Question

The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time sto

What are the numbers for subcontract (units) for the picture above?

The total cost, excluding normal time labor costs, for Plan A = $___?(enter response as a whole number)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Subcontract Units (SU) = Demand - Production

July: SU = 1300 - 1100 = 200

Aug: SU = 1150- 1100 = 50

Sep: SU = 1100 - 1100 = 0

Oct: SU = 1600 - 1100 = 500

Nov: SU = 1900 - 1100 = 800

Dec: SU = 1900 - 1100 = 800

Total Subcontract Units = 200 + 50 + 500 + 800 + 800 = 2350 units

Total Cost for Plan A = Total Subcontract Units*Subcontract Cost per unit = 2350*60 = $141000

Add a comment
Know the answer?
Add Answer to:
What are the numbers for subcontract (units) for the picture above? The total cost, excluding normal...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please help with the missing numbers above Also Total hiring cost $ _?(enter response as whole...

    Please help with the missing numbers above Also Total hiring cost $ _?(enter response as whole number) Total layoff cost $ _?(enter response as whole number) Total inventory carrying cost $ _?(enter response as whole number) Total stockout cost $ _?(enter response as whole number) Total cost, excluding normal time labor costs, for Plan B $ _?(enter response as whole number) The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time...

  • The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sale per unit, inventory carrying costs of...

    The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sale per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost basis: Plan A: Produce at a steady rate (equal to minimum requirements) of 1,100 units per month and subcontract additional units at a $60 per unit premium cost. Subcontracting capacity is...

  • The​ S&OP team at Kansas​ Furniture, has received estimates of demand requirements as shown in the...

    The​ S&OP team at Kansas​ Furniture, has received estimates of demand requirements as shown in the table. Assuming​ one-time stockout costs for lost sales of ​$100 per​ unit, inventory carrying costs of ​$25 per unit per​ month, and zero beginning and ending​ inventory, evaluate these two plans on an incremental cost​ basis: Plan​ A: Produce at a steady rate​ (equal to minimum​ requirements) of 1 comma 200 units per month and subcontract additional units at a ​$65 per unit premium...

  • Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inv...

    Her operations manager is considering a new plan, which begins in January with 200 units on hand and ends with zero inventory. Stockout cost of lost sales is $125 per unit. Inventory holding cost is $20 per unit per month. Ignore any idle-time costs. The plan is called plan B. Plan B: Produce at a constant rate of 1,400 units per month, which will meet minimum demands. Then use subcontracting, with additional units at a premium price of $75 per...

  • The​ S&OP team at Kansas​ Furniture, has received the following estimates of demand​ requirements: Complete the...

    The​ S&OP team at Kansas​ Furniture, has received the following estimates of demand​ requirements: Complete the table The S&OP team at Kansas Furniture, has received the following estimates of demand requirements: July Aug. Sept. Dec. Oct. 1,900 Nov. 1,900 900 1,200 1,500 1,900 Assuming stockout costs for lost sales of $90 per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate these two plans on an incremental cost basis: Plan C: Keep...

  • Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The t...

    Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The total inventory holding cost for January through August= $_____ The total​ cost, excluding normal time labor​ costs, for Plan E= $_____ Will thumps up if answers is correct! The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...

  • The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the...

    The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $125 per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis Plan B: Vary the workforce to produce the prior month's demand. The firm produced 1,300 units in June. The cost of hiring additional workers is $30 per unit...

  • The president of Hill​ Enterprises, Terri​ Hill, projects the​ firm's aggregate demand requirements over the next...

    The president of Hill​ Enterprises, Terri​ Hill, projects the​ firm's aggregate demand requirements over the next 8 months as​ follows:   January 1,400 May 2,100 February 1,700 June 2,300 March 1,800 July 1,900 April 1,800 August 1,500 Her operations manager is considering a new​ plan, which begins in January with 200 units on hand and ends with zero inventory. Stockout cost of lost sales is ​$125 per unit. Inventory holding cost is ​$25 per unit per month. Ignore any​ idle-time costs....

  • a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost...

    a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost of layoffs=$?(enter your response as a whole number) c)the total inventory carrying cost =$?(enter your response as a whole number) d)the total stockout cost$?(enter your response as a whole number) e) the total cost, excluding normal time labor cost, is =$ ?(enter your response as a whole number) The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next...

  • The total subcontracting costequals=​$ ???? ​(Enter your response as a whole​ number.) Total cost with plan...

    The total subcontracting costequals=​$ ???? ​(Enter your response as a whole​ number.) Total cost with plan 5​ = ???? Juarez has yet a sixth plan. A constant workforce of 7 is​ selected, with the remainder of demand filled by subcontracting. Evaluate this plan.The production rate per day equals= ???? A Juarez, Mexico, manufacturer of roofing supplies has developed monthly forecasts for a family of products. Data for the 6-month period January to June are presented in the table below. There...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT