| $ | Period | Average expenditure | |
| Accumulated expenditure Jan 1 | 693000 | 9/9 | 693000 |
| Feb. 28 | 95400 | 7/9 | 74,200 |
| Apr. 30 | 185400 | 5/9 | 103,000 |
| Jul. 1 | 41400 | 3/9 | 13,800 |
| Sept. 30 | 69400 | 0 | 0 |
| Average Accumulated expenditure | 1,084,600 | 884,000 | |
| Interest to be capitalized = 884000*10%*9/12= $66,300 | |||
| Completed lost of Library = 1084600+66300= $1,150,900 | |||
IN CASE OF ANY DOUBTS OR CORRECTIONS FEEL FREE TO COMMENT BELOW
PLEASE RATE MY ANSWER BY HITTING ??
THANK YOU
actice final exam Saved Montgomery Industries spent $660,000 in 2015 on a construction project to build...
Montgomery Industries spent $530,000 in 2015 on a construction project to build a library. Montgomery also capitalized $26,500 of interest on the project in 2015. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2016. Additional expenditures in 2016 were as follows: Feb. 28 Apr. 30 Jul. 1 Sept. 30 $ 83,700 173,700 29,700 57,700 Required: Determine the completed cost of the library. (Do not round intermediate calculations.) Completed cost of...
5. Montgomery Industries spent $590,000 in 2017 on a construction project to build a library. Montgomery also capitalized $29,500 of interest on the project in 2017. Montgomery financed 100% of the construction with a 8% construction loan. The project was completed on September 30, 2018. Additional expenditures in 2018 were as follows: Feb. 28 $ 89,100 Apr. 30 179,100 Jul. 1 35,100 Sept. 30 63,100 Required: Determine the completed cost of the library.
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...
Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...