||
| 10 | g. | Finished goods inventory | ||
| Work in process inventory | ||||
| 11 | h. | Cost of goods sold | ||
| Finished goods inventory | ||||
| 12 | i. | Accounts payable | 675,000 | |
| Sales | 675,000 | |||
| 13 | j. | Cost of goods sold | ||
| Factory overhead |
|
|||||||||||||||||||||||
Compute gross profit for April.
|
|||||
Show how to present the inventories on the April 30 balance sheet.
|
|||||||||||
| Job 306 | Job 307 | Job 308 | |
| Direct material | $32,000 | $37,000 | |
| Direct labor | 24,000 | 15,000 | |
| Applied overhead | 12,000 | 7,500 | |
| Total | 68,000 | 59,500 | |
| Cost during April | |||
| Direct materials | 133,000 | 205,000 | 110,000 |
| Direct labor | 102,000 | 151,000 | 101,000 |
| Applied overhead@50% | 51,000 | 75,500 | 50,500 |
| Total | 354,000 | 491,000 | 261,500 |
| Status on April 30 | Finished (sold) | Finished (unsold) | In process |
| Indirect materials | $54,000 |
| Indirect labor | 25,000 |
| Factory rent | 32,000 |
| Factory utilities | 21,000 |
| Factory equipment depreciation | 52,000 |
| Actual overhead | 184,000 |
| Applied overhead ($51,000+75,500+50,500) | 177,000 |
| Underapplied overhead | $7,000 |
| g | Finished goods inventory ($354,000+491,000) | $845,000 | |
| Work in process inventory | $845,000 | ||
| h | Cost of goods sold | $354,000 | |
| Finished goods inventory | $354,000 | ||
| j | Cost of goods sold | $7,000 | |
| Factory overhead | $7,000 |
|
MARCELINO COMPANY Schedule of Cost of Goods Manufactured For Month Ended April 30 |
|
| Direct material used ($133,000+205,000+110,000) | $448,000 |
| Direct labor | 354,000 |
| Factory overhead applied | 177,000 |
| Total manufacturing cost | 979,000 |
| Add: Work in process April 1 (68,000+59,500) | 127,500 |
| Less: Work in process April 30 | (261,500) |
| Less: Underapplied overhead | (7,000) |
| Cost of goods manufactured | $838,000 |
Gross profit = Sales - Adjusted cost of goods sold
Gross profit = $675,000 - 361,000 (354,000+7,000) = $314,000
| Inventories | |
| Raw materials ($84,000+580,000-448,000) | $216,000 |
| Work in process | 261,500 |
| Finished goods | 491,000 |
| Total inventories | $968,500 |
Marcelino Co.'s March 31 inventory of raw materials is $84,000. Raw materials purchases in April are...
Marcelino Co.'s March 31 inventory of raw materials is
$84,000. Raw materials purchases in April are $560,000, and factory
payroll cost in April is $382,000. Overhead costs incurred in April
are: indirect materials, $56,000; indirect labor, $26,000; factory
rent, $32,000; factory utilities, $23,000; and factory equipment
depreciation, $61,000. The predetermined overhead rate is 50% of
direct labor cost. Job 306 is sold for $695,000 cash in April.
Costs of the three jobs worked on in April
follow.
(The following information...
Marcelino Co.'s March 31 inventory of raw materials is $84,000. Raw materials purchases in April are $520,000, and factory payroll cost in April is $379,000. Overhead costs incurred in April are: indirect materials, $51,000; indirect labor, $22,000; factory rent, $38,000; factory utilities, $21,000; and factory equipment depreciation, $56,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $630,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $85,000. Raw materials purchases in April are $510,000, and factory payroll cost in April is $386,000. Overhead costs incurred in April are: indirect materials, $52,000; indirect labor, $25,000; factory rent, $36,000; factory utilities, $19,000; and factory equipment depreciation, $52,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $640,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $80,000. Raw materials purchases in April are $500,000, and factory payroll cost in April is $363,000. Overhead costs incurred in April are: indirect materials, $50,000; indirect labor, $23,000; factory rent, $32,000; factory utilities, $19,000; and factory equipment depreciation, $51,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $635,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $85,000. Raw materials purchases in April are $580,000, and factory payroll cost in April is $385,000. Overhead costs incurred in April are: indirect materials, $59,000; indirect labor, $28,000; factory rent, $33,000; factory utilities, $21,000; and factory equipment depreciation, $52,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $635,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $85,000. Raw materials purchases in April are $530,000, and factory payroll cost in April is $385,000. Overhead costs incurred in April are: indirect materials, $58,000; indirect labor, $28,000; factory rent, $30,000; factory utilities, $20,000; and factory equipment depreciation, $58,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $700,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $89,000. Raw materials purchases in April are $540,000, and factory payroll cost in April is $390,000. Overhead costs incurred in April are: indirect materials, $53,000; indirect labor, $28,000; factory rent, $30,000; factory utilities, $22,000; and factory equipment depreciation, $60,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $690,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $86,000. Raw materials purchases in April are $570,000, and factory payroll cost in April is $379,000. Overhead costs incurred in April are: indirect materials, $52,000; indirect labor, $24,000; factory rent, $30,000; factory utilities, $20,000; and factory equipment depreciation, $56,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $695,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co.'s March 31 inventory of raw materials is $86,000. Raw materials purchases in April are $520,000, and factory payroll cost in April is $380,000. Overhead costs incurred in April are: indirect materials, $53,000; indirect labor, $21,000; factory rent, $39,000; factory utilities, $22,000; and factory equipment depreciation, $57,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $640,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...
Marcelino Co's March 31 inventory of raw materials is $82,000. Raw materials purchases in April are $570,000, and factory payroll cost in April is $388,000. Overhead costs incurred in April are: indirect materials, $56,000; indirect labor, $28,000; factory rent, $31,000; factory utilities, $19,000; and factory equipment depreciation, $54,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $645,000 cash in April. Costs of the three jobs worked on in April follow. Job 306 Job...