Question

Question 4 (1 point) 1. A capital budgeting project is acceptable if the rate of return required for such a project is greate
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution :

As per the IRR Rule,

a. In case the required rate of return of a Capital budgeting project is lesser than the project’s internal rate of return, the project should be accepted.

b. In case the required rate of return of a Capital budgeting project is greater than the project’s internal rate of return, the project should not be accepted.

From the above it can be inferred that

A capital budgeting project is not acceptable if the rate of return required for such a project is greater than the project’s internal rate of return.

Thus the statement given is False

The solution is Option 2 : False

Add a comment
Know the answer?
Add Answer to:
Question 4 (1 point) 1. A capital budgeting project is acceptable if the rate of return...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. A capital budgeting project is acceptable if the rate of return required for such a...

    1. A capital budgeting project is acceptable if the rate of return required for such a project is greater than the project's internal rate of return. True False

  • The internal rate of return (IRR) is a capital budgeting project's expected return. Which of the...

    The internal rate of return (IRR) is a capital budgeting project's expected return. Which of the following statements about the IRR method is true? Because of the uncertainty connected with risky cash flows, the realized return will almost surely be different from the IRR. Decision rule for IRR: undertake the capital budgeting project only if the IRR equals r, the project's cost of capital. If the cost of capital (required return) equals the IRR (expected return), the NPV is greater...

  • 1. If the NPV from a project is positive it must be that the internal rate...

    1. If the NPV from a project is positive it must be that the internal rate of return is lower than the discount rate used. the project is not acceptable on a risk adjusted basis. this project is preferred to any other mutually exclusive project. accepting the project increases the value of the firm. 5 Question 9 (2 points) 1. Which of the following is not a rationale for using the NPV method in capital budgeting? An NPV of zero...

  • A capital budgeting technique that can be computed by solving for the discount rate that equates...

    A capital budgeting technique that can be computed by solving for the discount rate that equates the present value of a​ project's inflows to the present value of its outflows is called internal rate of return. True False

  • Which of the following statements is correct? The internal rate of return (IRR) does not allow...

    Which of the following statements is correct? The internal rate of return (IRR) does not allow you to determine whether mutually exclusive projects are acceptable. The net present value (NPV) is the only capital budgeting technique that allows you to determine which independent projects are acceptable. The net present value (NPV) technique provides an indication of the dollar benefit (on a present value basis) to the firm's shareholders of purchasing a capital budgeting project. A project's internal rate of return...

  • Ch 11: Assignment - The Basics of Capital Budgeting The internal rate of return (IRR) refers...

    Ch 11: Assignment - The Basics of Capital Budgeting The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider this case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Delta) that will require an initial investment of $1,450,000 Blue Llama Mining Company has been basing capital budgeting decisions on a project's NPV; however,...

  • 4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound...

    4. Internal rate of return (IRR) The internal rate of return (IRR) refers to the compound annual rate of return that a project generates based on its up-front cost and subsequent cash flows. Consider the case of Blue Llama Mining Company: Blue Llama Mining Company is evaluating a proposed capital budgeting project (project Sigma) that will require an initial investment of $800,000. The company has been basing capital budgeting decisions on a project's NPV; however, its new CFO wants to...

  • Question 29 (4 points) The marginal cost of capital is The minimum acceptable rate of return...

    Question 29 (4 points) The marginal cost of capital is The minimum acceptable rate of return on new investments of average risk The cost of the next dollar of new financing expected to be raised. The hurdle rate that must be met when the internal rate of return method is used All of the above Previous Page Next Page Page 29 of

  • 2. The basic process and rules for capital budgeting Aa Aa The capital budgeting process consists...

    2. The basic process and rules for capital budgeting Aa Aa The capital budgeting process consists of the following activities: I. Estimating the relevant cash flows II. Reviewing a project's post-implementation and post-termination performance III. Evaluating alternatives and selecting the projects to be implemented IV. Generating capital investment project proposals What is the correct sequence for these activities? O IV, II, III, I O I, IV, II, III There are several practical aspects of capital budgeting that complicate what appears...

  • Internal rate of return: For the project shown in the following​ table, Initial Investment $120,000 Year...

    Internal rate of return: For the project shown in the following​ table, Initial Investment $120,000 Year (t)   Cash inflows 1   $35,000 2   $40,000 3   $20,000 4   $40,000 5   $15,000 ​, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. The​ project's IRR is ___​%.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT