Question1
Total paid hours = 1041200
Unproductive hours = 1041200*0.25 = 260300 hours
Productive hours = 1041200 – 260300 = 780,900 hours
Productive hours per patient day = 780,900/137,200 = 5.7 hours
Question2
Total Number of hours = 1*5000 + 1.5*8000 + 2*4000 + 3*750 = 27250 Hours
Full Time Equivalent (FTE) = Total Hours / Total Hours in an year = 27250 / 2080
FTE = 13.1
QUES 0.5 points Save Answer The total paid hours for 7 North last year was 1,041,200....
QUES 0.5 points Save Answer Unit 6 West is budgeted for 12,775 patient days at an average PHPPD of 8.3. How many FTEs are budgeted? OA. 12.7 OB. 38 OC. 50.9 OD. Cannot calculate with this information.