Question

William Company is contemplating the establishment of an activil applies all overhead costs based on direct labor costs. The

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  1. 1. Items of Cost Pool are as follows:
  • Machine Set ups
  • Utilities
  • Material Handling

2. Cost Drivers are as follows:

  • Setups Implemented
  • Usage of utility hours
  • Crates Handled

              3. Cost Objectives are as follows:

  • Buckets
  • Pails
  1. Product Cost Per Pail if one cost pool is used to allocate all overheads=$ 2.58

Explanation:

Total Overheads=$ 177600

Total Direct Labor Hours=1776 hours($ 35520/$ 20)

Therefore Overheads per direct labor hour=$ 100 per direct labor hour

Particulars

Amount

Direct Material

$ 31200

Direct Labor

$ 12000

Overheads(600 direct labor hours* $ 100 per hour)

$ 60000

Total Cost

$ 103200

Total Units

40000

Cost per unit of pail

$ 2.58

  1. Product Cost Per Pail if ABC is used to allocate all overheads=$ 3.50

Explanation:

Cost Pool

Cost

Cost Driver

Cost/Cost Driver

Machine Setups

$ 33600

Setups

(400 set ups)

$ 84 /set up

Utilities

$ 60000

Usage Hours

(200000 hours)

$ 0.3 per utility hour

Material Handling

$ 84000

Crates

(12500 crates)

$ 6.72 per crate

Allocation of Cost for Pails

Particulars

Cost

Direct Material

$ 31200

Direct Labor

$ 12000

Machine Setups( 290 setups* $ 84 per set up)

$ 24360

Utilities( 125000 utility hours* $ 0.3 per utility hour)

$ 37500

Material Handling( 5200 crates* $ 6.72 per crate)

$ 34944

Total Cost

$ 140004

Total Units Produced

40000

Cost Per unit

$ 3.50

                                            

Add a comment
Know the answer?
Add Answer to:
William Company is contemplating the establishment of an activil applies all overhead costs based on direct...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem #3 15 Points William Company is contemplating the establishment of an activity-based costing (ABC) system. It c...

    Problem #3 15 Points William Company is contemplating the establishment of an activity-based costing (ABC) system. It currently applies all overhead costs based on direct labor costs. The company has estimated the following costs and activities for May: Table 1: | Cost Activity Machine Setups $33,600 400 setups Utilities 60,000 200,000 usage hours Materials Handling 84,000 12,500 crates Direct labor 35,520 $20 per labor hour Direct material 60,000 $1 per pound Direct labor cost is $20 per hour. The following...

  • Answer in excel 2. Direct labor budget: ABC Company plans to produce a number of plastic...

    Answer in excel 2. Direct labor budget: ABC Company plans to produce a number of plastic pails during the budget period. The pails are all within a limited size range, so the amount of processing labor related to each one is nearly identical. The labor routing for each pail is 0.1 hours per pail for the machine operator. The labor rate for machine operators is $25 per direct labor hour. Production for each quarter is as follows: Quarter 1 6,500...

  • Lane Company manufactures a single product and applies overhead cost to that product using standard direct...

    Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.80 per direct labor-hour and the budgeted fixed manufacturing overhead is $612,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $5.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.40 per hour. The company planned to operate at a...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000 The following additional data were provided for Job 845: Direct material costs $ 8,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours)...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Glassman Company consisted of the following activities and costs: Setup (1,000 setup hours) $ 146,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 90,000 Supervision (2,000 direct labor hours) 56,000 Machine maintenance (12,000 machine hours) 96,000 Total activity costs $ 448,000 The following additional data were provided for Job 845: Direct material costs $ 8,000 Direct labor cost (5 Milling direct labor hours; 35 Finishing direct labor hours)...

  • 2 Direct labor budet ABC Company plans to all within a limited size range identical. The...

    2 Direct labor budet ABC Company plans to all within a limited size range identical. The labor rate for machine operators is y plans to produce a number of plastic pails during the budget period. The pails are med sine range, so the amount of processing labor related to each one is nearly he labor routing for each pailis 0.1 hours per pail for the muchine operator. The labor the operators is 525 per direct labor hour. Production for each...

  • Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...

    Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...

  • A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the...

    A manufacturing company applies factory overhead based on direct labor hours. At the beginning of the year, it estimated that factory overhead costs would be $482,910 and direct labor hours would be 48,291. Actual factory overhead costs incurred were $520,224, and actual direct labor hours were 54,190. What is the amount of overapplied or underapplied manufacturing overhead at the end of the year? a. $58,990 underapplied b. $21,676 overapplied c. $541,900 overapplied d. $21,676 underapplied A manufacturing company applies factory...

  • Pro blem 2 (Supplemental Problem #2)-Activity-based costing versus traditional costing sunglasses. The company uses a normal...

    Pro blem 2 (Supplemental Problem #2)-Activity-based costing versus traditional costing sunglasses. The company uses a normal cos based on direct labor hours Lovelace Company produces only two products: reading glasses and sung system and overhead costs are currently allocated using a plant-wide overhead rate products. Itants have recommended that the company use activity-based costing to charge overhead to he company expects to produce 4,000 reading glasses and 8,000 sunglasses this year. Each pair of reading glasses requires two direct labor...

  • Lane Company manufactures a single product and applies overhead cost to that product using standard direct...

    Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $5.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,679,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $11.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.70 per hour. The company planned to operate at a...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT