Question

Make sure the answers are correct, well written, clear, and easy to understand. Thanks.

Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an

a-1. OCF a-2. NPV b. Worst-case NPV Best-case NPV

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A (1) Calculation of Operating Cash Flow

Depreciation = $ 3600000 / 4 = $ 900000

Particulars Calculation   

Amount ($)

Sales 20000 ton * $ 380 per ton 7600000
Less - Variable cost 20000*240 4800000
Fixed cost 850000
Depreciation 900000
profit before tax 1050000
Less - tax @ 24% 252000
profit after tax 798000
Add - Depreciation 900000

Less - increase in working capital

360000
Operating cash flow 1338000

Operating cash flow =  Net Income + Non-Cash Expenses – Increase in Working Capital

A. (2) Calculation of Estimated NPV

for calculating the NPV we use CFAT ( cash flow after tax + Deprecation)

CFAT = 798000+900000 = 1698000

Salvage value = 250000 - 24% = $ 190000

initial investment = 3600000 + 360000 = 3960000

(Amount in dollar)      

Year PVF @ 11% Cash flow Present value
0 1.00 -3960000 -3960000.0
1 0.9009 1698000 1529728.2
2 0.8116 1698000 1378096.8
3 0.7312 1698000 1241577.6
4 0.6587 1698000 1118472.6
4 0.6587 190000 ( salvage) 125153.0
4 0.6587 360000 (working capital) 237132.0
NPV $ 1673160.2

B. Best case NPV and worst case NPV after terms changed

Particulars at plus (+) at minus (-)
project cost (15%) 4140000 3060000
Salvage value (15%) 287500 212500
price change (10%) $ 418 $ 342
net working capital (5%) 378000 342000

At plus terms

Particulars Calculation   

Amount ($)

Sales 20000 ton * $ 418 per ton 8360000
Less - Variable cost 20000*240 4800000
Fixed cost 850000
Depreciation 1035000
profit before tax 1675000
Less - tax @ 24% 402000
profit after tax 1273000
Add - Depreciation 1035000
CFAT 2308000

NPV

Salvage value = 287500 - 24% = $ 218500

initial investment = 4140000 + 378000= 4518000

(Amount in dollar)      

Year PVF @ 11% Cash flow Present value
0 1.00 -4518000 -4518000.0
1 0.9009 2308000 2079277.2
2 0.8116 2308000 1873172.8
3 0.7312 2308000 1687609.6
4 0.6587 2308000 1520279.6
4 0.6587 218500( salvage) 143925.9
4 0.6587 378000 (working capital) 248988.6
NPV $ 3041358.1

At minus terms

Particulars Calculation   

Amount ($)

Sales 20000 ton * $ 342 per ton 6840000
Less - Variable cost 20000*240 4800000
Fixed cost 850000
Depreciation 765000
profit before tax 425000
Less - tax @ 24% 102000
profit after tax 323000
Add - Depreciation 765000
CFAT 1088000

Salvage value = 212500 - 24% = $ 161500

initial investment = 3060000 + 342000 = 3402000

(Amount in dollar)      

Year PVF @ 11% Cash flow Present value
0 1.00 -3402000 -3402000.0
1 0.9009 1088000 980179.2
2 0.8116 1088000 883020.8
3 0.7312 1088000 795545.6
4 0.6587 1088000 716665.6
4 0.6587 161500( salvage) 106380.05
4 0.6587 342000 (working capital) 225275.4
NPV $ 305066.65

best case NAV = $ 3041358.1

worst case NAV = $ 305066.65

Add a comment
Know the answer?
Add Answer to:
Make sure the answers are correct, well written, clear, and easy to understand. Thanks. Consider a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Make sure the answers are correct, well written, clear, and easy to understand. Thanks. Consider a...

    Make sure the answers are correct, well written, clear, and easy to understand. Thanks. Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 investment in threading equipment to get the project started; the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...

  • (Answer B please, Part A is correct) Consider a project to supply Detroit with 31,000 tons...

    (Answer B please, Part A is correct) Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will...

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • 20 points Consider a project to supply Detroit with 27,000 tons of machine screws annually for...

    20 points Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 Investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,200,000 and that variable costs should be $225 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a...

  • Problem 11-27 Scenario Analysis (LO2) (8 01:27:55 Consider a project to supply Detroit with 31,000 tons...

    Problem 11-27 Scenario Analysis (LO2) (8 01:27:55 Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT