8.
A positive NPV means the project is accepted. For a positive NPV, the amount of cash inflows is greater than the amount of cash outflows.
For a positive NPV, the Internal rate of return will always be higher than cost of capital, because the higher the IRR, the higher is the amount of cash inflows for a project.
Therefore answer is option A) IRR exceeds the cost of capital
9.
NPV= Total present value of cash inflows - Total present value of cash outflows
NPV = Total present value of cash inflows - cost of investment
Given NPV = $5000
cost of investment = $20000
5000 = Total present value of cash inflows - 20,000
Total present value of cash inflows = 25,000
Therefore answer is option D) project's cash inflows total $25,000
10.
to calculate price of stock one year ago (P)
percentage return = [(current price + dividend)/ previous year price] -1
0.2 =[ (60 + 4)/P] -1
1.2 = 64/P
1.2P = 64
P = $53.33
Therefore answer is option D)$53.33
8. Which of the following statementele mele wing statements is correct for a project with a...
15. Which of the following statements is correct for a project with positive net present worth (PW)? The MARR exceeds the IRR. Accepting the project has an indeterminate effect on the firm. The IRR exceeds the MARR. All cash flows must be positive except year 0 cash flow. . mume MARR to be 12% for each project
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's regular IRR is found by compounding the cash inflows at the cost of capital to find the terminal value (TV), then discounting this TV at the cost of capital. b. To find a project's IRR, we must find a discount rate that is equal to the cost of capital. c. If...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV), then discounting this TV at the WACC. b. A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV), then compounding this PV to...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Group of answer choices A) If a project's IRR is positive, then its NPV must also be positive. B) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. C) If a project's IRR is smaller than the WACC, then its NPV will be positive....
Which of the following statements is most correct? Group of answer choices If a project with normal cash flows has an IRR, which exceeds the cost of capital (required rate of return), then the project must have a positive NPV. If the IRR of Project A exceeds the IRR of Project B, then Project A must also have a higher NPV. Assuming a project has normal cash flows, the NPV will be positive if the IRR is less than the...
Question 30 (1 point) Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV), then discounting the TV at the WACC. A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV), then discounting the...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one cash outflow at t = o followed by a series of positive cash flows. 10 a. If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR. b. To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal...
Which of the following statements is correct? A project's discounted payback period (DBP) is normally shorter than its traditional payback period (PB) because DPB accounts for the time value of money, whereas PB does not. To compute the NPV for a project, the firm's required rate of return must be known. To compute a project's internal rate of return (IRR), the firm's required rate of return is not used because the IRR is the discount rate where the project's NPV...
Which of the following statements is correct? The internal rate of return (IRR) does not allow you to determine whether mutually exclusive projects are acceptable. The net present value (NPV) is the only capital budgeting technique that allows you to determine which independent projects are acceptable. The net present value (NPV) technique provides an indication of the dollar benefit (on a present value basis) to the firm's shareholders of purchasing a capital budgeting project. A project's internal rate of return...
Which one of the following statements is correct? a) The net present value is a measure of profits expressed in today's dollars. b) The net present value is positive when the required return exceeds the internal rate of return. c) If the initial cost of a project is increased, the net present value of that project will also increase. d) Net present value is equal to an investment's cash inflows discounted to today's dollars.