Patricia is a general contractor performing construction work for ABC Corp. Patricia requested extra payment because...

Patricia is a general contractor performing construction work for ABC Corp. Patricia requested extra payment because abnormal subsurface rock formations made excavation on the construction site far more costly and time-consuming than could have been reasonably expected. The court will:

A) consider the contract unenforceable.

B) consider the contract voidable.

C) allow the party to rescind such a contract.

D) enforce such modifications in contract.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans) the correct option is d) enforce such modifications in contract.

Patricia requested extra payment, excavation became time-consuming than expected. The court will enforce such modifications in contract.

Add a comment
Know the answer?
Add Answer to:
Patricia is a general contractor performing construction work for ABC Corp. Patricia requested extra payment because...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT