SOLUTION
| S.No. | Accounts titles and Explanation | Debit ($) | Credit ($) |
| (a) | Construction expense | 288,383 | |
| Construction in process | 22,400 | ||
| Construction revenue | 265,983 | ||
| (b) | Loss from contract | 22,400 | |
| Construction in process | 22,400 |
Total estimated cost = 280,200 + 161,600 = 441,800
Contract price = $419,400
Loss = Total estimated cost - Contract price
= $441,800 - $419,400 = 22,400
Percentage of completion method = Cost incurred / Total estimated cost
= 280,200 / 441,800 = 63.42%
Construction revenue = Contract price * Percentage complete
= 419,400 * 63.42% = 265,983
Headland Construction Company began work on a $419,400 construction contract in 2017. During 2017, Headland incurred...
Cheyenne Construction Company began work on a $424,000
construction contract in 2020. During 2020, Cheyenne incurred costs
of $279,500, billed its customer for $204,500, and collected
$170,500. At December 31, 2020, the estimated additional costs to
complete the project total $150,500.
Prepare Cheyenne’s journal entry to record profit or loss, if any,
using (a) the percentage-of-completion method and (b) the
completed-contract method.
Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
Indigo Construction Company began work on a $420,500 construction contract in 2020. During 2020, Indigo incurred costs of $299,000, billed its customer for $202,000, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $151,030. Prepare Indigo’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Vaughn Construction Company began work on a $423,000 construction contract in 2020. During 2020, Vaughn incurred costs of $295,500, billed its customer for $200,500, and collected $170,000. At December 31, 2020, the estimated additional costs to complete the project total $155,645. Prepare Vaughn’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Windsor Construction Company began work on a $404,000 construction contract in 2020. During 2020, Windsor incurred costs of $273,000, billed its customer for $232,000, and collected $182,000. At December 31, 2020, the estimated additional costs to complete the project total $163,660. Prepare Windsor’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Coronado Construction Company began work on a $407,000 construction contract in 2020. During 2020, Coronado incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Coronado’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Blue Construction Company, which began operations in 2017,
changed from the completed-contract to the percentage-of-completion
method of accounting for long-term construction contracts during
2018. For tax purposes, the company employs the completed-contract
method and will continue this approach in the future. The
appropriate information related to this change is as
follows.
Pretax Income from
Percentage-of-Completion
Completed-Contract
Difference
2017
$966,000
$600,000
$366,000
2018
906,000
434,000
472,000
(a) Assuming that the tax rate is 35%, what is the
amount of net income...
Exercise 18-33 During 2017, Marin Company started a construction yob with a contract price of $1,610,000. The job was completed in 2019. The following information is available, 2017 2018 2019 Costs incurred to date $405,900 $766,500 51,076,000 Estimated costs to complete 584,100 328,500 Brings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage of completion method is used. Gross proft recognized in 2017 Gross...
Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...