Question

Mcnamee Corporations activity-based costing system has three activity cost pools-Fabricating, Setting Up, and Other. Costs i

0 0
Add a comment Improve this question Transcribed image text
Answer #1

answer.

overhead allocation cost = predetermined overhead rate * actual quantity of the overhead allocation base used by each job

overhead allocation to fabrication is machine hours at $0.25/MHs

overhead allocation to setting up cost is number of batches at $3.41/ batch

product oo uses 2250 MHs and 310 batches

formula for allocation of overhead

(machine hours used * allocation rate of MHs) + (number of batches * overhead rate of batch)

overhead cost for product Oo is

(2250 * 0.25) + (310 * 3.41) = 562.5 + 1057.1

overhead cost for product O0 is $1619.6

product O1 uses 16650 MHs and 1690 batches

thus overhead cost for product O1 is

(16650 * 0.25) + (1690 * 3.14) = 4162.5 + 5306.6

thus overhead cost for product O1 is $9469.1

Add a comment
Know the answer?
Add Answer to:
Mcnamee Corporation's activity-based costing system has three activity cost pools-Fabricating, Setting Up, and Other. Costs in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Mcnamee Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and Other Costs in...

    Mcnamee Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and Other Costs in the Fabricating cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The activity rate for Fabricating is $0.31 per MH; the activity rate for Setting Up is $3.47 per batch. The following table shows...

  • Mcnamee Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and Other. Costs in...

    Mcnamee Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and Other. Costs in the Fabricating cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The activity rate for Fabricating is $0.18 per MH; the activity rate for Setting Up is $3.34 per batch. The following table shows...

  • Sukhu Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and other. The company's...

    Sukhu Corporation's activity-based costing system has three activity cost pools--Fabricating, Setting Up, and other. The company's overhead costs have already been allocated to these cost pools as follows: Fabricating Setting Up Other $13,800 $39,900 $20,300 Costs in the Fabricating cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The following...

  • Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The...

    Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining Setting Up Other $77,832 $95,800 $ 22,500 Costs in the Machining cost pool are assigned to products based on machine-hours (MHS) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The...

  • Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's...

    Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining $ 47,250 Setting Up $ 125,354 Other $ 21,600 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to...

  • Greife Corporation's activity-based costing system has three activity cost pools --Machining, Setting Up, and Other. The...

    Greife Corporation's activity-based costing system has three activity cost pools --Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining Setting Up Other $ 47,300 $100,738 $ 16,500 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to...

  • 3. Hugle Corporation's activity-based costing system has three activity cost pools-Machining, Setting Up, and Other. The...

    3. Hugle Corporation's activity-based costing system has three activity cost pools-Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining....... Setting Up.... Other ................. $15,200 $44,800 16,000 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products....

  • 3. (7 points) Griffin Corporation's activity-based costing system has three activity cost pools-- Machining, Setting Up...

    3. (7 points) Griffin Corporation's activity-based costing system has three activity cost pools-- Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining Setting Up Other $ 41,200 9,000 $ 33,800 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are...

  • Greife Corporation's activity-based costing system has three activity cost pools-Machining, Setting Up, and Other. The company's...

    Greife Corporation's activity-based costing system has three activity cost pools-Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining Setting Up $56,754 $81,016 $18,900 Other Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The following...

  • Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's...

    Greife Corporation's activity-based costing system has three activity cost pools--Machining, Setting Up, and Other. The company's overhead costs have already been allocated to these cost pools as follows: Machining Setting Up Other $90,138 $75,651 $25,400 Costs in the Machining cost pool are assigned to products based on machine-hours (MHs) and costs in the Setting Up cost pool are assigned to products based on the number of batches. Costs in the Other cost pool are not assigned to products. The following...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT