Part (a)
Flexible budget for the month ending 31st January 19X4
Please see the table. Please see the column titled "Working" for understanding the calculation of each item:
|
Parameter |
Working |
Value ($) |
|
Direct materials |
= 7800 units x 3 pounds x $ 2.5 / pound |
58,500 |
|
Direct labor |
= 7800 units x 5 hours x $ 7.5 / hour |
292,500 |
|
Factory Overheads |
||
|
- Variable |
= 7800 units x 5 hours x $ 3 / hour |
117,000 |
|
- Fixed |
= 40000 hours x $ 4 / hour |
160,000 |
|
Total budgeted production costs |
Sum of all the above |
628,000 |
Part (b)
Sub part: 1
Direct materials price variance based on materials purchased = (Actual cost per unit - Standard cost per unit) x actual material purchased = (2.60 - 2.50) x 25,000 = $ 2,500, Unfavorable (as actual cost per unit > standard cost per unit)
Sub part: 2
Direct materials usage variance = (Actual quantity used - standard quantity to be used) x standard cost per unit = (23,100 - 3 x 7,800) x 2.50 = - $ 750, Favorable (as actual quantity used is lower than the standard quantity)
Sub part: 3
Direct labor rate variance = (Actual labour rate - standard labour rate) x actual direct labor = (7.30 - 7.50) x 40,100 = - $ 8,020, Favorable (as actual labor rate < standard labor rate)
Sub part: 4
Direct labor efficiency variance = (Actual nos. of labour hours - standard nos. of labour hours) x standard labor rate = (40,100 - 5 x 7,800) x 7.50 = $ 8,250 Unfavorable (as actual nos. of labor hours > standard nos. of labor hours)
Sub part 5:
Factory overhead spending variance = Actual total factory overhead - budgeted total factory overhead at actual production volume
Actual total factory overhead = $ 300,000
Budgeted total factory overhead at actual production volume = Budgeted variable overhead at actual production volume + budgeted fixed overhead = 3 x 40,100 + 4 x 40,000 = $ 280,300
Factory overhead spending variance = Actual total factory overhead - budgeted total factory overhead at actual production volume = 300,000 - 280,300 = $ 19,700 Unfavorable (as actual overhead > budgeted overhead)
Sub part 6:
Variable factory overhead efficiency variance = Budgeted total factory overhead at actual hours - Budgeted total factory overhead at standard hours
Budgeted total factory overhead at actual hours = 280,300 (calculated in sub part 5 above)
Budgeted total factory overhead at standard hours = 117,000 + 160,000 = 277,000 (please see the production budget prepared in part (a)
Variable factory overhead efficiency variance = Budgeted total factory overhead at actual hours - Budgeted total factory overhead at standard hours = 280,300 - 277,000 = $ 3,300 Unfavorable
Sub part 7:
Factory overhead volume variance = Budgeted total factory overhead at standard hours - Applied total factory overhead
Budgeted total factory overhead at standard hours = 277,000 (as calculated in sub part 6 above)
Applied total factory overhead = actual production volume x standard labor hours x (Standard Variable overhead per direct labor hour + Standard fixed overhead per labor hour) = 7,800 x 5 x (3 + 4) = 273,000
Factory overhead volume variance = Budgeted total factory overhead at standard hours - Applied total factory overhead = 277,000 - 273,000 = 4,000 Unfavorable
At the beginning of 19X4, Beal Company adopted the following standards: Direct material (3 pounds &$2.50...
Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.50 per pound $7.50 Direct labor 5 hours at $7.50 per hour 37.50 Actual results: Units produced Direct materials purchased 7,800 units 26,000 pounds at $2.70 23,100 pounds at $2.70 $70,200 Direct materials used 62,370 Direct labor 40,100 hours at $7.30 292,730 The direct-labor rate variance is: O$7,800F. O$7.950F $8,020F. O$8,000U None of these.
The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ $4 per pound = $12 per unit Direct labor: 2 hours per unit @ $8 per hour = $16 per unit Variable manufacturing overhead: 2 hours per unit @ $5 per hour = $10 per unit Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased. Units produced 600 units Direct material used .......
The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ 84 per pound = $12 per unit Direct labor: 2 hours per unit @ $8 per hour = $16 per unit Variable manufacturing overhead: 2 hours per unit @ $5 per hour = $10 per unit Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased. 600 units 2,000 pounds $11,400 $9,240 $5,720 Units...
The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ $4 per pound $12 per unit Direct labor: 2 hours per unit @ $8 per hour = $16 per unit Variable manufacturing overhead: 2 hours per unit@ $5 per hour $10 per unit Actual production figures for the past year are given below The company records the materials price variance when materials are purchased Units produced.. 600 units 2,000 pounds si1,400 S9,240 S5,720 Direct material...
The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ S4 per pound = $12 per unit Direct labor: 2 hours per unit @ $8 per hour = $16 per unit Variable manufacturing overhead: 2 hours per unit @ $5 per hour = $10 per unit Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased. Units produced.. 600 units Direct material used. ..............
$ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds at $2.50 per pound Direct labor 5 hours at $7.50 per hour Actual results: Units produced 7,800 units Direct material purchased 26,000 pounds at $2.70 Direct material used 23,100 pounds at $2.70 Direct labor 40,100 hours at $7.30 $ 70,200 62,370 292,730 Assume that the company computes variances at the earliest point in time. The direct-labor rate variance is: Multiple Choice 0 $7,800F. 0...
Direct Materials and Direct Labor Variances At the beginning of June, Kimber Toy Company budgeted 12,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: Direct materials Direct labor $18,000 11,760 $29,760 Total The standard materials price is $0.60 per pound. The standard direct labor rate is $14.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: Actual direct materials $16,400 Actual...
36 $ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds at $2.50 per pound Direct labor 5 hours at $7.50 per hour Actual results: Units produced 8,100 units Direct material purchased 26,600 pounds at $2.70 Direct material used 24,000 pounds at $2.70 Direct labor 41,100 hours at $7.30 (8 04:26:11 $ 71,820 64,800 300,030 Print Assume that the company computes variances at the earliest point in time. The direct-material price variance is: Multiple...
2.
The standards for product V28 call for 7.6 pounds of a raw material that costs $18.00 per pound. Last month, 1,500 pounds of the raw material were purchased for $26,700. The actual output of the month was 170 units of product V28. A total of 1,400 pounds of the raw material were used to produce this output. The direct materials purchases variance is computed when the materials are purchased. Required: a. What is the materials price variance for the...
Direct Material Variances Goldman, Inc. is a manufacturer of lead crystal glasses. The standard direct materials quantity is 0.7 pounds per glass at the cost of $0.35 per pound. The actual result for one month’s production of 6,950 glasses was 1.3 pounds per glass, at the cost of $0.45 per pound. Calculate the direct materials cost variance and the direct materials efficiency variance. Direct Labour Variances Goldman, Inc. manufactures lead crystal glasses. The standard direct labor time is 0.5 hours...