4. A sustainable construction practice is the balancing of cut (soil to be removed) and fill...
4. A sustainable construction practice is the balancing of cut (soil to be removed) and fill (soil to be added) for any particular infrastructure site. Unfortunately, any remaining soil that needs to be removed/added to the site will cost an expense per volume. One particular site has a fill and cut of 1,188 and 527 cubic meters, respectively, which must be balanced to deternmine the remaining demand (i.e. determine the remainder from difference between fill and cut). The truck driver...