Samuelson's Work in Process inventory balance on June 30
was:
Solution:
Work in process inventory balance on June 30 = Cost of Job 476
= 900 + 600+ 800 + (600*70%)
= $2,720
Hence option "d" is correct.
Samuelson's Work in Process inventory balance on June 30 was: The Samuelson Company uses a job-order...
Question 13 points) Data for the next 2 questions: The Shaw Company uses a job-order cost system. Factory overhead is applied to jobs at the rate of 140% of direct labor cost. Jobs 475, 477, and 478 were completed during April and transferred to finished goods. Jobs 475 and 478 have been delivered to the customer. The following data were recorded for April: 100 Added During April Direct Direct Number Materials Labor $ 500 S 800 476 $ 700 $1,000...
At the beginning of June, Rhone Company had two jobs in process, Job 44 and Job 45, with the following accumulated cost information: Job 44 Job 45 Direct materials $4,850 $1,400 Direct labor 800 2,800 Applied overhead 560 1,960 Balance, June 1 $6,210 $6,160 During June, two more jobs (46 and 47) were started. The following direct materials and direct labor costs were added to the four jobs during the month of June: Job 44 Job 45 Job 46 Job...
Reconcile the balance in Work in Process Inventory with the
costs of unfinished jobs. Prepare a cost of goods manufactured
schedule for June.
Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. $4,100 $33,800 Raw Materials Inventory Work in Process Inventory Manufacturing Overhead Applied Manufacturing Overhead Incurred $5,675 $28,600 Subsidiary data...
3. calculate the ending balances of work in process and finished
goods as of June 30.
A. WIP:
B, FG:
4. calculate cost of goods sold for June.
4.5 At the beginning of June, Galway Company had two jobs in process, Job 78 and Job 79, with the following accumulated cost information: Job 79 Direct materials Direct labor Applied overhead Balance, June 1 Job 78 $1,000 600 750 $2,350 $ 800 1,000 1.250 $3,050 During June, two more jobs (80...
On August 1, Cairle Company’s work-in-process inventory consisted of three jobs with the following costs: Job 70 Job 71 Job 72 Direct materials $1,700 $2,000 $850 Direct labor 1,900 1,200 900 Applied overhead 1,330 840 630 During August, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 70 Job 71 Job 72 Job 73 Job 74 Job 75 Job 76 Direct materials $800 $1,235 $3,600 $5,000 $300 $560 $80...
Custom Cabinetry has one job in process (Job 120) as of June 30, at that time, its job cost sheet reports direct materials of $7,700, direct labor of $3,400, and applied overhead of $2,720. Custom Cabinetry applies overhead at the rate of 80% of direct labor cost. During July, Job 120 is sold (on account) for $26,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...
Applying Concepts On June 1, Delman Company's work in process inventory consisted of three jobs with the following costs: Job 40 Job 41 Job 42 Direct materials $1,000 $2,000 $700 Direct labor 1,800 1,200 800 Applied overhead 1,260 840 560 During June, four more jobs were started. Information on costs added to the seven jobs during the month is as follows: Job 40 Job 41 Job 42 Job 43 Job 44 Job 45 Job 46 Direct materials $3,000 $5,000 $4,700...
Check my work Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $7,900, direct labor of $2,800, and applied overhead of $2,520. Custom Cabinetry applies overhead at the rate of 90% of direct labor cost. During July, Job 120 is sold (on account) for $27,000, Job 121 is started and completed, and Job 122 is started and still in process at the end of the...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $8,100, direct labor of $3,700, and applied overhead of $2,960. Custom Cabinetry applies overhead at the rate of 80% of direct labor cost. During July, Job 120 is sold (on account) for $26,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...
Chapter 15 Homework Custom Cabinetry has one job in process (Job 120) as of June 30, at that time, its job cost sheet reports direct materials of $8,100. direct labor of $3,700, and applied overhead of $2.960. Custom Cabinetry applies overhead at the rate of 80% of direct labor cost. During July, Job 120 is sold on account) for $26.500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the...