|
Agasse Industries began construction of a new facility and took out a $1,500,000, 8% construction loan on April 1, 2016. Agasse made payments to the general contractor of $481,000 on April 1, $981,000 on August 31, and $581,000 on December 31. |
| Required: |
| Compute the amount of interest that Agasse would capitalize in 2016. (Do not round intermediate calculations.) |
Amount of Interest________
| Expenditure | |||||
| 1-Apr | 481000*9/9= | 481000 | |||
| 31-Aug | 981000*4/9= | 436000 | |||
| 31-Dec | 581000*0/9= | 0 | |||
| 917000 | |||||
| interest 917000*8%*9/12= | 55020 | ||||
| interest capitalized $55,020 | |||||
Agasse Industries began construction of a new facility and took out a $1,500,000, 8% construction loan...
Agasse Industries began construction of a new facility and took out a $1,500,000, 12% construction loan on April 1, 2021. Agasse made payments to the general contractor of $337,000 on April 1, $837,000 on August 31, and $437,000 on December 31. Required: figure the amount of interest that Agasse would capitalize in 2021. (Do not round intermediate calculations.)
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,200,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $9,000,000, 10% bonds $6,000,000, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 900,000 March 31 1,500,000 June 30 1,160,000 September 30 900,000...
On January 1, 2016, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2017. The company borrowed $1,500,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2016: Construction expenditures incurred during 2016 were as follows: Calculate the amount of interest capitalized for 2016 using the specific interest method.
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $ 1,000,000 March 1, 2016 600,000 June 30, 2016 800,000 October 1, 2016 600,000 January 31, 2017 270,000 April 30, 2017 585,000 August 31, 2017 900,000 On January 1, 2016, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,420,000 1,140,000 1,340,000 1,140,000 351,000 684,000 981,000 On January 1, 2021, the company obtained a $3,900,000 construction loan with a 12% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 $1,850,000 1,500,000 1,700,000 1,500,000 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 405,000 738,000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% interest rate. The...
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....
On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1.850,000 1.500.000 1,700,000 1.500.000 405,000 738.000 1,035,000 On January 1, 2021, the company obtained a $4,500,000 construction loan with a 12% Interest rate. The...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,850,000 at 10% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $4,000,000, 14% bonds $1,000,000, 10% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 800,000 March 31 1,400,000 June 30 1,040,000 September 30 800,000...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $1,700,000 at 7% on January 1 to help finance the construction, in addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 12t bonds $3,000,000, 78 long-term note Construction expenditures incurred during 2018 were as follows: January 1 March 31 June 30 September 30 December 31 $ 740,000 1,340,000...