| If rate is 7.86% | ||||||||
| Year | Project A Cash flow | Present value formula | Present value | Year | Project B Cash flow | Present value formula | Present value | |
| 0 | -32,000 | -32,000 | -32,000 | 0 | -32,000 | -32,000 | -32,000 | |
| 1 | 18,000 | =18000/(1+7.86%)^1 | 16,688 | 1 | 12,000 | =12000/(1+7.86%)^1 | 11,126 | |
| 2 | 13,000 | =13000/(1+7.86%)^2 | 11,174 | 2 | 13,000 | =13000/(1+7.86%)^2 | 11,174 | |
| 3 | 9,000 | =9000/(1+7.86%)^3 | 7,172 | 3 | 16,000 | =16000/(1+7.86%)^3 | 12,751 | |
| NPV | 3,035 | NPV | 3,051 | |||||
| If rate is 7.92% | ||||||||
| Year | Project A Cash flow | Present value formula | Present value | Year | Project B Cash flow | Present value formula | Present value | |
| 0 | -32,000 | -32,000 | -32,000 | 0 | -32,000 | -32,000 | -32,000 | |
| 1 | 18,000 | =18000/(1+7.92%)^1 | 16,679 | 1 | 12,000 | =12000/(1+7.92%)^1 | 11,119 | |
| 2 | 13,000 | =13000/(1+7.92%)^2 | 11,162 | 2 | 13,000 | =13000/(1+7.92%)^2 | 11,162 | |
| 3 | 9,000 | =9000/(1+7.92%)^3 | 7,160 | 3 | 16,000 | =16000/(1+7.92%)^3 | 12,730 | |
| NPV | 3,001 | NPV | 3,011 | |||||
| If rate is 8.01% | ||||||||
| Year | Project A Cash flow | Present value formula | Present value | Year | Project B Cash flow | Present value formula | Present value | |
| 0 | -32,000 | -32,000 | -32,000 | 0 | -32,000 | -32,000 | -32,000 | |
| 1 | 18,000 | =18000/(1+8.01%)^1 | 16,665 | 1 | 12,000 | =12000/(1+8.01%)^1 | 11,110 | |
| 2 | 13,000 | =13000/(1+8.01%)^2 | 11,143 | 2 | 13,000 | =13000/(1+8.01%)^2 | 11,143 | |
| 3 | 9,000 | =9000/(1+8.01%)^3 | 7,143 | 3 | 16,000 | =16000/(1+8.01%)^3 | 12,698 | |
| NPV | 2,951 | NPV | 2,951 | |||||
| Answer : | ||||||||
| The crossover point is 8.01% | ||||||||
3. You are considering the following two mutually exclusive projects. The crossover point (the discount rate...
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is _percent and Project should be accepted if the required return is greater than the crossover rate. Year Project A -$33,000 21,000 13,000 13,000 Project B -$33,000 13,160 11,000 24,500 o 19.62%; В o 9.03%; А o 9.03%; В o 2223%; А 2223%; В
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$33,000 −$33,000 1 21,000 13,160 2 13,000 11,000 3 13,000 24,500 Multiple Choice 19.62%; B 9.03%; B 22.23%; A 22.23%; B 9.03%; A
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is less than the crossover rate. Year Project A Project B 0 −$31,000 −$31,000 1 12,000 20,140 2 12,000 10,000 3 20,000 12,160 Multiple Choice 11.19%; A 19.46%; A 17.93%; A 17.93%; B 11.19%; B
11. You are considering the following two mutually exclusive projects. The crossover point is _ should be accepted at a discount rate of 9 percent. percent and Project Year Project A -$ 69,000 13,000 33,000 38,000 Project B -$ 69,000 29,000 24,000 27,000 A) 15.68 percent; B B) 11.38 percent; A C) 11.38 percent; B D) 15.68 percent; A E) 14.02 percent; B.
you are considering the following two mutually exclusive projects. the crossover point is ______ and Project ______ should be accepted if the discount rate is 14 percent. year, project A, project B, 0, -43000, -43000, 1, 18000, 29000, 2, 18000, 14000, 3, 28000, 21000.
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is greater than the crossover rate. Year Project A Project B 0 −$43,000 −$43,000 1 21,500 13,760 2 13,500 11,500 3 13 ,500 26,000
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is less than the crossover rate. Year Project A Project B 0 −$45,000 −$45,000 1 21,500 13,780 2 13,500 11,500 3 13,500 26,200 PLEASE READ CAREFULLY.
You are considering the following two mutually exclusive projects. The crossover rate between these two projects is ___ percent and Project ___ should be accepted if the required return is less than the crossover rate. Year Project A Project B 0 −$35,000 −$35,000 1 21,500 13,680 2 13,500 11,500 3 13,500 25,200 18.30%; B 10.20%; A 10.20%; B 20.21%; A 20.21%; A
Crossover and NPV. Seether, Inc., has the following two mutually exclusive projects available. Year Project R Projects -$45,000 17,000 19,000 21,000 9,000 7,000 -$76,000 20,000 20,000 35,000 30,000 10,000 What is the crossover rate for these two projects? What is the NPV of each project at the crossover rate?
Crossover and NPV. Seether, Inc., has the following two mutually exclusive projects available. Year Project R Project S -$45,000 -$76,000 20,000 20,000 17,000 19,000 35,000 30,000 10,000 21,000 9,000 7,000 O12345 What is the crossover rate for these two projects? What is the NPV of each project at the crossover rate?