Patricia is a general contractor performing construction work for ABC Corp. Patricia requested extra payment because abnormal subsurface rock formations made excavation on the construction site far more costly and time-consuming than could have been reasonably expected. The court will:
A) consider the contract unenforceable.
B) consider the contract voidable.
C) allow the party to rescind such a contract.
D) enforce such modifications in contract.
Ans) the correct option is d) enforce such modifications in contract.
Patricia requested extra payment, excavation became time-consuming than expected. The court will enforce such modifications in contract.
Patricia is a general contractor performing construction work for ABC Corp. Patricia requested extra payment because...