Make sure the answers are correct, well written, clear, and easy to understand. Thanks.


A (1) Calculation of Operating Cash Flow
Depreciation = $ 3600000 / 4 = $ 900000
| Particulars | Calculation |
Amount ($) |
| Sales | 20000 ton * $ 380 per ton | 7600000 |
| Less - Variable cost | 20000*240 | 4800000 |
| Fixed cost | 850000 | |
| Depreciation | 900000 | |
| profit before tax | 1050000 | |
| Less - tax @ 24% | 252000 | |
| profit after tax | 798000 | |
| Add - Depreciation | 900000 | |
|
Less - increase in working capital |
360000 | |
| Operating cash flow | 1338000 |
Operating cash flow = Net Income + Non-Cash Expenses – Increase in Working Capital
A. (2) Calculation of Estimated NPV
for calculating the NPV we use CFAT ( cash flow after tax + Deprecation)
CFAT = 798000+900000 = 1698000
Salvage value = 250000 - 24% = $ 190000
initial investment = 3600000 + 360000 = 3960000
(Amount in dollar)
| Year | PVF @ 11% | Cash flow | Present value |
| 0 | 1.00 | -3960000 | -3960000.0 |
| 1 | 0.9009 | 1698000 | 1529728.2 |
| 2 | 0.8116 | 1698000 | 1378096.8 |
| 3 | 0.7312 | 1698000 | 1241577.6 |
| 4 | 0.6587 | 1698000 | 1118472.6 |
| 4 | 0.6587 | 190000 ( salvage) | 125153.0 |
| 4 | 0.6587 | 360000 (working capital) | 237132.0 |
| NPV | $ 1673160.2 |
B. Best case NPV and worst case NPV after terms changed
| Particulars | at plus (+) | at minus (-) |
| project cost (15%) | 4140000 | 3060000 |
| Salvage value (15%) | 287500 | 212500 |
| price change (10%) | $ 418 | $ 342 |
| net working capital (5%) | 378000 | 342000 |
At plus terms
| Particulars | Calculation |
Amount ($) |
| Sales | 20000 ton * $ 418 per ton | 8360000 |
| Less - Variable cost | 20000*240 | 4800000 |
| Fixed cost | 850000 | |
| Depreciation | 1035000 | |
| profit before tax | 1675000 | |
| Less - tax @ 24% | 402000 | |
| profit after tax | 1273000 | |
| Add - Depreciation | 1035000 | |
| CFAT | 2308000 |
NPV
Salvage value = 287500 - 24% = $ 218500
initial investment = 4140000 + 378000= 4518000
(Amount in dollar)
| Year | PVF @ 11% | Cash flow | Present value |
| 0 | 1.00 | -4518000 | -4518000.0 |
| 1 | 0.9009 | 2308000 | 2079277.2 |
| 2 | 0.8116 | 2308000 | 1873172.8 |
| 3 | 0.7312 | 2308000 | 1687609.6 |
| 4 | 0.6587 | 2308000 | 1520279.6 |
| 4 | 0.6587 | 218500( salvage) | 143925.9 |
| 4 | 0.6587 | 378000 (working capital) | 248988.6 |
| NPV | $ 3041358.1 |
At minus terms
| Particulars | Calculation |
Amount ($) |
| Sales | 20000 ton * $ 342 per ton | 6840000 |
| Less - Variable cost | 20000*240 | 4800000 |
| Fixed cost | 850000 | |
| Depreciation | 765000 | |
| profit before tax | 425000 | |
| Less - tax @ 24% | 102000 | |
| profit after tax | 323000 | |
| Add - Depreciation | 765000 | |
| CFAT | 1088000 |
Salvage value = 212500 - 24% = $ 161500
initial investment = 3060000 + 342000 = 3402000
(Amount in dollar)
| Year | PVF @ 11% | Cash flow | Present value |
| 0 | 1.00 | -3402000 | -3402000.0 |
| 1 | 0.9009 | 1088000 | 980179.2 |
| 2 | 0.8116 | 1088000 | 883020.8 |
| 3 | 0.7312 | 1088000 | 795545.6 |
| 4 | 0.6587 | 1088000 | 716665.6 |
| 4 | 0.6587 | 161500( salvage) | 106380.05 |
| 4 | 0.6587 | 342000 (working capital) | 225275.4 |
| NPV | $ 305066.65 |
best case NAV = $ 3041358.1
worst case NAV = $ 305066.65
Make sure the answers are correct, well written, clear, and easy to understand. Thanks. Consider a...
Make sure the answers are correct, well written, clear,
and easy to understand. Thanks.
Consider a project to supply Detroit with 20,000 tons of machine screws annually for automobile production. You will need an initial $3,600,000 investment in threading equipment to get the project started; the project will last for 4 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...
(Answer B please, Part A is correct)
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...
Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...
20 points Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,000,000 Investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,200,000 and that variable costs should be $225 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a...
Problem 11-27 Scenario Analysis (LO2) (8 01:27:55 Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project...