Question

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

ActivityImmediate Predecessor(s)Time (days)
A-2
B-7
C-2
DB10
EA, D4
FC5
GE, F10

This exercise contains only parts b, c, and d.

 b) The critical activities for the leadership training program development project are

The critical activities for the leadership training program development project are

c) The project length for the leadership training program development project =

d) Slack time for each of the activities is:

Please show detail on how to calculate the slack time


1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Add a comment
Know the answer?
Add Answer to:
Roger Ginde is developing a program in supply chain management certification for managers
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT