Question

can you answer this question and explain why? thanks.

A 50-Hz 10-MVA, 66/22-kV distribution transformer has a full-load efficiency of 98% at 0.8 lagging power factor. The transfor

(b) Suppose the transformer has a 20 % continuous overloading capability. Determine the additional load (in kW and KVA ) that

A 50-Hz 10-MVA, 66/22-kV distribution transformer has a full-load efficiency of 98% at 0.8 lagging power factor. The transformer core loss is 80 kW. The transformer supplies an industrial load that has a constant demand of 5000 kW at 0.65 lagging power factor. The cost of energy is $0.1 per kWh. 1. In the following questions, assume that the voltage at the load terminal is maintained constant at 22 kV. calculations. State any other assumptions made in your Calculate the capacitor rating (in kVAr) to improve the power factor at the (a) load terminal to 0.95 lagging. Also, determine the reduction in the average power loss of the transformer and the saving in energy costs per year when the capacitor is in service. Assume that one year has 365 days. (10 Marks) Note: Question No. 1 continues on page 2.
(b) Suppose the transformer has a 20 % continuous overloading capability. Determine the additional load (in kW and KVA ) that can be supplied through the transformer following the installation of the capacitor if the additional load absorbs power at 0.8 lagging power factor. 9071623 92 (10 Marks) What is load shedding? Briefly discuss what are the factors to consider in load shedding. (5 Marks)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

5oz, 10 MuA, 66/21kv Transformer details Efficieng 16. at o8 lag. 1- full load PeCose loss of Transformer = Bokw fuu load coQutput Tuli load Efticienuy= 1 98v Qutputt PeotPef (104103)o. (10x18 x0-8) +o+ Pe¢ Pef = 8 3.26 53 Kul =fuu load Copper lossimproved to o- 351g Now when load power factor Lo ad teminals= L, at dauon Cumrent Sos103 J3 (221103) *o.JS I2 I, 138.122 A PSaving in Energ caste (P 2)365+Q4 L,-PL kwh 26.204)(365) Sauing in Energy Cast kass47.04) x(0H) - So Cost- Transfomes has ao1Can be SSI6.19g16 addiHonal load of So with o. Continous ovesloading Ca pacity. &upplied ) Load she dding Power System the Pa

Add a comment
Know the answer?
Add Answer to:
can you answer this question and explain why? thanks. A 50-Hz 10-MVA, 66/22-kV distribution transformer has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Can you help me calculating this question? Thank you. Can you calculate this working and explain why? Thank you! 1. A 5...

    Can you help me calculating this question? Thank you. Can you calculate this working and explain why? Thank you! 1. A 50-Hz 10-MVA, 66/22-kV distribution transformer has a full-load efficiency of 98% at 0.8 lagging power factor. The transformer core loss is 80 kW. The transformer supplies an industrial load that has a constant demand of 5000 kW at 0.65 lagging power factor. The cost of energy is S0.1 per kWh. In the following questions, assume that the voltage at...

  • A three-phase feeder has line voltage of 13.8 kV and supplies load of 7000 kVA at...

    A three-phase feeder has line voltage of 13.8 kV and supplies load of 7000 kVA at power factor of 0.8 lagging. Find: The feeder current in A, real power in kW and Reactive power in kVAr. The capacitor size in kVAr to improve the power factor to 0.98. The feeder power in kW and kVA and current in A, after installing the capacitor bank.

  • A three phase distribution substation transformer has a nameplate rating of 7250 kVA and a thermal...

    A three phase distribution substation transformer has a nameplate rating of 7250 kVA and a thermal capability of 120% of nameplate rating. If the connected load on the transformer is 8816 kVA at a power factor of 0.85 lagging, determine the following: The kilovar rating of the shunt capacitor bank required to decrease the kilovoltampere load on the transformer to its thermal capability level. The power factor of the corrected load. The kilovar rating of the capacitor bank to correct...

  • QUESTION 3 A 200 - MVA, 15/200 kV single-phase power transformer has a per – unit...

