Question

The difference between the actual cost of the input and its planned cost is the total budget variance. the usage variance. th
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answers :

  • Option : 1) The Total budgeted Variance
  • Option :3)(Actual Hours*Standard Rate )-(Standard Hours* Standard Rate)

The difference between the actual total Cost of input and the Budgetd cost is known as the Total budgeted variance , IF the Total budget cost is more than the actual cost , Favourable variance , Vice-versa.

Labour Efficiency Variance =

( AH-SH) * Standard rate

Add a comment
Know the answer?
Add Answer to:
The difference between the actual cost of the input and its planned cost is the total...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Which of the following variances is the difference between the actual cost of the input...

    1. Which of the following variances is the difference between the actual cost of the input and its planned cost? Total labor variance Materials usage variance Total budget variance Materials price variance c 2. Which of the following conditions leads to an unfavorable price variance? It occurs when the actual usage of input is greater than the standard usage of input. It occurs when the actual price is greater than the standard price. It occurs when the standard price is...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • _ 16. The total manufacturing cost variance is a. the difference between actual costs and standard...

    _ 16. The total manufacturing cost variance is a. the difference between actual costs and standard costs for units produced b. the flexible budget variance plus the time variance c. the difference between planned costs and standard costs for units produced d. None of these choices

  • Caps L Shift 29. The difference between the split cost and the standard cost for direct...

    Caps L Shift 29. The difference between the split cost and the standard cost for direct materials is called the Select one a Materials Price Variance b Materials Usage Variance eMaterials Eficiency Variance d. Materials Budget Variance e None of the above 30. Which of the following could cause a variable overhead flexible budget variance? a Varlable overhead costs being greater than expected for the given driver usage Select one: b. Variable overhead costs being less than expected for the...

  • The difference between actual quantity of input used and the standard quantity of input used results in a Multiple...

    The difference between actual quantity of input used and the standard quantity of input used results in a Multiple Choice Controllable variance Standard variance o O Budget variance Quantity variance

  • The following data were drawn from the records of Solomon Corporation. Planned volume for year (static...

    The following data were drawn from the records of Solomon Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 4,100 units 4.00 pounds @ $1.60 per pound 2.10 hours @ $5.00 per hour $ 18,450 4,500 units 3.60 pounds @ $2.00...

  • The Lucerne Chocolate Company uses standard costs to control its manufacturing of fine chocolates. The purchasing...

    The Lucerne Chocolate Company uses standard costs to control its manufacturing of fine chocolates. The purchasing agent is responsible for material price variances while the production manager is responsible for all other variances. Operating data for the past accounting period are summarized as follows: Finished units produced total 2,900 boxes of chocolate Direct material purchased and used totaled 3,400 lbs. (pounds) The purchase price was $17.30 per lbs. Standard price per pound of chocolate is $18.00 The manufacturing standard is...

  • The following data reflect the current month's activity for Vickers Corporation. Actual total direct labor Actual...

    The following data reflect the current month's activity for Vickers Corporation. Actual total direct labor Actual hours worked Standard labor-hours allowed for actual output (flexible budget) Direct labor price variance Actual variable overhead Standard variable overhead rate per standard direct labor-hour $671,460 38,000 36,900 $ 12,540 F $154,500 $ 4.10 Variable overhead is applied based on standard direct labor-hours allowed. Required: Compute the labor and variable overhead price and efficiency variances. (Indicate the effect of each variance by selecting "F"...

  • The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard d...

    The following data were drawn from the records of Perez Corporation. Planned volume for year (static budget) Standard direct materials cost per unit Standard direct labor cost per unit Total expected fixed overhead costs Actual volume for the year (flexible budget) Actual direct materials cost per unit Actual direct labor cost per unit Total actual fixed overhead costs 3,400 units 3.50 pounds @ $1.50 per pound 2.30 hours @ $3.30 per hour $14,620 3,900 units 3.10 pounds @ $2.00 per...

  • The difference between the total actual overhead cost incurred during a period and budgeted total factory...

    The difference between the total actual overhead cost incurred during a period and budgeted total factory overhead cost for the actual quantity of the cost driver used to apply overhead is equal to the: Multiple Choice A: Total overhead spending variance. B: Total overhead efficiency variance. C: Factory overhead production-volume variance. D: Total overhead rate variance. E: Total overhead variance.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT