The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation.
Production: 7,000 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs.
Manufacturing costs: Materials $33,000; labor $21,000; and overhead $36,000.
Instructions
Prepare a production cost report.
Cost report is given at the end
|
Reconciliation of Units |
||
|
A |
Opening WIP |
- |
|
B |
Introduced |
10,000 |
|
C=A+B |
TOTAL |
10,000 |
|
D |
Transferred |
7,000 |
|
E=C-D |
Closing WIP |
3,000 |
|
Statement of Equivalent Units |
|||||
|
Material |
Conversion Cost |
||||
|
Units |
Complete % |
Equivalent units |
Complete % |
Equivalent units |
|
|
Transferred |
7,000 |
100% |
7,000 |
100% |
7,000 |
|
Closing WIP |
3,000 |
100% |
3,000 |
20% |
600 |
|
Total |
10,000 |
Total |
10,000 |
Total |
7,600 |
|
Cost per Equivalent Units |
||||
|
COST |
Material |
Conversion Cost |
TOTAL |
|
|
Beginning WIP Inventory Cost |
$ - |
|||
|
Cost incurred during period |
$ 33,000 |
$ 57,000 |
$ 90,000 |
|
|
Total Cost to be accounted for |
$ 33,000 |
$ 57,000 |
$ 90,000 |
|
|
Total Equivalent Units |
10,000 |
7,600 |
||
|
Cost per Equivalent Units |
$ 3.30 |
$ 7.50 |
||
|
Statement of cost |
|||||
|
Cost |
Equivalent Cost/unit |
Ending WIP |
Transferred |
||
|
Units |
Cost Allocated |
Units |
Cost Allocated |
||
|
Material |
$ 3.30 |
3,000 |
$ 9,900.00 |
7,000 |
$ 23,100.00 |
|
Conversion Cost |
$ 7.50 |
600 |
$ 4,500.00 |
7,000 |
$ 52,500.00 |
|
TOTAL |
$ 90,000 |
TOTAL |
$ 14,400 |
TOTAL |
$ 75,600 |
|
Reconciliation and Cost report |
||||
|
Cost to be accounted for |
||||
|
Beginning Work In Progress: |
||||
|
Material |
$ - |
|||
|
Conversion Cost |
$ - |
$ - |
||
|
Cost incurred during period: |
||||
|
Material |
$ 33,000.00 |
|||
|
Conversion Cost |
$ 57,000.00 |
$ 90,000.00 |
||
|
Total Cost to be accounted for |
$ 90,000.00 |
|||
|
Cost accounted for |
||||
|
Cost of Units transferred |
Equivalent Units |
Cost per Equivalent Units |
Cost accounted for |
|
|
Material |
7,000 |
$ 3.30 |
$ 23,100.00 |
|
|
Conversion Cost |
7,000 |
$ 7.50 |
$ 52,500.00 |
|
|
$ 75,600.00 |
||||
|
Cost of ending WIP |
Equivalent Units |
Cost per Equivalent Units |
Cost accounted for |
|
|
Material |
3,000 |
$ 3.30 |
$ 9,900.00 |
|
|
Conversion Cost |
600 |
$ 7.50 |
$ 4,500.00 |
|
|
$ 14,400.00 |
||||
|
Total Cost accounted for |
$ 90,000.00 |
|||
The Sanding Department of Quik Furniture Company has the following production
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation Production: 6,810 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $32,079; labor $20,600; overhead $35,271. Prepare a production cost report. (Round unit costs to 2 decimal places, e-s. 2.25.) QUIK FURNITURE COMPANY Sanding Department Production Cost Report For the Month...
Exercise 16-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 7,330 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,981; labor $21,100; overhead $42,102. CALCULATOR QUIK FURNITURE COMPANY Sanding Department Production Cost Report For the Month Ended March 31, 2017 Equivalent Units Physical Conversion Units Materials Costs...
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 7,330 units finished and transferred out; 3,000 units started that are 100% complie e as to mater as and 20% tomplete as to conversion costs. Manufacturing costs: Materials $36,981; labor $21,100; overhead $42,102. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25.) QUIK FURNITURE COMPANY Sanding Department Production Cost Report For...
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 7,140 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs Manufacturing costs: Materials $35,490; labor $20,700: overhead $42,768. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to decimal places, eg, 125.) QUIK FURNITURE COMPANY...
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,520 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,176; labor $21,400; overhead $34,848. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to decimal places, eg. 125.) QUIK FURNITURE COMPANY...
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 6,060 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $28,992; labor $21,300; overhead $34,311. Prepare a production cost report. (Round unit costs to 2 decimal places, eg. 2.25 and other answers to O decimal places, e-g. 125.) QUIK FURNITURE...
Exercise 21-7 The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2017, the first month of operation. Production: 6,230 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $36,735; labor $21,400; overhead $30,235 Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25.) QUIK FURNITURE COMPANY Production Cost Renort For the Month...
Please explain answer thank
you!
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation. Production: 7,060 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $39,234; labor $21,100; overhead $40,180. Prepare a production cost report. (Round unit costs to 2 decimal places, e.g. 2.25 and other answers to o decimal...
need help with this chart please
The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation Production: 7,140 units finished and transferred out: 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $35,490; labor $20,700, overhead $42.768. Prepare a production cost report. (Round unlt costs to 2 decimal places, es2.25 and other answers to decimal places,...
lems Assignment > Question 7 of 7 - 112 III The Sanding Department of Quik Furniture Company has the following production and manufacturing cost data for March 2020, the first month of operation Production: 7,020 units finished and transferred out; 3,000 units started that are 100% complete as to materials and 20% complete as to conversion costs. Manufacturing costs: Materials $37.575; labor $21.400; overhead $38,417. Prepare a production cost report. (Round unit costs to 2 decimal places, es. 2.25 and...