    QUESTION 3 A 200 - MVA, 15/200 kV single-phase power transformer has a per – unit resistance of 1.2 percent and a per-unit reactance of 5 percent (data taken from the transformer's nameplate). The magnetizing impedance is impedance is j80 per unit. a. Find the equivalent circuit referred to the low-voltage side of this transformer. b. Calculate the voltage regulation of this transformer for a full-load current at power factor of 0.8 lagging. c. Assume that the primary voltage of...

  • A 400-MVA, 200-kV/20-kV, three phase Y-Y transformer has an equivalent series impedance of ZTL = 0.012...

    A 400-MVA, 200-kV/20-kV, three phase Y-Y transformer has an equivalent series impedance of ZTL = 0.012 + 20.0162 per phase referred to the low-voltage side (secondary side). The transformer is supplying a three-phase load of 300-MVA, 0.8 power factor lagging at terminal voltage of 20 kV (line-to-line) on its low-voltage side (secondary side) as shown in Fig. 22. The primary is supplied from a transmission line with an impedance of ZL = 0.5 + j1.0 per phase. The line-to-neutral load...

  • Q6. A 50 Hz, 25 kVA 7200/240 V transformer has the following equivalent circuit parameters: Prima...

    Please show full working Q6. A 50 Hz, 25 kVA 7200/240 V transformer has the following equivalent circuit parameters: Primary resistance-1562, secondary resistance-0.02 Ω Primary leakage reactance-140Q, Secondary leakage reactance-0.15Q, Magnetising reactance 30 k2, Core loss resistance 200 k2 (a) The transformer is connected to two loads in parallel. The first load is 10 kW at 0.866 power factor lagging and the second load is 15kVA with a power factor of 0.8 lagging. Find the percentage regulation and power efficiency...

  • Q6. A 50 Hz, 25 kVA 7200/240 V transformer has the following equivalent circuit parameters: Prima...

    Help me answer c and d Q6. A 50 Hz, 25 kVA 7200/240 V transformer has the following equivalent circuit parameters: Primary resistance-1562, secondary resistance-0.02 Ω Primary leakage reactance-140Q, Secondary leakage reactance-0.15Q, Magnetising reactance 30 k2, Core loss resistance 200 k2 (a) The transformer is connected to two loads in parallel. The first load is 10 kW at 0.866 power factor lagging and the second load is 15kVA with a power factor of 0.8 lagging. Find the percentage regulation and...

  • Given a 31.5 MVA Single phase step down transformer.110 KV:11 KV The open circuit test values...

    Given a 31.5 MVA Single phase step down transformer.110 KV:11 KV The open circuit test values are Input voltage = 11 KV, P = 22.1 KW, I=5.85 A The short circuit test values are.Input voltage = 5.755 KV, P=163.935 KW, I= 286.36A If the transformer is run full load output with a power factor of 0.8 lagging 13.            Find I2 and V2     bold denotes phasor values 14.            Find the full load power P 15.            Find the voltage drop across the...

  • can you calculate this question and explain why? thanks 1. A 250-kVA, 11000/2200-V, 50-Hz, single-phase transformer...

    can you calculate this question and explain why? thanks 1. A 250-kVA, 11000/2200-V, 50-Hz, single-phase transformer has the following parameters: RI 1.3 , R2 0.05 , Rel 193 k2, X1 4.5 Q X2 0.16 2 I,- 80 kQ Xml (a) Draw the approximate equivalent circuit of the transformer showing all the circuit parameters referred to the low-voltage side. Use the approximate equivalent circuit to calculate the input voltage and voltage regulation of the transformer when it delivers full load at...

  • A 1200 kVA, 11/3.3 kV, 50-Hz, three phase Dyn 11 transformer is subjected to both the...

    A 1200 kVA, 11/3.3 kV, 50-Hz, three phase Dyn 11 transformer is subjected to both the open, and short circuit tests, yielding the following results: OPEN CIRCUIT TEST SHORT CIRCUIT TEST Vsupply = 3.3 kV Vsupply = 650 V Io = 7.3 A Isc = 54.4A Po = 6.71 kW Psc = 8.89 kW Determine: 1.1 The no load current per phase, in RECTANGULAR form, referred to the H.V. side. (5) 1.2 How would you know, without being told, that...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT