Answer: $ 5.81 per direct labor hour
Explanation
Predetermined overhead rate = Factory overhead / direct labor hours
= $1,570,000 / 270,000 hours
= $ 5.81 per direct labor hour
Dallas Company uses a job order costing system. The company's executives estimated that direct labor would...
Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $5,130,000 (190,000 hours at $27/hour) and that factory overhead would be $1,430,000 for the current period. At the end of the period, the records show that there had been 110,000 hours of direct labor and $1,130,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? (Round your answer to two decimal places.) Multiple Choice $7.53...
Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be 52,990,000 (230.000 hours at $13/hour) and that factory overhead would be $1,530,000 for the current period. At the end of the period, the records show that there had been 210.000 hours of direct labor and S1,230,000 of actual overhead costs. Using direct labor hours as a base. what was the predetermined overhead rate? (Round your answer decimal places.) two Multiele Choice 56.02 per...
Question 28 2 pts Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $2,000,000 (200,000 hours at $10/hour) and that factory overhead would be $1.500,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,200,000 of actual overhead costs. Using direct labor hours as base, what was the predetermined overhead rate? $6.00 per direct labor hour. $7.50 per...
Hunter, Inc. uses a job order costing system. The company's executives estimated that direct labor would be $1,500,000 (150,000 hours at $15/hour) and that estimated factory overhead would be $3,000,000 for the current period. At the end of the period, the records show that there had been 180,000 hours of direct labor and $1,800,000 of actual overhead costs. Using direct labor dollars as a base, what was the predetermined overhead rate? HTML Editor y В І U A А IX...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 54,500 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost 2 ? $1,533,500 Job Omega Direct materials Direct...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $12.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 65,100 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: ? Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost ? $ 1,632,000 Job Omega Direct materials...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $12.50 per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 68,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are show below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job cost $1,674,000 Job Omega Direct materials Direct labor $...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $21.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 2,806,000 Job Omega Direct...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $13.00 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 64,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 1,620,000 Job Omega Direct...
Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $19.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 55,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials ? Direct labor ? Manufacturing overhead applied ? Total job cost $ 2,230,000 Job Omega Direct...