Question

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....

Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $4,800,000 investment in threading equipment to get the project started; the project will last for three years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $250 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the three-year project life. It also estimates a salvage value of $460,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $330 per ton. The engineering department estimates you will need an initial net working capital investment of $480,000. You require a return of 10 percent and face a marginal tax rate of 38 percent on this project.

What is the estimated OCF for this project?


What is the estimated NPV for this project?  

Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What are your worst-case and best-case NPVs for this project?

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Detroit 0 1 2 3
Investment -$4,800,000
NWC -$480,000 $480,000
Salvage $460,000
Sales $13,200,000 $13,200,000 $13,200,000
VC -$10,000,000 -$10,000,000 -$10,000,000
FC -$850,000 -$850,000 -$850,000
Depreciation -$1,600,000 -$1,600,000 -$1,600,000
EBT $750,000 $750,000 $750,000
Tax (38%) -$285,000 -$285,000 -$285,000
Net Income $465,000 $465,000 $465,000
Cash Flows -$5,280,000 $2,065,000 $2,065,000 $2,830,200
NPV $430,255.45

Estimated OCF = Net Income + Depreciation = 2,065,000

NPV = $430,255.45 using 10% discount rate and NPV function

Best case NPV is when initial cost and working capital is lower while salvage value and price is higher.

Detroit 0 1 2 3
Investment -$4,080,000
NWC -$456,000 $456,000
Salvage $529,000
Sales $14,520,000 $14,520,000 $14,520,000
VC -$10,000,000 -$10,000,000 -$10,000,000
FC -$850,000 -$850,000 -$850,000
Depreciation -$1,360,000 -$1,360,000 -$1,360,000
EBT $2,310,000 $2,310,000 $2,310,000
Tax (38%) -$877,800 -$877,800 -$877,800
Net Income $1,432,200 $1,432,200 $1,432,200
Cash Flows -$4,536,000 $2,792,200 $2,792,200 $3,576,180
NPV $2,996,803.91

Worst case NPV is when initial cost and working capital is higher while salvage value and price are lower.

Detroit 0 1 2 3
Investment -$4,080,000
NWC -$504,000 $504,000
Salvage $391,000
Sales $11,880,000 $11,880,000 $11,880,000
VC -$10,000,000 -$10,000,000 -$10,000,000
FC -$850,000 -$850,000 -$850,000
Depreciation -$1,360,000 -$1,360,000 -$1,360,000
EBT -$330,000 -$330,000 -$330,000
Tax (38%) $125,400 $125,400 $125,400
Net Income -$204,600 -$204,600 -$204,600
Cash Flows -$4,584,000 $1,155,400 $1,155,400 $1,901,820
NPV
-$1,149,894.82
Add a comment
Know the answer?
Add Answer to:
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4,600,000 investment in threading equipment to get the project started; the project will last for 3 years. The accounting department estimates that annual fixed costs will be $750,000 and that variable costs should be $410 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 3-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 28,000 tons of machine screws annually for automobile production. You will need an initial $5,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,250,000 and that variable costs should be $235 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,200,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $700,000 and that variable costs should be $400 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $5,300,000 investment in threading equipment to get the project started; the project will last for 6 years. The accounting department estimates that annual fixed costs will be $1,275,000 and that variable costs should be $240 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 6-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will...

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 30,000 tons of machine screws annually for automobile production. You will need an initial $4.3 million investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $1.025 million and that variable costs should be $190 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the five-year project life. It also estimates a...

  • Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 31,000 tons of machine screws annually for automobile production. You will need an initial $6,200,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,500,000 and that variable costs should be $285 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

  • Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $4,500,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,075,000 and that variable costs should be $200 per ton; accounting will depreciate the in itial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage...

  • Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production....

    Consider a project to supply Detroit with 27,000 tons of machine screws annually for automobile production. You will need an initial $4,700,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $1,125,000 and that variable costs should be $210 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT