Question

the following information to answer the next three questions. A retailer faces uncertain demand for goods i antiers fom a supplier that guarantees 3-week lead time for deliveries 32. Which one of the following is CORRECT regarding the average lead time demand? A) Average lead time demand is 3 times the average weekly demand. 8) Average lead time demand equals the average weekly demand. Q Average lead time demand is more than 3 times the average weekly demand. D) Average lead time demand is less than 3 times the average weekly demand. a. Which one of the following is CORRECT regarding the standard devlation of the lead time demand? A) Standard deviation of the lead time demand is 3 times the standard deviation of the weekly 8) standard devistion of the lead time demand equals the standard deviation of the weekly 9 standard deviation of the lead time demand is more than 3 times the standard deviation of the demand demand weekdy demand b) standard deviation of the lead time demand is less than 3 times the standard deviation of the weekly demand W. Which one of the following is CORRECT regarding the variance of the lead time demand? A) Variancs of the lead time demand is 3 times the variance of the weekly demand e) Variance of the lead time demand equals the variance of the weekly demand G Variance of the lead time demand is more than 3 times the varlance of the weekly demand b) Verianca of the lead time demand is less than 3 times the variance of the weekly demand %. Which one of the folloing companys successful implementation of lean operations management prhogles was featured in a video we watched in dlass? Airbu ) Ford o) Being
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:-32)

Lead time means the total time requires to manufacture an item including order preparation time queue time,set up time,run time,move time,inspection time and put away time.

Correct Answer is A) Average lead time demand is 3 times the average weekly demand

Because if an order when the inventory on hand is equal to the average demand during the lead time.

Answer :33)

A) Standard deviation of the lead time demand is 3 time the standard deviation of the weekly demand.

If the standard deviation of demand is calculated from weekly demand data and the total lead time including review period is three weeks the standard deviation of demand is the weekly standard deviation time the square root the reaction of the time units.

Answer 34) C) Variance of the lead time demand is less than 3 times the variance of the weekly demand.

Add a comment
Know the answer?
Add Answer to:
the following information to answer the next three questions. A retailer faces uncertain demand for goods...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • HighLife corporation has the following information: Average demand = 30 units per day Average lead time...

    HighLife corporation has the following information: Average demand = 30 units per day Average lead time = 40 days Item unit cost = $45 for orders of less than 400 units Item unit cost = $40 for orders of 400 units or more Ordering cost = $50 Inventory carrying cost = 15% The business year is 300 days Standard deviation of demand during lead time = 90 Desired service level = 95% What is the TAC at $40/unit?

  • Practice Problem 1. Consider the following information for a product: Lead time is 3 weeks. The...

    Practice Problem 1. Consider the following information for a product: Lead time is 3 weeks. The average weekly demand is 1500 and weekly standard deviation is 300. If company wants to have cycle service level of 90%. What should the safety stock be?

  • Assume that the daily demand, at one of the retailer, for Keurig beverage brewing system is...

    Assume that the daily demand, at one of the retailer, for Keurig beverage brewing system is normally distributed and that the average daily demand is 20 machine with a standard deviation of 3 machine per day. The lead time for receiving a new order of a Keurig system constant at 9 days. Determine the safety stock if the retailer wants a stock-out risk equal to 6%. Safety Stock=___________?

  • A retailer sells four items i = 1, 2, 3, 4. Their weekly demand characteristics are...

    A retailer sells four items i = 1, 2, 3, 4. Their weekly demand characteristics are the same, with a mean demand of µi = 100 units, and a standard deviation of σi = 10 units. The four items are also independent of one another (wherever you need to, you can assume the covariance is 0). The retailer does not know exactly how the item demands are distributed, but they assume they follow a normal distribution. Answer the following questions....

  • Please answer the following 4 questions based on the same problem: A small shop implemented a...

    Please answer the following 4 questions based on the same problem: A small shop implemented a continuous review policy in managing its inventory with the given parameters for one item: Annual demand: 15,000 units Holding costs: 40% of purchase price per year. Landed purchase cost: $10 Setup cost: $75 per order Number of working days per calendar year: 250 Lead time: 3 days Required service level: 95% 1. Determine the reorder point, assuming no safety stock. Round your answer to...

  • One of the products sold by OfficeMax is a Hewlett-Packard LaserJet 299 printer. As purchasing manager,...

    One of the products sold by OfficeMax is a Hewlett-Packard LaserJet 299 printer. As purchasing manager, you have the following information for the printer: i Click the icon to view the information for the printer. a. The EOQ is 21. (Enter your response rounded to the nearest whole number.) b. The annual ordering costs and holding costs (ignoring safety stock) for the EOQ is $ 988 . (Enter your response rounded to the nearest dollar.) c. Suppose Office Max currently...

  • Given this information: Expected demand during lead time = 285 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 285 units Standard deviation of lead time demand = 16 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 1 percent during lead time. (Round your answer to the nearest whole number.) ROP _____ units    b. The safety stock needed to attain a 1 percent risk of stockout during lead time. (Do...

  • Given this information: Expected demand during lead time = 295 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 295 units Standard deviation of lead time demand = 20 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 2 percent during lead time. (Round your answer to the nearest whole number.) ROP             units    b. The safety stock needed to attain a 2 percent risk of stockout during lead time....

  • The following information is available for a product whose demand is variable. The daily demand is...

    The following information is available for a product whose demand is variable. The daily demand is distributed normally, with an average demand of 5 and one standard deviation of 2. The delivery time for this product is also approximately normal, with an average of 10 days and a standard deviation of 3 days. We want a service level of 95%. Calculate the security stock level and the order point for this product

  • Given the following information, formulate a continuous-review inventory management system. The item is demanded 50 weeks...

    Given the following information, formulate a continuous-review inventory management system. The item is demanded 50 weeks a year. 2. Item cost Order cost Annual holding cost (%) Annual demand Average demand $20 $250 10% df item cost 25,000 500 per week Standard deviation of weekly demand Lead time Service probability 25 per week 1 week 95% Compute the order quantity and reorder point. For the order quantity, please provide at least one step of calculation and the correct answer for...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT