Draw the following network and calculate all dates (all activities are contiguous):
|
Activity |
Duration |
IPA |
Type Rel |
Lag |
ES |
EF |
LS |
LF |
TF |
FF |
|
A |
4 |
- |
||||||||
|
B |
3 |
- |
||||||||
|
C |
8 |
A |
||||||||
|
D |
7 |
A,B |
||||||||
|
E |
6 |
D |
SS |
3 |
||||||
|
F |
3 |
D |
FF |
|||||||
|
G |
5 |
F |
SS |
2 |
||||||
|
2 |
F |
FF |
please do not copy from others, they are wrong
Answer:

TF=LF-EF
=LS-ES
FF=MIN(ES of sucesors)-EFof activity
| Activity | ES | EF | LS | LF | TF | FF |
| A | 0 | 4 | 0 | 4 | 0 | 0 |
| B | 0 | 3 | 1 | 4 | 1 | 1 |
| C | 4 | 12 | 11 | 19 | 7 | 7 |
| D | 4 | 11 | 4 | 11 | 0 | 0 |
| E | 11 | 17 | 13 | 19 | 2 | 0 |
| F | 11 | 14 | 11 | 14 | 0 | 0 |
| G | 14 | 19 | 14 | 19 | 0 | 0 |
Draw the following network and calculate all dates (all activities are contiguous): Activity Duration IPA Type...
Problem #2 (25 points) For the project below, choose a random duration for each activity (Activity A already has a duration of 3). Calculate the ES, EF, LS, LF, TF and FF for all activities. Use the legend shown below for each activity and highlight the critical path. Fill the answers in the activity's boxes shown below. F с E H A 3 D G Legend: ES TF EF FF Activity LS Duration LF
3 & 15. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 3 with an imposed finish date of 15 and then 20 days. Activity Duration IPA ES EF LS LF TF FF A 2 - B 4 A C 6 A D 9 A E 5 B F 7 B, C G 3 D, E, F
1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...
For the following, draw the node network, perform the CPM
calculations, mark the critical Path, and complete the table.
IAAB 745 00 ABCDE Make possibility of rejection. Also show procurement activities CHAPTER 4 EXERCISES 1. For the following schedule, draw the node network, perform the CPM tions, mark the critical path, and complete the table. Activity Duration IPA ES EF LS LF TF FF В 8 B, C For the following schedule, draw the node network, perform the CPM tions,...
5 & 17. For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Repeat exercise 5 with an imposed finish date of 26 and then 35 days. Activity Duration IPA ES EF LS LF TF FF A 6 - B 2 - C 9 - D 4 A, B E 7 B F 5 D G 10 D, E H 8 C, F, G I 3 C, G J 2...
3. For the following schedule, draw the node network, perform the CPM calcula tions, mark the critical path, and complete the table TF FE LS LF ES IPA Duration Activity 2 A - A 4 A 6 C A 5 F B, C D, E, F 7 F 3 G
: A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...
For the following Engineering project, draw the network diagram and calculate ES, EF, LS, LF, TF Predecessors Durations (Days) A1 3 A2 A1 7 A3 A1 14 A4 A2, A3 3 Activity ES EF LF LS TF A1 A2 A3 A4 Critical Path is
2. Draw a precedence network for 3 activities: A, B, and C; with durations of 9, 4, and 7 days; respectively, and connected with SS and FF relationships. Put a 2-day lag on every SS relationship and a 1-day lag on every FF relationship. All activities are contiguous. Do the CPM calculations.
Consider the following project activities:
Calculate the expected time (te) for each
activity.
Draw an Activity on Node (AON) diagram to reflect the flow of
these activities.
Calculate the Early Start (ES), Early Finish (EF), Late Start
(LS), and Late Finish (LF) for each activity.
Calculate the slack for each activity.
Identify all activities on the Critical Path.
Use the data to calculate the probability the project will
finish in 20 weeks (Hint: z-score).
Activity A 8 с D E...