Please help me fill those
in
and also what is Plan B's cost = ____$? (enter your response as a whole number)
We solve the given problem in POM-QM as shown below:
Regular time cost per unit = Labor cost per hour * Hours per refrigerator = 12 * 4 = $48
Overtime cost per unit = Overtime cost per hour * Hours per refrigerator = 18 * 4 = $72
Current production in December = No. of workers * Hours per day * Days per month / Hours per unit = 8 * 8 * 20 / 4 = 320 units
We enter the required data as shown below:

On solving, we get

The above solution in the table format as per question is:

Required answer in green.
Plan B's cost = $107200 as seen from middle table above
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!
Please help me fill those in and also what is Plan B's cost = ____$? (enter...
Need help filling the empty slots above in.
What is Plan A's cost = ___?(enter response as a whole
number)
Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: B Click the icon to view the company's data. Consider the two following strategies. a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff in...
Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following data: a) Plan A: Vary the workforce so that production meets the forecasted demand (maintain inventory at 250 units). Bell had eight employees on staff in December. Part-time labor is available. Complete the following table (enter your responses as whole numbers). Costs Holding cost $8/ refrigerator/ month Subcontracting $80/ refrigerator Regular-time labor $12/ hour Overtime labor $18/ hour for hours...
A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...
Please help with the missing
numbers above
Also
Total hiring cost $ _?(enter response as whole number)
Total layoff cost $ _?(enter response as whole number)
Total inventory carrying cost $ _?(enter response as whole
number)
Total stockout cost $ _?(enter response as whole number)
Total cost, excluding normal time labor costs, for Plan B $
_?(enter response as whole number)
The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time...
USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor cost per hour $15 Subcontracting cost per unit $80 Back order cost per unit per period $20 Inventory holding cost per unit per period $10 Hiring cost per employee $400 Firing cost per employee $500 Capacity data Beginning workforce 40 employees Beginning inventory 0 units Beginning backorders 0 units Production standard per unit (hours) 2 hours of labor per unit Regular time available per...
The total subcontracting
costequals=$ ????
(Enter your response as a whole number.)
Total cost with plan 5 = ????
Juarez has yet a sixth plan. A constant workforce of 7 is
selected, with the remainder of demand filled by subcontracting.
Evaluate this plan.The production rate per day equals= ????
A Juarez, Mexico, manufacturer of roofing supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June are presented in the table below. There...
Please answer only the empty boxes (bottom table and the
questions below it)
The total subtracting cost= $_______
The total inventory holding cost for January through August=
$_____
The total cost, excluding normal time labor costs, for Plan E=
$_____
Will thumps up if answers is correct!
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...
You are developing an aggregate plan for a toolbox maker which sells to professional mechanics. The relevant cost and demand data are shown below: Holding cost $8/toolbox/month Month Demand Subcontract $80/toolbox July 400 Regular time $45/toolbox August 500 OT Regular time cost plus additional $20 per toolbox September 500 Capacity increase $50/unit October 700 Capacity decrease $90/unit November 800 Backlog cost $10/toolbox/month December 700 June capacity and demand 500 toolboxes Beginning inventory 0 toolboxes Plan A: Try a level strategy...
Consuelo Chua, Inc., is a disk drive manufacturer in need of an aggregate plan for July through December. The company has gathered the following data given in the tables. There are 8 hours of production per day. You manage a consulting firm down the street from Consuelo Chua, Inc., and to get your foot in the door, you have told Mr. Chua that you can do a better job at aggregate planning than his current staff. He said, "Fine. You...
a) the total cost of hiring=$ (enter your
response as a whole number)
b)the total cost of layoffs=$?(enter your response as a whole
number)
c)the total inventory carrying cost =$?(enter your response as a
whole number)
d)the total stockout cost$?(enter your response as a whole
number)
e) the total cost, excluding normal time labor cost, is =$
?(enter your response as a whole number)
The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next...