NPV=TVECF−TVIC
where:
TVECF=Today’s value of the expected cash flows
TVIC=Today’s value of invested cash
a.
In case of small facility-
NPV in case of low demand=TVECF−TVIC =9 million-9 million=0 million
NPV in case of high demand=TVECF−TVIC =12 million-9 million=3 million
Expected NPV for small facility=Σ (p × Scenario NPV) =(0.6*0 million)+(0.4*3 million)= 1.2 million
In case of large facility-
NPV in case of low demand=TVECF−TVIC =12 million- 10 million=2 million
NPV in case of high demand=TVECF−TVIC =15 million-10 million=5 million
Expected NPV for small facility=Σ (p × Scenario NPV) =(0.6*2 million)+(0.4*5 million)= 1.2 million+ 2 million=3.2 million
In case of No New facility-
NPV= zero
| PLANS | NPV |
| SMALL FACILITY | 1.2 MILLION |
| DO NOTHING | 0 MILLION |
| LARGE FACILITY | 3.2 MILLION |
b. Best decision is to build large facility as the NPV is more
in this case.
Expando, Inc. is considering the possibility of building an additional factory that would produce a new...
Expando, Inc. is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
Expando, Inc. is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $5 million. If demand for new products is low, the company expects to receive $9 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
Problem 5-8 Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $7 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high,...
Problem 5-4 AlwaysRain Irrigation, Inc., would like to determine capacity requirements for the next four years. Currently two production lines are in place for making bronze and plastic sprinklers. Three types of sprinklers are available in both bronze and plastic: 90-degree nozzle sprinklers, 180-degree nozzle sprinklers, and 360-degree nozzle sprinklers. Management has forecast demand for the next four years as follows: YEARLY DEMAND 1 (IN 000s) 2 (IN 000s) 3 (IN 000s) 4 (IN 000s) Plastic 90 Plastic 180 Plastic...
For number 2, I need help with part C.
BELOW THESE ARE WRONG ANSWERS FOR NUMBER 2.
1.092
30.876
17.575
41.425
Demand for a book at Amazon.com is 220 units per week. The product is supplied to Amazon from a factory. The factory charges Amazon $8 per book, while the total cost of shipping an order from the factory to the Amazon, when the shipment size is Q, is given by Shipment cost = $60 + 20 Assume the annual...
HOMIE food manufacturing company needs to make capacity decisions to produce a new product line to export to the regional market. As chief operations officer of this company, you are considering three options in the face of considerable uncertainties over the next four years: Option 1: Build a new factory, - New site cost is $6 million, - Payoffs: Strong demand = $12 million; Weak demand= $10 million. Option 2: Expand at current site, - Expanding current site cost is...
The Managing Director of a company is deciding whether to build a large or small additional production facility to ensure that the company has sufficient operating capacity to satisfy current and future sales demand. In consultation with the company’s senior management accountant, the following two possible scenarios in terms of the net present value of future cash flows from the alternatives are being considered. Possible Outcome Low Demand High Demand Action Build small facility £700,000 £520,000 Build large facility £420,000...
show all work, please and thank you
1. A firm that plans to expand its product line must decide whether to build a small or a large facility to produce the new products. If it builds a small facility and demand is low, the net present value after deducting for building costs will be $400,000. If demand is high, the firm can either maintain the small facility or expand it. Expansion would have a net present value of$450,000 and maintaining...
Dowlings Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of $6,000,000 and would generate annual net flows of $1,200,000 per year for 9 years. Calculate the project's NPV using a discount rate of 3 5 percent. If the discount rate is 5 percent, then the project's NPV is $
Dowling Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of $5 comma 000 comma 0005,000,000 and would generate annual net cash inflows of $1 comma 000 comma 0001,000,000 per year for 88 years. Calculate the project's NPV using a discount rate of 99 percent.