Solution 1:
Assembling is not a batch level activity as it is a unit level activity.
'Hence option 1 is correct.
solution 2:
Activity based overhead rate for inspection = Expected cost / Expected activity = $300,000 / 4000 = $75 per inspection
Hence option 3 is correct.
Solution 3:
In determining total manufacturing costs on the cost of goods manufactured schedule in a job order costing system, "Manufacturing overhead applied is added to the direct materials and direct labor"
Hence last option is correct.
Which of the following is not a batch-level activity! 1) Assembling 2) Inspection 3) Equipment setups...
For its inspecting cost pool, Ellsworth, Inc. expected overhead cost of $400,000 and 4,000 inspections. The actual overhead cost for that cost pool was $480,000 for 5,000 inspections. The activity-based overhead rate used to assign the costs of the inspecting cost pool to products is $120 per inspection. $80 per inspection. $96 per inspection. $100 per inspection.
ses and make sure your NAME IS UII SII 21, For its inspecting cost pool, Ellsworth, Inc. expected overhead cost of $400,000 and 4,000 inspections. The actual overhead cost for that cost pool was $480,000 for 5,000 inspections. The activity-based overhead rate used to assign the costs of the inspecting cost pool to products is A) $80 per inspection. B) $96 per inspection. C) $100 per inspection. D) $120 per inspection.
QUESTION 19 Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year Activity Cost Cost Driver Pool Ordering and Orders Receiving Machine Setup Setups Machining Assembly Inspection Cost Driver Activity Est. Overhead $120,000 500 orders 450 setups 1,500,000 125,000 MH 1,200,000 1,000,000 parts 500 inspections 297,000 Machine hours Parts |Inspections 300,000 If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $1.20 per direct...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 95000 500 orders Machine Setup Setups 274500 450 setups Machining Machine hours 1437500 125000 MH Assembly Parts 1150000 1000000 parts Inspection Inspections 275000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $0.10 per part. $6464 per...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 135000 500 orders Machine Setup Setups 310500 450 setups Machining Machine hours 1550000 125000 MH Assembly Parts 1230000 1000000 parts Inspection Inspections 315000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $7081 per order. $0.14 per...
Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 110000 500 orders Machine Setup Setups 288000 450 setups Machining Machine hours 1475000 125000 MH Assembly Parts 1180000 1000000 parts Inspection Inspections 290000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is $220 per order. $6686 per...
Owlet distractors inc. uses activity-based costing to determine product costs. Activity rates computed at the beginning of the year are used to apply manufacturing overhead costs to products. The following data concerning its activity-based costing system has been provided. Estimated overhead and activity rates, at the beginning of the year were: Estimated Expected Activity cost pools Overhead cost Activity Machine related (Machine hours) $431,200 16,000 MHs Batch setup (setups) $661,500 21,000 setups General factory (direct labor-hours) $612,150 26,500 DLHs The...
Current Attempt in Progress Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100000 for the year. Cost Driver Orders Est. Overhead $ 150000 Cost Driver Activity 500 orders Activity Cost Pool Ordering and Receiving Machine Setup Machining Assembly Inspection 324000 1587500 Setups Machine hours Parts Inspections 450 setups 125000 MH 1000000 parts 500 inspections 1260000 330000 If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is...
Unleash the Beast/ fova If 150,000 units are started into production le 50,000 units are in process at the end of the per transferred out? a. 150.000 D50,000 G100,000 d. 200.000 The following information is available oduction there was no bening was in FBESS period, how many units were complete 40.000, direct labor $180.000 manufacturing produced, 5,000 units; units sold, A. this job is a $60,000 b. $390,000 $78,000 d. $312,000 available for completa Jon po 403 Dit morale Waguring...
x Tidwell Industries has the following overhead costs and cost drivers. Direct labor hours are estimated at 100,000 for the year. Activity Cost Pool Cost Driver Est. Overhead Cost Driver Activity Ordering and Receiving Orders $ 120,000 500 orders Machine Setup Setups 297,000 450 setups Machining Machine hours 1,500,000 125,000 MH Assembly Parts 1,200,000 1,000,000 parts Inspection Inspections 300,000 500 inspections If overhead is applied using activity-based costing, the overhead application rate for ordering and receiving is Selected Answer: A....