6. If it took 80 hours to produce the first unit of a product, and the learning rate is 80%, how long will it take to produce5. If it takes 60 hours to produce the first unit of a product and 50 hours to produce the 12th unit, what is the learning ra

0 0
Add a comment Improve this question Transcribed image text
Answer #1

D. 2064.36 hrs

Explanation:

The learning curve is usually given by

Y = aXb

Where

Y = cumulative average time per unit or batch.

a = time taken to produce the first unit; 80 hours here

X = Cumulative units of production

Learning Rate = 0.8

b = the learning coefficient, which is calculated as: log(learning rate) ÷ log 2 =

= (log(.80)/log2)

= -0.32193

Given Y26 = a(26)(log(.80)/log2) = 28.03 hrs

Similarly, Y125 = 80(125)(log(.80)/log2) = 16.91 hrs

Therefore, total time taken to produce from unit 26 through units 125 = ΣYi

Where i = 26 to 125

We can create a data table for that using the formulaes above

Learning rate Number of Units Produced a Y X b 80% 80 13.5246 250 -0.3219 26 27 28 Learning Rate 80% 28.03 27.69 27.37

29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 27.06 26.76 26.48 26.21 2595 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 18.47 18.4

Add a comment
Know the answer?
Add Answer to:
6. If it took 80 hours to produce the first unit of a product, and the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • А 3. The jobs listed below needed to be completed. Assume that it is now day...

    А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Job Processing Time (days) Due Date 20 180 30 200 10 175 16 230 18 210 B с D E 4. Given the data from question 3, if the jobs are sequenced according to the longest processing time rule, what is the lateness of job B? A. O B. 24 C. 7.4 D. 9 E 13.4 5. If it takes 60 hours to...

  • Job А 3. The jobs listed below needed to be completed. Assume that it is now...

    Job А 3. The jobs listed below needed to be completed. Assume that it is now day 140. Processing Time (days) Due Date 20 180 30 200 10 175 230 210 B с D 16 18 E If the jobs are sequenced according to shortest processing time rule, what is the average completion time? A. 47.6 B. 60 C. 50 D. 238 E 300 4. Given the data from question 3, if the jobs are sequenced according to the longest...

  • The first unit of a product took 80 days for production. The learning rate for the...

    The first unit of a product took 80 days for production. The learning rate for the production process is 75%. How long will it take to make the 17th unit? (You can use Table E.3 in Module E (Learning Curves) of the textbook.) from 22 to 23 days from 24 to 25 days from 21 to 22 days from 25 to 26 days from 23 to 24 days The first unit of a product took 80 days for production. The...

  • The direct labor times required to produce the first unit was 5 hours. The fourth unit...

    The direct labor times required to produce the first unit was 5 hours. The fourth unit took 3.2 hours. what is the estimated learning or improvement rate? Answers: a. 68% b.80% c. 70% D. 60%

  • (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate...

    (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate of 95%, determine the cost of the 160th unit. (2) If the 4th unit took 24 hours to produce, and the 20th unit took 19 hours to produce, what would the learning rate be? Note: Express your answer in decimal places, i.e., if your answer is 40.56%, enter in 0.4056. (3) Let us suppose it costs $500 to produce the 120th unit, assuming a...

  • The first unit of a product took 500 hours to build, and the learning rate for...

    The first unit of a product took 500 hours to build, and the learning rate for the production process is 78%. How long will it take to make the 256th unit? (Use at least five decimals in the exponent if you use the logarithmic approaches.) from 75 to 85 hours from 85 to 95 hours from 65 to 75 hours from 95 to 105 hours from 55 to 65 hours

  • If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer...

    If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer the following: a) What is the learning rate? b) How long did the first unit take to complete? c) How long did the third unit to take to complete?

  • If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer...

    If the tenth unit produced took 24 hours and the fifth unit took 32 hours, answer the following. a) What is the learning rate? b) How long did the first unit take to complete? c) How long did the third unit take to complete?

  • It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for...

    It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for Antarctic exploration. Your company, Natural Resources, Inc. has agreed to purchase the fifth oil drilling rig from their manufacturing yard. Assume that MegaTech experiences a learning rate of 75%. At a labor rate of $38 per hour, what should you, as the purchasing agent expect to pay for the fifth unit? TN = T1C, Where TN = Time needed to produce the Nth unit...

  • Question 3 2 pts The first unit of a product took 80 days for production. The...

    Question 3 2 pts The first unit of a product took 80 days for production. The learning rate for the production process is 85%. How long will it take to make the units 10th through 13th? (Use Table E.3 in Module E (Learning Curves) of the textbook.) from 115 to 135 days from 175 to 195 days from 135 to 155 days from 155 to 175 days from 195 to 215 days

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT